843 W VENEZIA AVE 90291
Certificate Information: 843 W VENEZIA AVE 90291
- Application / Permit
- 20014-10000-04004
- Plan Check / Job No.
- B20LA16925
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- Convert (E) two-car garage to Accessory Dwelling Unit and add 2nd floor, creating a two-story ADU.
- Permit Issued
- Issued on 9/16/2022
- Issuing Office
- Current Status
- CofO Issued on 10/7/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 9/15/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 10/8/2020 | JOE VO |
| Corrections Issued | 10/10/2020 | JOE VO |
| Quality Review Completed | 10/21/2020 | MINYE PAK |
| Plan Check Approved | 9/6/2022 | JOE VO |
| Issued | 9/16/2022 | APPLICANT |
| CofO in Progress | 10/4/2023 | HERBERT GIRON |
| Permit Finaled | 10/7/2023 | DANIEL ORRANTE |
| CofO Issued | 10/7/2023 | DANIEL ORRANTE |
| Permit Finaled | 10/7/2023 | DANIEL ORRANTE |
Permit Application Clearance Information
| Specific Plan | Cleared | 11/2/2020 | PEDRO AYALA |
| Address approval | Cleared | 11/4/2020 | DINAH GARIN |
| Sewer availability | Cleared | 11/4/2020 | DINAH GARIN |
| Eng Process Fee Ord 176,300 | Cleared | 11/5/2020 | DINAH GARIN |
| Low Impact Development | Cleared | 6/8/2021 | SUNG JOON WON |
| Coastal Zone | Cleared | 6/17/2022 | ANACANY HURTADO |
| Specific Plan | Cleared | 6/17/2022 | ANACANY HURTADO |
| Roof/Waste drainage to street | Cleared | 6/21/2022 | ANTHONY MAINEZ |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Garcia,, Francisco Diaz; Lic. No.: C88029 | 19145 MALABAR ST SANTA CLARITA, CA 91351 |
Inspector Information
| RUBEN RIVAS, (310) 914-3981 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 12/1/2022 | Partial Approval | DAVID FEILER |
| Deputy Drilled-In Anchors | 12/7/2022 | Conditional Approval | EVAN COOPER |
| Deputy Drilled-In Anchors | 12/8/2022 | Conditional Approval | EVAN COOPER |
| Footing/Foundation/Slab | 12/9/2022 | Corrections Issued | EVAN COOPER |
| BUILDING-Rough-Frame | 1/12/2023 | Corrections Issued | EVAN COOPER |
| Floor/Roof Diaphrgm/Shear Wall | 1/12/2023 | Partial Approval | EVAN COOPER |
| BUILDING-Rough-Frame | 1/13/2023 | Not Ready for Inspection | EVAN COOPER |
| Green Building Rough | 1/13/2023 | Not Ready for Inspection | EVAN COOPER |
| Floor/Roof Diaphrgm/Shear Wall | 2/3/2023 | Partial Approval | EVAN COOPER |
| PLUMBING-Rough | 3/1/2023 | Conditional Approval | EVAN COOPER |
| Shower Pan | 3/6/2023 | Approved | HERBERT GIRON |
| ELECTRICAL-Rough | 3/20/2023 | Approved | EVAN COOPER |
| PLUMBING-Rough | 3/20/2023 | Approved | EVAN COOPER |
| Insulation | 4/18/2023 | Not Ready for Inspection | EVAN COOPER |
| BUILDING-Rough-Frame | 5/16/2023 | Approved | EVAN COOPER |
| Green Building Rough | 5/16/2023 | Approved | EVAN COOPER |
| HVAC-Rough | 5/16/2023 | Approved | EVAN COOPER |
| Insulation | 5/16/2023 | Approved | EVAN COOPER |
| Interior/Exterior Lathing | 5/16/2023 | Approved | EVAN COOPER |
| Drywall Nailing | 5/24/2023 | Approved | HERBERT GIRON |
| Footing/Foundation/Slab | 8/24/2023 | Approved | HERBERT GIRON |
| Green Building Final | 8/24/2023 | Approved | HERBERT GIRON |
| HVAC-Final | 8/24/2023 | Corrections Issued | HERBERT GIRON |
| PLUMBING-Final | 8/24/2023 | Corrections Issued | HERBERT GIRON |
| SGSOV-Seismic Gas S/O Valve | 8/24/2023 | SGSOV Not Ready | HERBERT GIRON |
| Smoke Detectors | 8/24/2023 | Approved | HERBERT GIRON |
| ELECTRICAL-Final | 8/29/2023 | Corrections Issued | HERBERT GIRON |
| Gas Test | 8/29/2023 | Approved | HERBERT GIRON |
| HVAC-Final | 8/29/2023 | Corrections Issued | HERBERT GIRON |
| PLUMBING-Final | 8/29/2023 | Approved | HERBERT GIRON |
| ELECTRICAL-Final | 8/31/2023 | Approved | HERBERT GIRON |
| Final | 8/31/2023 | Corrections Issued | HERBERT GIRON |
| HVAC-Final | 8/31/2023 | Approved | HERBERT GIRON |
| SGSOV-Seismic Gas S/O Valve | 8/31/2023 | SGSOV Approved | HERBERT GIRON |
| Final | 9/7/2023 | Corrections Issued | HERBERT GIRON |
| Final | 9/18/2023 | Not Ready for Inspection | HERBERT GIRON |
| Final | 10/3/2023 | OK to Issue CofO | HERBERT GIRON |
| Service/Power Release | 10/3/2023 | Approved | HERBERT GIRON |