10340 S GRAMERCY PL 90047
Certificate Information: 10340 S GRAMERCY PL 90047
- Application / Permit
- 20014-10000-04024
- Plan Check / Job No.
- B20LA17015
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- INTERIOR ALTERATIO AND ADDITION 12' X 28'10" TO REAR OF (E) SFD FOR A MASTERS BEDROOM. CONVERT 1 (E) BEDROOM INTO AN OFFICE, REMODEL 2 (E) BEDROOMS, AND REMOVE WALL IN KITCHEN AREA.
- Permit Issued
- Issued on 1/23/2021
- Issuing Office
- Current Status
- CofO Issued on 3/16/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 9/20/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 9/28/2020 | FARSHAD ALIMOHAMADI |
| Corrections Issued | 9/28/2020 | FARSHAD ALIMOHAMADI |
| Applicant returned to address corrections | 11/30/2020 | LUKE GONZALES |
| Applicant returned to address corrections | 12/22/2020 | FARSHAD ALIMOHAMADI |
| Building Plans Picked Up | 12/29/2020 | APPLICANT |
| Plan Check Approved | 1/7/2021 | FARSHAD ALIMOHAMADI |
| Issued | 1/23/2021 | APPLICANT |
| CofO in Progress | 3/13/2023 | ENRIQUE MIRELES |
| Permit Finaled | 3/16/2023 | DEROLD HAUFF |
| CofO Issued | 3/16/2023 | DEROLD HAUFF |
| Permit Finaled | 3/16/2023 | DEROLD HAUFF |
Permit Application Clearance Information
| Roof/Waste drainage to street | Cleared | 11/18/2020 | CELINA MORENO |
| Eng Process Fee Ord 176,300 | Cleared | 11/19/2020 | CELINA MORENO |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Acciani,, Mark; Lic. No.: C83929 | PO BOX 1390 RUNNING SPRINGS, CA 92382 |
Inspector Information
| SALVADOR MARTINEZ, (213) 202-3479 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 8/26/2021 | Not Ready for Inspection | FREDDIE RIVERA |
| Footing/Foundation/Slab | 8/26/2021 | Not Ready for Inspection | FREDDIE RIVERA |
| METHANE-Barrier | 8/26/2021 | Not Ready for Inspection | FREDDIE RIVERA |
| METHANE-Subgrade | 8/26/2021 | Corrections Issued | FREDDIE RIVERA |
| Footing/Foundation/Slab | 9/8/2021 | Conditional Approval | FREDDIE RIVERA |
| METHANE-Barrier | 9/8/2021 | Approved | FREDDIE RIVERA |
| METHANE-Subgrade | 9/8/2021 | Approved | FREDDIE RIVERA |
| BUILDING-Rough-Frame | 10/20/2021 | Partial Approval | FREDDIE RIVERA |
| Green Building Rough | 10/20/2021 | Not Ready for Inspection | FREDDIE RIVERA |
| METHANE-Rough | 10/20/2021 | Approved | FREDDIE RIVERA |
| PLUMBING-Rough | 10/20/2021 | Partial Approval | FREDDIE RIVERA |
| Floor/Roof Diaphrgm/Shear Wall | 10/28/2021 | Partial Approval | FREDDIE RIVERA |
| Insulation | 10/28/2021 | Partial Approval | FREDDIE RIVERA |
| ELECTRICAL-Rough | 12/6/2021 | Approved | FREDDIE RIVERA |
| Floor/Roof Diaphrgm/Shear Wall | 12/6/2021 | Approved | FREDDIE RIVERA |
| Green Building Rough | 12/6/2021 | Not Ready for Inspection | FREDDIE RIVERA |
| Insulation | 12/17/2021 | Corrections Issued | LILIANA PORTILLO |
| Shower Pan | 12/23/2021 | Corrections Issued | FREDDIE RIVERA |
| BUILDING-Rough-Frame | 1/20/2022 | Not Ready for Inspection | JOAQUIN GREENOUGH |
| Green Building Rough | 1/20/2022 | Corrections Issued | JOAQUIN GREENOUGH |
| HVAC-Rough | 1/20/2022 | Approved | JOAQUIN GREENOUGH |
| PLUMBING-Rough | 1/20/2022 | Approved | JOAQUIN GREENOUGH |
| BUILDING-Rough-Frame | 2/14/2022 | Conditional Approval | FREDDIE RIVERA |
| Floor/Roof Diaphrgm/Shear Wall | 2/14/2022 | Not Ready for Inspection | FREDDIE RIVERA |
| Green Building Rough | 2/14/2022 | Conditional Approval | FREDDIE RIVERA |
| Pre-Inspection | 2/14/2022 | Corrections Issued | FREDDIE RIVERA |
| BUILDING-Rough-Frame | 2/24/2022 | Not Ready for Inspection | FREDDIE RIVERA |
| Green Building Rough | 2/24/2022 | Not Ready for Inspection | FREDDIE RIVERA |
| Insulation | 2/24/2022 | Not Ready for Inspection | FREDDIE RIVERA |
| Interior/Exterior Lathing | 2/24/2022 | Not Ready for Inspection | FREDDIE RIVERA |
| BUILDING-Rough-Frame | 3/9/2022 | Approved | FREDDIE RIVERA |
| Green Building Rough | 3/9/2022 | Approved | FREDDIE RIVERA |
| Insulation | 3/9/2022 | Conditional Approval | FREDDIE RIVERA |
| Interior/Exterior Lathing | 3/9/2022 | Corrections Issued | FREDDIE RIVERA |
| Special/Order Compliance | 3/9/2022 | Approved | HORACE FULTZ |
| Drywall Nailing | 3/24/2022 | Approved | ENRIQUE MIRELES |
| Interior/Exterior Lathing | 3/24/2022 | Approved | ENRIQUE MIRELES |
| Final | 2/27/2023 | Corrections Issued | ENRIQUE MIRELES |
| Footing/Foundation/Slab | 2/27/2023 | Approved | ENRIQUE MIRELES |
| Green Building Final | 2/27/2023 | Approved | ENRIQUE MIRELES |
| SGSOV-Seismic Gas S/O Valve | 2/27/2023 | SGSOV Approved | ENRIQUE MIRELES |
| Smoke Detectors | 2/27/2023 | Approved | ENRIQUE MIRELES |
| Final | 3/7/2023 | OK to Issue CofO | ENRIQUE MIRELES |