513 S MORENO AVE 90049
Certificate Information: 513 S MORENO AVE 90049
- Application / Permit
- 20014-10000-03983
- Plan Check / Job No.
- B20LA16818
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- ADDITION AND REMODEL OF EXISTING 1 STORY SFD
- Permit Issued
- Issued on 11/9/2021
- Issuing Office
- Metro
- Current Status
- CofO Issued on 3/14/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 9/23/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 10/22/2020 | STARR CHEN |
| Corrections Issued | 10/24/2020 | STARR CHEN |
| Quality Review Completed | 6/24/2021 | JASON HEALEY |
| Applicant returned to address corrections | 6/24/2021 | STARR CHEN |
| Applicant returned to address corrections | 7/1/2021 | STARR CHEN |
| Applicant returned to address corrections | 7/15/2021 | STARR CHEN |
| Applicant returned to address corrections | 9/9/2021 | STARR CHEN |
| Plan Check Approved | 9/17/2021 | STARR CHEN |
| Issued | 11/9/2021 | APPLICANT |
| Building Plans Picked Up | 11/10/2021 | APPLICANT |
| CofO in Progress | 3/13/2026 | MICHAEL ALLEN |
| Permit Finaled | 3/14/2026 | RICHARD STEINBACH |
| Permit Finaled | 3/14/2026 | RICHARD STEINBACH |
| CofO Issued | 3/14/2026 | RICHARD STEINBACH |
Permit Application Clearance Information
| Specific Plan | Cleared | 4/12/2021 | KEVIN ARUCAN |
| Permit | Cleared | 4/28/2021 | DINAH GARIN |
| Sewer availability | Cleared | 4/28/2021 | DINAH GARIN |
| Eng Process Fee Ord 176,300 | Cleared | 4/29/2021 | DINAH GARIN |
| Low Impact Development | Cleared | 7/29/2021 | SARAH YOUSSEF |
| Roof/Waste drainage to street | Cleared | 7/29/2021 | DINAH GARIN |
Contact Information
| Architect | Newbern,, Walter Pedro; Lic. No.: C22914 | 1010 NO. MADISON AVENUE PASADENA, CA 91104 |
| Contractor | R G Remodel; Lic. No.: 1074569-B | 11971 DEBBIE LN GARDEN GROVE, CA 92840 |
| Engineer | Dejban,, Masoud; Lic. No.: S2521 | 17200 VENTURA BLVD STE 213A ENCINO, CA 91316 |
Inspector Information
| ANTHONY EGSON, (310) 914-3893 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 3/15/2022 | Corrections Issued | OGANES TARAKHCHYAN |
| Underground Mechanical | 3/22/2022 | Partial Approval | OGANES TARAKHCHYAN |
| Excavation/Setback/Form/Re-Bar | 5/9/2022 | Approved | OGANES TARAKHCHYAN |
| Deputy Wood Construction | 7/7/2022 | Partial Approval | OGANES TARAKHCHYAN |
| BUILDING-Rough-Frame | 7/20/2022 | Partial Approval | JOHN KIDWELL |
| Floor/Roof Diaphrgm/Shear Wall | 7/20/2022 | Approved | JOHN KIDWELL |
| Green Building Rough | 7/20/2022 | Partial Approval | JOHN KIDWELL |
| PLUMBING-Rough | 10/4/2022 | Approved | ASHLEY THOMPSON |
| Special/Order Compliance | 10/4/2022 | Corrections Issued | ASHLEY THOMPSON |
| Drywall Nailing | 11/16/2022 | Partial Approval | ASHLEY THOMPSON |
| ELECTRICAL-Rough | 1/25/2023 | Corrections Issued | JULIAN AMAYA |
| ELECTRICAL-Rough | 5/10/2023 | Approved | HERBERT GIRON |
| Interior/Exterior Lathing | 5/30/2023 | Partial Approval | JESUS PINEDA |
| HVAC-Rough | 6/9/2023 | Approved | JESUS PINEDA |
| BUILDING-Rough-Frame | 7/13/2023 | Approved | JEREMY TODD |
| Green Building Rough | 7/13/2023 | Approved | JEREMY TODD |
| Wood Frame | 7/13/2023 | Approved | JEREMY TODD |
| Insulation | 7/17/2023 | Corrections Issued | DAVID FEILER |
| Interior/Exterior Lathing | 7/18/2023 | Partial Approval | DAVID FEILER |
| Verify Sprinkler Sign Off | 7/18/2023 | Approved | DAVID FEILER |
| Insulation | 7/24/2023 | Approved | JEREMY TODD |
| Interior/Exterior Lathing | 7/24/2023 | Approved | JEREMY TODD |
| Sewer | 7/27/2023 | Approved | CARLOS MATAMOROS |
| Drywall Nailing | 8/9/2023 | Approved | MEL KHACHATOURIAN |
| Shower Pan | 11/27/2023 | Corrections Issued | BEN MOLSTAD |
| Shower Pan | 12/6/2023 | Approved | BEN MOLSTAD |
| Interior/Exterior Lathing | 12/15/2023 | Approved | BEN MOLSTAD |
| Gas Test | 2/26/2024 | Partial Approval | ARAM AVEDISIAN |
| PLUMBING-Final | 3/4/2025 | Not Ready for Inspection | KIRK SANDERS |
| PLUMBING-Final | 4/1/2025 | Corrections Issued | KIRK SANDERS |
| Special/Order Compliance | 4/1/2025 | Corrections Issued | KIRK SANDERS |
| ELECTRICAL-Final | 6/23/2025 | Corrections Issued | KIRK SANDERS |
| PLUMBING-Final | 7/1/2025 | Corrections Issued | KIRK SANDERS |
| ELECTRICAL-Final | 7/17/2025 | Not Ready for Inspection | KEVIN SARGSYAN |
| ELECTRICAL-Final | 7/18/2025 | Corrections Issued | MEL KHACHATOURIAN |
| PLUMBING-Final | 7/30/2025 | Corrections Issued | ARAM AVEDISIAN |
| ELECTRICAL-Final | 8/5/2025 | Approved | TEMISTOCLES CAAL |
| Final | 8/5/2025 | Corrections Issued | TEMISTOCLES CAAL |
| PLUMBING-Final | 8/8/2025 | Partial Approval | HERBERT GIRON |
| Final | 8/26/2025 | Corrections Issued | CARLOS MATAMOROS |
| Footing/Foundation/Slab | 8/26/2025 | Approved | CARLOS MATAMOROS |
| SGSOV-Seismic Gas S/O Valve | 8/26/2025 | SGSOV Not Ready | CARLOS MATAMOROS |
| Final | 2/3/2026 | Corrections Issued | MICHAEL ALLEN |
| SGSOV-Seismic Gas S/O Valve | 2/3/2026 | SGSOV Not Ready | MICHAEL ALLEN |
| Final | 2/12/2026 | Corrections Issued | ASHLEY THOMPSON |
| Green Building Final | 2/12/2026 | Approved | ASHLEY THOMPSON |
| HVAC-Final | 2/12/2026 | Corrections Issued | ASHLEY THOMPSON |
| SGSOV-Seismic Gas S/O Valve | 2/12/2026 | SGSOV Not Ready | ASHLEY THOMPSON |
| Smoke Detectors | 2/12/2026 | Approved | ASHLEY THOMPSON |
| PLUMBING-Final | 2/18/2026 | Conditional Approval | MICHAEL ALLEN |
| HVAC-Final | 2/19/2026 | Corrections Issued | MICHAEL ALLEN |
| Final | 3/2/2026 | Not Ready for Inspection | RYAN SALAZAR |
| SGSOV-Seismic Gas S/O Valve | 3/2/2026 | SGSOV Not Ready | RYAN SALAZAR |
| Final | 3/5/2026 | Corrections Issued | MICHAEL ALLEN |
| HVAC-Final | 3/5/2026 | Approved | MICHAEL ALLEN |
| Final | 3/10/2026 | OK to Issue CofO | MICHAEL ALLEN |
| PLUMBING-Final | 3/10/2026 | Approved | MICHAEL ALLEN |
| SGSOV-Seismic Gas S/O Valve | 3/10/2026 | SGSOV Approved | MICHAEL ALLEN |