7703 S LA SALLE AVE 90047

Certificate Information: 7703 S LA SALLE AVE 90047

Application / Permit
20014-10000-04045
Plan Check / Job No.
B20LA17060
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
*EPLAN* Convert existing detached garage to an ADU and addition
Permit Issued
Issued on 6/9/2022
Issuing Office
Current Status
CofO Issued on 4/29/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 9/16/2020 APPLICANT
Assigned to Plan Check Engineer 10/15/2020 ARSALAN SHABESTARI
Corrections Issued 10/21/2020 ARSALAN SHABESTARI
Quality Review Completed 11/13/2020 MINYE PAK
Applicant returned to address corrections 6/29/2021 ARSALAN SHABESTARI
Applicant returned to address corrections 8/5/2021 ARSALAN SHABESTARI
Applicant returned to address corrections 9/8/2021 ARSALAN SHABESTARI
Plan Check Approved 9/22/2021 ARSALAN SHABESTARI
Issued 6/9/2022 APPLICANT
CofO in Progress 4/20/2023 ENRIQUE MIRELES
Permit Finaled 4/29/2023 DEROLD HAUFF
CofO Issued 4/29/2023 DEROLD HAUFF
Permit Finaled 4/29/2023 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 4/29/2021 JEANIE LAM
Roof/Waste drainage to street Cleared 4/29/2021 JEANIE LAM
Eng Process Fee Ord 176,300 Cleared 6/22/2021 JEANIE LAM
Sewer availability Cleared 6/22/2021 JEANIE LAM
Public Works-Open Permits Cleared 6/22/2021 JEANIE LAM
Construction near power lines Cleared 8/21/2021 RIDWAN HARDY
Construction within easement Cleared 8/21/2021 RIDWAN HARDY

Contact Information

Contractor Monroy M W Construction Inc; Lic. No.: 1066342-B 710 W 66TH ST      LOS ANGELES, CA 90044

Inspector Information

SALVADOR MARTINEZ, (213) 202-3479 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Underground Mechanical 6/14/2022 Approved ENRIQUE MIRELES
Footing/Foundation/Slab 6/22/2022 Corrections Issued ALEJANDRO DE ARTOLA
Excavation/Setback/Form/Re-Bar 6/23/2022 Corrections Issued ALEJANDRO DE ARTOLA
Footing/Foundation/Slab 6/27/2022 Corrections Issued ALEJANDRO DE ARTOLA
Floor/Roof Diaphrgm/Shear Wall 7/11/2022 Approved ENRIQUE MIRELES
BUILDING-Rough-Frame 7/21/2022 Approved ENRIQUE MIRELES
Rough-Elec/Plmb/HVAC 7/21/2022 Approved ENRIQUE MIRELES
Insulation 7/27/2022 Approved RYAN SALAZAR
Interior/Exterior Lathing 7/27/2022 Approved RYAN SALAZAR
Shower Pan 7/27/2022 Approved RYAN SALAZAR
Drywall Nailing 8/2/2022 Approved ENRIQUE MIRELES
Final 10/5/2022 Corrections Issued ENRIQUE MIRELES
Footing/Foundation/Slab 10/5/2022 Approved ENRIQUE MIRELES
SGSOV-Seismic Gas S/O Valve 10/5/2022 SGSOV Approved ENRIQUE MIRELES
Service/Power Release 10/5/2022 Approved ENRIQUE MIRELES
Smoke Detectors 10/5/2022 Approved ENRIQUE MIRELES
Final 11/2/2022 OK to Issue CofO ENRIQUE MIRELES
Service/Power Release 11/2/2022 Approved ENRIQUE MIRELES