6932 N ALCOVE AVE 91605

Certificate Information: 6932 N ALCOVE AVE 91605

Application / Permit
20014-10000-03962
Plan Check / Job No.
B20LA16676
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
ADDITION WITH EXTERIOR PERGOLA. REMODEL (E) HALL BATH AND CLOSETS IN BEDROOMS. FLOORING, FIXTURES, WINDOWS AND DOORS. REPAIR ROOF
Permit Issued
Issued on 2/18/2021
Issuing Office
Current Status
CofO Issued on 2/5/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 9/11/2020 APPLICANT
Assigned to Plan Check Engineer 9/18/2020 SINA KHOSRAVI
Corrections Issued 9/20/2020 SINA KHOSRAVI
Applicant returned to address corrections 12/1/2020 RICARDO RAMIREZ
Plan Check Approved 12/10/2020 RICARDO RAMIREZ
Building Plans Picked Up 12/11/2020 APPLICANT
Issued 2/18/2021 APPLICANT
CofO in Progress 1/18/2022 JACK KARGODORIAN
Permit Finaled 2/5/2022 MICHAEL SMITH
CofO Issued 2/5/2022 MICHAEL SMITH
Permit Finaled 2/5/2022 MICHAEL SMITH

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 11/18/2020 GABRIEL ROBLES
Roof/Waste drainage to street Cleared 11/18/2020 GABRIEL ROBLES

Contact Information

Engineer Garcia,, Francisco Javier; Lic. No.: C76510 2705 S FREMONT AVE APT D      ALHAMBRA, CA 91803

Inspector Information

WAYNE REGESTER, (818) 374-1164 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 3/16/2021 No Result Entered GREG ALLTON
Footing/Foundation/Slab 3/22/2021 Corrections Issued THOMAS FINNILA
Footing/Foundation/Slab 3/31/2021 Approved RICHARD DOCKUS
Insulation 4/14/2021 Partial Approval RICHARD DOCKUS
Deputy Wood Construction 5/20/2021 Approved JAVIER RAMOS JR
BUILDING-Rough-Frame 5/25/2021 Corrections Issued RICHARD DOCKUS
Green Building Rough 5/25/2021 Approved RICHARD DOCKUS
Rough-Elec/Plmb/HVAC 5/25/2021 Approved RICHARD DOCKUS
Floor/Roof Diaphrgm/Shear Wall 5/26/2021 Approved RICHARD DOCKUS
BUILDING-Rough-Frame 6/3/2021 Approved RICHARD DOCKUS
Insulation 6/3/2021 Approved RICHARD DOCKUS
Interior/Exterior Lathing 6/3/2021 Partial Approval RICHARD DOCKUS
Shower Pan 6/3/2021 Approved RICHARD DOCKUS
Drywall Nailing 6/14/2021 Approved MORRIS JACKSON
Rough-Elec/Plmb/HVAC 10/12/2021 Approved CALEB MEISTER
Insulation 10/14/2021 Approved CHRISTOPHE COCHRAN
Drywall Nailing 10/25/2021 Approved CHRISTOPHE COCHRAN
Shower Pan 10/25/2021 Approved CHRISTOPHE COCHRAN
Final 1/18/2022 OK to Issue CofO JACK KARGODORIAN
Green Building Final 1/18/2022 Approved JACK KARGODORIAN
SGSOV-Seismic Gas S/O Valve 1/18/2022 SGSOV Approved JACK KARGODORIAN
Smoke Detectors 1/18/2022 Approved JACK KARGODORIAN