3437 W LONDON ST 90026
Certificate Information: 3437 W LONDON ST 90026
- Application / Permit
- 20014-10000-03940
- Plan Check / Job No.
- B20LA16589
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- PROPOSED IRREGULAR SHAPE ADDITION TO AND CONVERSION OF GARAGE TO ACCESORY DWELLING UNIT PER ORDINANCE 186,481
- Permit Issued
- Issued on 12/11/2020
- Issuing Office
- Metro
- Current Status
- CofO Issued on 7/3/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 9/11/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 9/18/2020 | SINA KHOSRAVI |
| Corrections Issued | 9/20/2020 | SINA KHOSRAVI |
| Plan Check Approved | 11/25/2020 | RICARDO RAMIREZ |
| Building Plans Picked Up | 11/25/2020 | APPLICANT |
| Issued | 12/11/2020 | APPLICANT |
| CofO in Progress | 6/24/2021 | ROBERT VORHIS |
| CofO in Progress | 6/24/2021 | ROBERT VORHIS |
| Permit Finaled | 7/3/2021 | DEROLD HAUFF |
| CofO Issued | 7/3/2021 | DEROLD HAUFF |
| Permit Finaled | 7/3/2021 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 10/2/2020 | ELAINE LEI |
| Eng Process Fee Ord 176,300 | Cleared | 10/2/2020 | ELAINE LEI |
| Sewer availability | Cleared | 10/2/2020 | ELAINE LEI |
| Low Impact Development | Cleared | 10/22/2020 | MITESH PATEL |
| Roof/Waste drainage to street | Cleared | 10/26/2020 | ELAINE LEI |
| Construction near power lines | Cleared | 11/19/2020 | RIDWAN HARDY |
| Grading Pre-Inspection | Cleared | 11/25/2020 | SINA KHOSRAVI |
Contact Information
| Contractor | Minchez Construction Inc; Lic. No.: 1022183-B | 11211 OSBORNE STREET LAKE VIEW TERRACE, CA 91342 |
Inspector Information
| FREDDIE RIVERA, (213) 202-3437 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 12/16/2020 | Corrections Issued | ROBERT VORHIS |
| Excavation/Setback/Form/Re-Bar | 12/22/2020 | Approved | ROBERT VORHIS |
| PLUMBING-Rough | 1/26/2021 | Partial Approval | ROBERT VORHIS |
| HVAC-Rough | 3/8/2021 | Approved | ROBERT VORHIS |
| ELECTRICAL-Rough | 3/15/2021 | Approved | ROBERT VORHIS |
| Floor/Roof Diaphrgm/Shear Wall | 3/15/2021 | Approved | ROBERT VORHIS |
| Green Building Rough | 3/15/2021 | Not Ready for Inspection | ROBERT VORHIS |
| MERV13>=Rough | 3/15/2021 | Approved | ROBERT VORHIS |
| PLUMBING-Rough | 3/15/2021 | Approved | ROBERT VORHIS |
| BUILDING-Rough-Frame | 3/19/2021 | Approved | ROBERT VORHIS |
| Green Building Rough | 3/19/2021 | Approved | ROBERT VORHIS |
| Interior/Exterior Lathing | 3/19/2021 | Approved | ROBERT VORHIS |
| Insulation | 3/26/2021 | Approved | RUBEN SALAS |
| Drywall Nailing | 4/9/2021 | Approved | CHRISTOPHER DELLEFIELD |
| Interior/Exterior Lathing | 4/9/2021 | Approved | CHRISTOPHER DELLEFIELD |
| Shower Pan | 4/9/2021 | Approved | CHRISTOPHER DELLEFIELD |
| Sewer | 5/3/2021 | Approved | ROBERT VORHIS |
| Final | 6/15/2021 | Not Ready for Inspection | ROBERT VORHIS |
| Footing/Foundation/Slab | 6/15/2021 | Approved | ROBERT VORHIS |
| Green Building Final | 6/15/2021 | Approved | ROBERT VORHIS |
| MERV13>=Final | 6/15/2021 | Approved | ROBERT VORHIS |
| SGSOV-Seismic Gas S/O Valve | 6/15/2021 | SGSOV Approved | ROBERT VORHIS |
| Smoke Detectors | 6/15/2021 | Approved | ROBERT VORHIS |
| Final | 6/23/2021 | OK to Issue CofO | ROBERT VORHIS |