7637 N CAMELLIA AVE 91605
Certificate Information: 7637 N CAMELLIA AVE 91605
- Application / Permit
- 20014-10000-03998
- Plan Check / Job No.
- B20LA16875
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- *ePLAN CHECK* ADDITION TO (E) GARAGE & STORAGE FOR (N) ACCESSORY DWELLING UNIT PER LAMC 12.22A33 (c) & (d). ALL WORK PER IB/P/BC 2020-004 WOOD FRAME PRESCRIPTIVE PROVISIONS
- Permit Issued
- Issued on 4/23/2022
- Issuing Office
- Current Status
- CofO Issued on 1/14/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 9/16/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 10/15/2020 | LAMAR DAVIS |
| Corrections Issued | 10/19/2020 | LAMAR DAVIS |
| Quality Review Completed | 11/22/2020 | TU HUA |
| Applicant returned to address corrections | 8/3/2021 | LAMAR DAVIS |
| Applicant returned to address corrections | 8/20/2021 | LAMAR DAVIS |
| Applicant returned to address corrections | 2/2/2022 | LAMAR DAVIS |
| Plan Check Approved | 4/20/2022 | LAMAR DAVIS |
| Issued | 4/23/2022 | APPLICANT |
| CofO in Progress | 12/27/2022 | MATTHEW NELSON |
| CofO Issued | 1/14/2023 | MICHAEL SMITH |
| Permit Finaled | 1/14/2023 | MICHAEL SMITH |
Permit Application Clearance Information
| Address approval | Cleared | 1/6/2021 | GABRIEL ROBLES |
| Sewer availability | Cleared | 1/7/2021 | GABRIEL ROBLES |
| Low Impact Development | Cleared | 7/16/2021 | ORVAL HERNANDEZ-MARCI |
| Hydrant and Access approval | Cleared | 10/22/2021 | GILBERT URREA |
| Eng Process Fee Ord 176,300 | Cleared | 2/2/2022 | ABDULLAH SADOZAI |
| Roof/Waste drainage to street | Cleared | 2/28/2022 | AMIR KASHFI |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| WILLIAM WREN, (818) 374-1170 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 6/27/2022 | No Result Entered | ADRIAN GAUTHIER |
| Footing/Foundation/Slab | 6/29/2022 | Approved | CHRISTOPHER DELLEFIELD |
| PLUMBING-Rough | 6/29/2022 | Partial Approval | CHRISTOPHER DELLEFIELD |
| Floor/Roof Diaphrgm/Shear Wall | 7/8/2022 | Corrections Issued | CHRISTOPHER DELLEFIELD |
| ELECTRICAL-Rough | 9/2/2022 | Conditional Approval | CHRISTOPHER DELLEFIELD |
| Floor/Roof Diaphrgm/Shear Wall | 9/2/2022 | Approved | CHRISTOPHER DELLEFIELD |
| PLUMBING-Rough | 9/2/2022 | Approved | CHRISTOPHER DELLEFIELD |
| Underground Mechanical | 9/2/2022 | Approved | CHRISTOPHER DELLEFIELD |
| BUILDING-Rough-Frame | 9/9/2022 | Conditional Approval | CHRISTOPHER DELLEFIELD |
| HVAC-Rough | 9/9/2022 | Corrections Issued | CHRISTOPHER DELLEFIELD |
| Insulation | 9/9/2022 | Partial Approval | CHRISTOPHER DELLEFIELD |
| Insulation | 9/16/2022 | Approved | WILLIAM WREN |
| Interior/Exterior Lathing | 9/16/2022 | Conditional Approval | WILLIAM WREN |
| BUILDING-Rough-Frame | 9/21/2022 | Approved | CHRISTOPHER DELLEFIELD |
| Drywall Nailing | 9/21/2022 | Approved | CHRISTOPHER DELLEFIELD |
| Green Building Rough | 9/21/2022 | Approved | CHRISTOPHER DELLEFIELD |
| HVAC-Rough | 9/21/2022 | Approved | CHRISTOPHER DELLEFIELD |
| Interior/Exterior Lathing | 9/21/2022 | Approved | CHRISTOPHER DELLEFIELD |
| Interior/Exterior Lathing | 9/29/2022 | Approved | MICHEL ABAJAN |
| Final | 12/2/2022 | Corrections Issued | MATTHEW NELSON |
| Green Building Final | 12/2/2022 | Approved | MATTHEW NELSON |
| SGSOV-Seismic Gas S/O Valve | 12/2/2022 | SGSOV Approved | MATTHEW NELSON |
| Smoke Detectors | 12/2/2022 | Approved | MATTHEW NELSON |
| Final | 12/20/2022 | Corrections Issued | MATTHEW NELSON |
| ELECTRICAL-Final | 12/27/2022 | Approved | MATTHEW NELSON |
| Final | 12/27/2022 | OK to Issue CofO | MATTHEW NELSON |
| HVAC-Final | 12/27/2022 | Approved | MATTHEW NELSON |
| PLUMBING-Final | 12/27/2022 | Approved | MATTHEW NELSON |