843 W VENEZIA AVE 90291

Certificate Information: 843 W VENEZIA AVE 90291

Application / Permit
20014-10000-04004
Plan Check / Job No.
B20LA16925
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
Convert (E) two-car garage to Accessory Dwelling Unit and add 2nd floor, creating a two-story ADU.
Permit Issued
Issued on 9/16/2022
Issuing Office
Current Status
CofO Issued on 10/7/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 9/15/2020 APPLICANT
Assigned to Plan Check Engineer 10/8/2020 JOE VO
Corrections Issued 10/10/2020 JOE VO
Quality Review Completed 10/21/2020 MINYE PAK
Plan Check Approved 9/6/2022 JOE VO
Issued 9/16/2022 APPLICANT
CofO in Progress 10/4/2023 HERBERT GIRON
Permit Finaled 10/7/2023 DANIEL ORRANTE
CofO Issued 10/7/2023 DANIEL ORRANTE
Permit Finaled 10/7/2023 DANIEL ORRANTE

Permit Application Clearance Information

Specific Plan Cleared 11/2/2020 PEDRO AYALA
Address approval Cleared 11/4/2020 DINAH GARIN
Sewer availability Cleared 11/4/2020 DINAH GARIN
Eng Process Fee Ord 176,300 Cleared 11/5/2020 DINAH GARIN
Low Impact Development Cleared 6/8/2021 SUNG JOON WON
Coastal Zone Cleared 6/17/2022 ANACANY HURTADO
Specific Plan Cleared 6/17/2022 ANACANY HURTADO
Roof/Waste drainage to street Cleared 6/21/2022 ANTHONY MAINEZ

Contact Information

Contractor Owner-Builder       ,
Engineer Garcia,, Francisco Diaz; Lic. No.: C88029 19145 MALABAR ST      SANTA CLARITA, CA 91351

Inspector Information

RUBEN RIVAS, (310) 914-3981 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 12/1/2022 Partial Approval DAVID FEILER
Deputy Drilled-In Anchors 12/7/2022 Conditional Approval EVAN COOPER
Deputy Drilled-In Anchors 12/8/2022 Conditional Approval EVAN COOPER
Footing/Foundation/Slab 12/9/2022 Corrections Issued EVAN COOPER
BUILDING-Rough-Frame 1/12/2023 Corrections Issued EVAN COOPER
Floor/Roof Diaphrgm/Shear Wall 1/12/2023 Partial Approval EVAN COOPER
BUILDING-Rough-Frame 1/13/2023 Not Ready for Inspection EVAN COOPER
Green Building Rough 1/13/2023 Not Ready for Inspection EVAN COOPER
Floor/Roof Diaphrgm/Shear Wall 2/3/2023 Partial Approval EVAN COOPER
PLUMBING-Rough 3/1/2023 Conditional Approval EVAN COOPER
Shower Pan 3/6/2023 Approved HERBERT GIRON
ELECTRICAL-Rough 3/20/2023 Approved EVAN COOPER
PLUMBING-Rough 3/20/2023 Approved EVAN COOPER
Insulation 4/18/2023 Not Ready for Inspection EVAN COOPER
BUILDING-Rough-Frame 5/16/2023 Approved EVAN COOPER
Green Building Rough 5/16/2023 Approved EVAN COOPER
HVAC-Rough 5/16/2023 Approved EVAN COOPER
Insulation 5/16/2023 Approved EVAN COOPER
Interior/Exterior Lathing 5/16/2023 Approved EVAN COOPER
Drywall Nailing 5/24/2023 Approved HERBERT GIRON
Footing/Foundation/Slab 8/24/2023 Approved HERBERT GIRON
Green Building Final 8/24/2023 Approved HERBERT GIRON
HVAC-Final 8/24/2023 Corrections Issued HERBERT GIRON
PLUMBING-Final 8/24/2023 Corrections Issued HERBERT GIRON
SGSOV-Seismic Gas S/O Valve 8/24/2023 SGSOV Not Ready HERBERT GIRON
Smoke Detectors 8/24/2023 Approved HERBERT GIRON
ELECTRICAL-Final 8/29/2023 Corrections Issued HERBERT GIRON
Gas Test 8/29/2023 Approved HERBERT GIRON
HVAC-Final 8/29/2023 Corrections Issued HERBERT GIRON
PLUMBING-Final 8/29/2023 Approved HERBERT GIRON
ELECTRICAL-Final 8/31/2023 Approved HERBERT GIRON
Final 8/31/2023 Corrections Issued HERBERT GIRON
HVAC-Final 8/31/2023 Approved HERBERT GIRON
SGSOV-Seismic Gas S/O Valve 8/31/2023 SGSOV Approved HERBERT GIRON
Final 9/7/2023 Corrections Issued HERBERT GIRON
Final 9/18/2023 Not Ready for Inspection HERBERT GIRON
Final 10/3/2023 OK to Issue CofO HERBERT GIRON
Service/Power Release 10/3/2023 Approved HERBERT GIRON