8129 1/2 W 4TH ST 90048

Certificate Information: 8129 1/2 W 4TH ST 90048

Application / Permit
20014-10000-03951
Plan Check / Job No.
B20LA16608
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
*ePLAN CHECK* CONVERSION & ADDITION OF (E) GARAGE TO (N) ACCESSORY DWELLING UNIT PER LAMC 12.22A33 (c) & (d). ALL WORK PER IB/P/BC 2020-004 WOOD FRAME PRESCRIPTIVE PROVISIONS
Permit Issued
Issued on 2/25/2021
Issuing Office
Current Status
CofO Issued on 9/29/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 9/11/2020 APPLICANT
Assigned to Plan Check Engineer 10/8/2020 LAMAR DAVIS
Corrections Issued 10/14/2020 LAMAR DAVIS
Quality Review Completed 10/15/2020 TU HUA
Applicant returned to address corrections 11/5/2020 LAMAR DAVIS
Applicant returned to address corrections 11/25/2020 LAMAR DAVIS
Applicant returned to address corrections 12/9/2020 LAMAR DAVIS
Applicant returned to address corrections 1/27/2021 LAMAR DAVIS
Plan Check Approved 2/24/2021 LAMAR DAVIS
Issued 2/25/2021 APPLICANT
CofO in Progress 9/13/2021 EVAN COOPER
Permit Finaled 9/29/2021 KENNETH NAGLE
CofO Issued 9/29/2021 KENNETH NAGLE
Permit Finaled 9/29/2021 KENNETH NAGLE

Permit Application Clearance Information

Address approval Cleared 10/23/2020 WALLIE JONG
Eng Process Fee Ord 176,300 Cleared 10/23/2020 WALLIE JONG
Sewer availability Cleared 10/23/2020 WALLIE JONG
Construction near power lines Cleared 11/13/2020 RIDWAN HARDY
Construction within easement Cleared 11/13/2020 RIDWAN HARDY
Low Impact Development Cleared 2/5/2021 MARTIN FRAGOSO
Roof/Waste drainage to street Cleared 2/18/2021 WALLIE JONG

Contact Information

Contractor Owner-Builder       ,

Inspector Information

WILBER ROSALES, (310) 914-3892 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 3/2/2021 Corrections Issued EVAN COOPER
METHANE-Rough 3/22/2021 Partial Approval EVAN COOPER
PLUMBING-Rough 3/22/2021 Partial Approval EVAN COOPER
Excavation/Setback/Form/Re-Bar 3/26/2021 Conditional Approval EVAN COOPER
Footing/Foundation/Slab 4/21/2021 Corrections Issued EVAN COOPER
PLUMBING-Rough 4/21/2021 Approved EVAN COOPER
BUILDING-Rough-Frame 4/27/2021 Not Ready for Inspection EVAN COOPER
ELECTRICAL-Rough 4/27/2021 Not Ready for Inspection EVAN COOPER
Green Building Rough 4/27/2021 Not Ready for Inspection EVAN COOPER
HVAC-Rough 4/27/2021 Not Ready for Inspection EVAN COOPER
METHANE-Rough 4/27/2021 Not Ready for Inspection EVAN COOPER
BUILDING-Rough-Frame 4/30/2021 Corrections Issued EVAN COOPER
Green Building Rough 4/30/2021 Not Ready for Inspection EVAN COOPER
METHANE-Rough 4/30/2021 Not Ready for Inspection EVAN COOPER
BUILDING-Rough-Frame 5/4/2021 Partial Approval EVAN COOPER
Green Building Rough 5/4/2021 Not Ready for Inspection EVAN COOPER
METHANE-Rough 5/4/2021 Approved EVAN COOPER
Interior/Exterior Lathing 5/10/2021 Corrections Issued WILLIAM MICHALAK
Insulation 5/12/2021 Approved EVAN COOPER
Drywall Nailing 5/17/2021 Approved EVAN COOPER
Green Building Rough 5/17/2021 Approved EVAN COOPER
HVAC-Rough 6/24/2021 No Access for Inspection EVAN COOPER
Insulation 6/24/2021 No Access for Inspection EVAN COOPER
ELECTRICAL-Final 7/8/2021 Approved EVAN COOPER
Final 7/8/2021 Corrections Issued EVAN COOPER
Gas Test 7/8/2021 Approved EVAN COOPER
HVAC-Final 7/8/2021 Approved EVAN COOPER
PLUMBING-Final 7/8/2021 Approved EVAN COOPER
SGSOV-Seismic Gas S/O Valve 7/8/2021 SGSOV Approved EVAN COOPER
Smoke Detectors 7/8/2021 Approved EVAN COOPER
BUILDING-Rough-Frame 7/16/2021 Approved EVAN COOPER
Final 7/16/2021 Corrections Issued EVAN COOPER
Footing/Foundation/Slab 7/16/2021 Approved EVAN COOPER
Green Building Final 7/16/2021 Approved EVAN COOPER
METHANE-Barrier 7/16/2021 Approved EVAN COOPER
METHANE-Subgrade 7/16/2021 Approved EVAN COOPER
Final 9/13/2021 OK to Issue CofO EVAN COOPER