8129 1/2 W 4TH ST 90048
Certificate Information: 8129 1/2 W 4TH ST 90048
- Application / Permit
- 20014-10000-03951
- Plan Check / Job No.
- B20LA16608
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- *ePLAN CHECK* CONVERSION & ADDITION OF (E) GARAGE TO (N) ACCESSORY DWELLING UNIT PER LAMC 12.22A33 (c) & (d). ALL WORK PER IB/P/BC 2020-004 WOOD FRAME PRESCRIPTIVE PROVISIONS
- Permit Issued
- Issued on 2/25/2021
- Issuing Office
- Current Status
- CofO Issued on 9/29/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 9/11/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 10/8/2020 | LAMAR DAVIS |
| Corrections Issued | 10/14/2020 | LAMAR DAVIS |
| Quality Review Completed | 10/15/2020 | TU HUA |
| Applicant returned to address corrections | 11/5/2020 | LAMAR DAVIS |
| Applicant returned to address corrections | 11/25/2020 | LAMAR DAVIS |
| Applicant returned to address corrections | 12/9/2020 | LAMAR DAVIS |
| Applicant returned to address corrections | 1/27/2021 | LAMAR DAVIS |
| Plan Check Approved | 2/24/2021 | LAMAR DAVIS |
| Issued | 2/25/2021 | APPLICANT |
| CofO in Progress | 9/13/2021 | EVAN COOPER |
| Permit Finaled | 9/29/2021 | KENNETH NAGLE |
| CofO Issued | 9/29/2021 | KENNETH NAGLE |
| Permit Finaled | 9/29/2021 | KENNETH NAGLE |
Permit Application Clearance Information
| Address approval | Cleared | 10/23/2020 | WALLIE JONG |
| Eng Process Fee Ord 176,300 | Cleared | 10/23/2020 | WALLIE JONG |
| Sewer availability | Cleared | 10/23/2020 | WALLIE JONG |
| Construction near power lines | Cleared | 11/13/2020 | RIDWAN HARDY |
| Construction within easement | Cleared | 11/13/2020 | RIDWAN HARDY |
| Low Impact Development | Cleared | 2/5/2021 | MARTIN FRAGOSO |
| Roof/Waste drainage to street | Cleared | 2/18/2021 | WALLIE JONG |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| WILBER ROSALES, (310) 914-3892 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 3/2/2021 | Corrections Issued | EVAN COOPER |
| METHANE-Rough | 3/22/2021 | Partial Approval | EVAN COOPER |
| PLUMBING-Rough | 3/22/2021 | Partial Approval | EVAN COOPER |
| Excavation/Setback/Form/Re-Bar | 3/26/2021 | Conditional Approval | EVAN COOPER |
| Footing/Foundation/Slab | 4/21/2021 | Corrections Issued | EVAN COOPER |
| PLUMBING-Rough | 4/21/2021 | Approved | EVAN COOPER |
| BUILDING-Rough-Frame | 4/27/2021 | Not Ready for Inspection | EVAN COOPER |
| ELECTRICAL-Rough | 4/27/2021 | Not Ready for Inspection | EVAN COOPER |
| Green Building Rough | 4/27/2021 | Not Ready for Inspection | EVAN COOPER |
| HVAC-Rough | 4/27/2021 | Not Ready for Inspection | EVAN COOPER |
| METHANE-Rough | 4/27/2021 | Not Ready for Inspection | EVAN COOPER |
| BUILDING-Rough-Frame | 4/30/2021 | Corrections Issued | EVAN COOPER |
| Green Building Rough | 4/30/2021 | Not Ready for Inspection | EVAN COOPER |
| METHANE-Rough | 4/30/2021 | Not Ready for Inspection | EVAN COOPER |
| BUILDING-Rough-Frame | 5/4/2021 | Partial Approval | EVAN COOPER |
| Green Building Rough | 5/4/2021 | Not Ready for Inspection | EVAN COOPER |
| METHANE-Rough | 5/4/2021 | Approved | EVAN COOPER |
| Interior/Exterior Lathing | 5/10/2021 | Corrections Issued | WILLIAM MICHALAK |
| Insulation | 5/12/2021 | Approved | EVAN COOPER |
| Drywall Nailing | 5/17/2021 | Approved | EVAN COOPER |
| Green Building Rough | 5/17/2021 | Approved | EVAN COOPER |
| HVAC-Rough | 6/24/2021 | No Access for Inspection | EVAN COOPER |
| Insulation | 6/24/2021 | No Access for Inspection | EVAN COOPER |
| ELECTRICAL-Final | 7/8/2021 | Approved | EVAN COOPER |
| Final | 7/8/2021 | Corrections Issued | EVAN COOPER |
| Gas Test | 7/8/2021 | Approved | EVAN COOPER |
| HVAC-Final | 7/8/2021 | Approved | EVAN COOPER |
| PLUMBING-Final | 7/8/2021 | Approved | EVAN COOPER |
| SGSOV-Seismic Gas S/O Valve | 7/8/2021 | SGSOV Approved | EVAN COOPER |
| Smoke Detectors | 7/8/2021 | Approved | EVAN COOPER |
| BUILDING-Rough-Frame | 7/16/2021 | Approved | EVAN COOPER |
| Final | 7/16/2021 | Corrections Issued | EVAN COOPER |
| Footing/Foundation/Slab | 7/16/2021 | Approved | EVAN COOPER |
| Green Building Final | 7/16/2021 | Approved | EVAN COOPER |
| METHANE-Barrier | 7/16/2021 | Approved | EVAN COOPER |
| METHANE-Subgrade | 7/16/2021 | Approved | EVAN COOPER |
| Final | 9/13/2021 | OK to Issue CofO | EVAN COOPER |