10771 W CUSHDON AVE 90064
Certificate Information: 10771 W CUSHDON AVE 90064
- Application / Permit
- 20014-10000-04017
- Plan Check / Job No.
- B20LA16988
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- Second story addition to (E) detached garage and storage and conversion of second floor and a portion of first story into an Accesory Dwelling Unit. Detached ADU per ordinance.
- Permit Issued
- Issued on 7/15/2021
- Issuing Office
- Current Status
- CofO Issued on 5/11/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 9/16/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 9/17/2020 | HELEN NGUYEN |
| Corrections Issued | 9/22/2020 | HELEN NGUYEN |
| Quality Review Completed | 9/22/2020 | STANLEY RAAP |
| Applicant returned to address corrections | 12/13/2020 | HELEN NGUYEN |
| Applicant returned to address corrections | 4/8/2021 | HELEN NGUYEN |
| Applicant returned to address corrections | 5/7/2021 | HELEN NGUYEN |
| Plan Check Approved | 5/18/2021 | HELEN NGUYEN |
| Issued | 7/15/2021 | APPLICANT |
| Building Plans Picked Up | 7/16/2021 | APPLICANT |
| CofO in Progress | 5/9/2022 | EVAN COOPER |
| Permit Finaled | 5/11/2022 | DANIEL ORRANTE |
| CofO Issued | 5/11/2022 | DANIEL ORRANTE |
| Permit Finaled | 5/11/2022 | DANIEL ORRANTE |
Permit Application Clearance Information
| Specific Plan | Cleared | 10/13/2020 | DYLAN SITTIG |
| Grading Pre-Inspection | Cleared | 10/19/2020 | BRIAN MILLER |
| Specific Plan | Cleared | 11/2/2020 | VALERIA CEJA |
| Address approval | Cleared | 11/18/2020 | SAUL GARCIA |
| Eng Process Fee Ord 176,300 | Cleared | 11/18/2020 | SAUL GARCIA |
| Roof/Waste drainage to street | Cleared | 11/18/2020 | SAUL GARCIA |
| Sewer availability | Cleared | 11/18/2020 | SAUL GARCIA |
| Construction near power lines | Cleared | 1/4/2021 | RIDWAN HARDY |
| Flood clearance | Cleared | 2/18/2021 | RAYMOND LAM |
| Hydrant and Access approval | Cleared | 2/24/2021 | MATTHEW CRAIG |
| GPI Written Notices | Cleared | 4/8/2021 | HELEN NGUYEN |
Contact Information
| Contractor | Ground Up Builders And Design Inc; Lic. No.: 911849-B | 14545 VICTORY BLVD STE 601 VAN NUYS, CA 91411 |
| Engineer | Song,, Zhenyu Michael; Lic. No.: S5266 | 12631 IMPERIAL HWY F-230 SANTA FE SPRINGS, CA 90670 |
Inspector Information
| KIRK SANDERS, (310) 914-3896 | Office Hours: 7:00-8:00 AM MON-FRI |
| ARAM AVEDISIAN, (310) 914-3896 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 8/2/2021 | Partial Inspection | KEVIN SARGSYAN |
| PLUMBING-Rough | 8/12/2021 | Partial Approval | OGANES TARAKHCHYAN |
| FLOOD-Elevation Certificate | 8/19/2021 | Not Ready for Inspection | KEVIN SARGSYAN |
| FLOOD-Proofing Certificate | 8/19/2021 | Not Ready for Inspection | KEVIN SARGSYAN |
| Footing/Foundation/Slab | 8/19/2021 | Corrections Issued | KEVIN SARGSYAN |
| FLOOD-Elevation Certificate | 8/25/2021 | Corrections Issued | KEVIN SARGSYAN |
| Footing/Foundation/Slab | 8/25/2021 | Corrections Issued | KEVIN SARGSYAN |
| PLUMBING-Rough | 9/8/2021 | Corrections Issued | KEVIN SARGSYAN |
| PLUMBING-Rough | 9/10/2021 | Partial Approval | KEVIN SARGSYAN |
| FLOOD-Elevation Certificate | 10/5/2021 | Approved | EVAN COOPER |
| Footing/Foundation/Slab | 10/5/2021 | Conditional Approval | EVAN COOPER |
| Floor/Roof Diaphrgm/Shear Wall | 10/15/2021 | Partial Approval | EVAN COOPER |
| BUILDING-Rough-Frame | 11/30/2021 | Partial Approval | JOHNNY MIRANDA |
| Floor/Roof Diaphrgm/Shear Wall | 11/30/2021 | Approved | JOHNNY MIRANDA |
| BUILDING-Rough-Frame | 12/8/2021 | Corrections Issued | JOHNNY MIRANDA |
| ELECTRICAL-Rough | 12/8/2021 | Corrections Issued | JOHNNY MIRANDA |
| FLOOD-Proofing Certificate | 12/8/2021 | Partial Approval | JOHNNY MIRANDA |
| Green Building Rough | 12/8/2021 | Not Ready for Inspection | JOHNNY MIRANDA |
| HVAC-Rough | 12/8/2021 | Not Ready for Inspection | JOHNNY MIRANDA |
| PLUMBING-Rough | 12/8/2021 | Approved | JOHNNY MIRANDA |
| BUILDING-Rough-Frame | 12/20/2021 | Corrections Issued | OGANES TARAKHCHYAN |
| ELECTRICAL-Rough | 12/20/2021 | Not Ready for Inspection | OGANES TARAKHCHYAN |
| FLOOD-Proofing Certificate | 12/20/2021 | Not Ready for Inspection | OGANES TARAKHCHYAN |
| Green Building Rough | 12/20/2021 | Not Ready for Inspection | OGANES TARAKHCHYAN |
| Interior/Exterior Lathing | 12/20/2021 | Not Ready for Inspection | OGANES TARAKHCHYAN |
| BUILDING-Rough-Frame | 12/23/2021 | Approved | JOHNNY MIRANDA |
| ELECTRICAL-Rough | 12/23/2021 | Approved | JOHNNY MIRANDA |
| FLOOD-Proofing Certificate | 12/23/2021 | Approved | JOHNNY MIRANDA |
| Green Building Rough | 12/23/2021 | Approved | JOHNNY MIRANDA |
| HVAC-Rough | 12/23/2021 | Approved | JOHNNY MIRANDA |
| Interior/Exterior Lathing | 12/23/2021 | Partial Approval | JOHNNY MIRANDA |
| Insulation | 12/30/2021 | Approved | JOHNNY MIRANDA |
| Drywall Nailing | 1/7/2022 | Approved | KEVIN SARGSYAN |
| Shower Pan | 1/13/2022 | Approved | OGANES TARAKHCHYAN |
| Interior/Exterior Lathing | 1/18/2022 | Approved | DEANDRE HOFFMAN |
| Final | 3/29/2022 | Not Ready for Inspection | JOHNNY MIRANDA |
| Footing/Foundation/Slab | 3/29/2022 | Approved | JOHNNY MIRANDA |
| Green Building Final | 3/29/2022 | Not Ready for Inspection | JOHNNY MIRANDA |
| SGSOV-Seismic Gas S/O Valve | 3/29/2022 | SGSOV Approved | JOHNNY MIRANDA |
| Smoke Detectors | 3/29/2022 | Not Ready for Inspection | JOHNNY MIRANDA |
| ELECTRICAL-Final | 5/5/2022 | Approved | EVAN COOPER |
| Final | 5/5/2022 | Corrections Issued | EVAN COOPER |
| Green Building Final | 5/5/2022 | Approved | EVAN COOPER |
| HVAC-Final | 5/5/2022 | Approved | EVAN COOPER |
| PLUMBING-Final | 5/5/2022 | Approved | EVAN COOPER |
| Smoke Detectors | 5/5/2022 | Approved | EVAN COOPER |
| Final | 5/6/2022 | OK to Issue CofO | EVAN COOPER |