5128 E RAPHAEL ST 90042

Certificate Information: 5128 E RAPHAEL ST 90042

Application / Permit
20014-10000-03997
Plan Check / Job No.
B20LA16865
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
ePlan CONVERT EXISTING TOOL SHED AND PROPOSED (11.5' X 15.5') ADDITION TO CREATE AN ACCESSORY DWELLING UNIT PER ORDINANCE.
Permit Issued
Issued on 2/22/2021
Issuing Office
Current Status
CofO Issued on 12/5/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 9/17/2020 APPLICANT
Assigned to Plan Check Engineer 10/15/2020 MICHAEL LOPEZ
Corrections Issued 10/22/2020 MICHAEL LOPEZ
Quality Review Completed 11/18/2020 TU HUA
Plan Check Approved 1/7/2021 MICHAEL LOPEZ
No Progress 2/11/2021 MICHAEL LOPEZ
Plan Check Approved 2/19/2021 MICHAEL LOPEZ
Issued 2/22/2021 APPLICANT
CofO in Progress 11/29/2022 HAMIK HARTOUNIAN
CofO Issued 12/5/2022 DEROLD HAUFF
Permit Finaled 12/5/2022 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 12/4/2020 CECILIO NAVARRO
BHO/Hillside ordinance Cleared 12/4/2020 CECILIO NAVARRO
BHO/Hillside ordinance Cleared 12/4/2020 CECILIO NAVARRO
BHO/Hillside ordinance Cleared 12/4/2020 CECILIO NAVARRO
BHO/Hillside ordinance Cleared 12/4/2020 CECILIO NAVARRO
BHO/Hillside ordinance Cleared 12/4/2020 CECILIO NAVARRO
Roof/Waste drainage to street Cleared 12/4/2020 CECILIO NAVARRO
Eng Process Fee Ord 176,300 Cleared 12/8/2020 CECILIO NAVARRO
Sewer availability Cleared 12/8/2020 CECILIO NAVARRO
Grading Pre-Inspection Cleared 12/15/2020 MANUEL TEJADA

Contact Information

Contractor Owner-Builder       ,
Engineer Pinzon,, Eduardo A; Lic. No.: C74869 821 W SPRUCE ST      WEST COVINA, CA 91790

Inspector Information

NICHOLAS LOPEZ, (213) 202-3224 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Reinf. Concrete 5/6/2021 Conditional Approval HAMIK HARTOUNIAN
Excavation/Setback/Form/Re-Bar 5/7/2021 Corrections Issued HAMIK HARTOUNIAN
Pre-Inspection 5/7/2021 Approved HAMIK HARTOUNIAN
Excavation/Setback/Form/Re-Bar 5/20/2021 Not Ready for Inspection HAMIK HARTOUNIAN
Excavation/Setback/Form/Re-Bar 6/4/2021 Approved HAMIK HARTOUNIAN
Deputy Wood Construction 9/21/2021 Conditional Approval HAMIK HARTOUNIAN
ELECTRICAL-Rough 9/22/2021 Partial Approval HAMIK HARTOUNIAN
Floor/Roof Diaphrgm/Shear Wall 9/22/2021 Corrections Issued HAMIK HARTOUNIAN
PLUMBING-Rough 9/22/2021 Corrections Issued HAMIK HARTOUNIAN
Floor/Roof Diaphrgm/Shear Wall 10/1/2021 Not Ready for Inspection HAMIK HARTOUNIAN
Insulation 10/1/2021 Not Ready for Inspection HAMIK HARTOUNIAN
PLUMBING-Rough 10/1/2021 Approved HAMIK HARTOUNIAN
Underground Mechanical 10/1/2021 Partial Approval HAMIK HARTOUNIAN
Excavation/Setback/Form/Re-Bar 10/5/2021 Conditional Approval HAMIK HARTOUNIAN
Floor/Roof Diaphrgm/Shear Wall 1/13/2022 Conditional Approval FREDDIE RIVERA
Insulation 1/13/2022 Not Ready for Inspection FREDDIE RIVERA
ELECTRICAL-Rough 1/24/2022 Corrections Issued HAMIK HARTOUNIAN
Insulation 1/24/2022 Not Ready for Inspection HAMIK HARTOUNIAN
Interior/Exterior Lathing 1/24/2022 Approved HAMIK HARTOUNIAN
Wood Frame 1/24/2022 Not Ready for Inspection HAMIK HARTOUNIAN
ELECTRICAL-Rough 1/27/2022 Approved HAMIK HARTOUNIAN
HVAC-Rough 1/27/2022 Approved HAMIK HARTOUNIAN
Insulation 1/27/2022 Corrections Issued HAMIK HARTOUNIAN
Wood Frame 1/27/2022 Approved HAMIK HARTOUNIAN
Insulation 2/1/2022 Approved HAMIK HARTOUNIAN
Drywall Nailing 2/16/2022 Approved HAMIK HARTOUNIAN
Interior/Exterior Lathing 3/8/2022 Approved CHARLES BOGHOSKHAN
Underground Mechanical 4/7/2022 Approved HAMIK HARTOUNIAN
Final 9/26/2022 Corrections Issued HAMIK HARTOUNIAN
Green Building Final 9/26/2022 Corrections Issued HAMIK HARTOUNIAN
Smoke Detectors 9/26/2022 Approved HAMIK HARTOUNIAN
Final 11/2/2022 Corrections Issued HAMIK HARTOUNIAN
BUILDING-Rough-Frame 11/29/2022 Approved HAMIK HARTOUNIAN
Final 11/29/2022 OK to Issue CofO HAMIK HARTOUNIAN
Footing/Foundation/Slab 11/29/2022 Approved HAMIK HARTOUNIAN
Green Building Final 11/29/2022 Approved HAMIK HARTOUNIAN
Green Building Rough 11/29/2022 Approved HAMIK HARTOUNIAN
SGSOV-Seismic Gas S/O Valve 11/29/2022 SGSOV Approved HAMIK HARTOUNIAN