2402 S GRAND CL 90291
Certificate Information: 2402 S GRAND CL 90291
- Application / Permit
- 20014-10000-03931
- Plan Check / Job No.
- B20LA16524
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- INTERIOR REMODEL AND SECOND STORY ADDITION TO AN EXISTING SINGLE FAMILY RESIDENCE. EXPAND EXISTING ROOF DECK OVER ENCLOSED BALCONY
- Permit Issued
- Issued on 6/4/2021
- Issuing Office
- Current Status
- CofO Issued on 9/28/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 9/13/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 9/17/2020 | STARR CHEN |
| Corrections Issued | 9/19/2020 | STARR CHEN |
| Quality Review Completed | 10/7/2020 | HERNAN ARREOLA |
| Applicant returned to address corrections | 12/3/2020 | STARR CHEN |
| Applicant returned to address corrections | 1/13/2021 | STARR CHEN |
| Plan Check Approved | 2/17/2021 | STARR CHEN |
| Issued | 6/4/2021 | APPLICANT |
| CofO in Progress | 9/19/2022 | DAVID FEILER |
| Permit Finaled | 9/28/2022 | DANIEL ORRANTE |
| CofO Issued | 9/28/2022 | DANIEL ORRANTE |
| Permit Finaled | 9/28/2022 | DANIEL ORRANTE |
Permit Application Clearance Information
| Roof/Waste drainage to street | Cleared | 10/29/2020 | DINAH GARIN |
| Sewer availability | Cleared | 10/29/2020 | DINAH GARIN |
| ZI | Cleared | 10/29/2020 | RUBEN VASQUEZ |
| Eng Process Fee Ord 176,300 | Cleared | 11/2/2020 | DINAH GARIN |
| Specific Plan | Cleared | 11/4/2020 | BINDU KANNAN |
| Specific Plan | Cleared | 11/5/2020 | VALERIA CEJA |
| Coastal Zone | Cleared | 12/2/2020 | ANACANY HURTADO |
| City Hist. Cultural Monument | Cleared | 12/14/2020 | MELISSA JONES |
| Historic monument | Cleared | 12/14/2020 | MELISSA JONES |
Contact Information
| Contractor | Greve Built; Lic. No.: 923371-B | 832 SUPERBA AVENUE VENICE, CA 90291 |
Inspector Information
| RUBEN RIVAS, (310) 914-3981 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 7/1/2021 | Approved | JOHNNY MIRANDA |
| BUILDING-Rough-Frame | 9/14/2021 | Partial Approval | JOHNNY MIRANDA |
| Green Building Rough | 9/14/2021 | Not Ready for Inspection | JOHNNY MIRANDA |
| METHANE-Rough | 9/14/2021 | Approved | JOHNNY MIRANDA |
| BUILDING-Rough-Frame | 2/1/2022 | Not Ready for Inspection | DAVID FEILER |
| Green Building Rough | 2/1/2022 | Not Ready for Inspection | DAVID FEILER |
| PLUMBING-Rough | 2/11/2022 | Corrections Issued | DAVID FEILER |
| HVAC-Rough | 2/15/2022 | Partial Approval | DAVID FEILER |
| HVAC-Rough | 2/24/2022 | Approved | KRISTEN CAUSEY |
| PLUMBING-Rough | 2/24/2022 | Approved | KRISTEN CAUSEY |
| BUILDING-Rough-Frame | 3/4/2022 | Partial Approval | DAVID FEILER |
| Green Building Rough | 3/4/2022 | Not Ready for Inspection | DAVID FEILER |
| Shower Pan | 3/17/2022 | Approved | DAVID FEILER |
| ELECTRICAL-Rough | 3/25/2022 | Approved | PATRICK QUALEY |
| Insulation | 3/25/2022 | Approved | PATRICK QUALEY |
| BUILDING-Rough-Frame | 3/30/2022 | Approved | KENNETH NAGLE |
| Green Building Rough | 3/30/2022 | Approved | KENNETH NAGLE |
| Interior/Exterior Lathing | 3/30/2022 | Partial Approval | KENNETH NAGLE |
| Interior/Exterior Lathing | 4/5/2022 | Partial Approval | STEPHANIE SWANSON |
| Interior/Exterior Lathing | 4/13/2022 | Approved | DAVID FEILER |
| Drywall Nailing | 4/15/2022 | Approved | DAVID FEILER |
| ELECTRICAL-Final | 8/30/2022 | Not Ready for Inspection | DAVID FEILER |
| Final | 8/30/2022 | Corrections Issued | DAVID FEILER |
| Footing/Foundation/Slab | 8/30/2022 | Partial Inspection | DAVID FEILER |
| Green Building Final | 8/30/2022 | Approved | DAVID FEILER |
| HVAC-Final | 8/30/2022 | Approved | DAVID FEILER |
| METHANE-Barrier | 8/30/2022 | Approved | DAVID FEILER |
| METHANE-Subgrade | 8/30/2022 | Approved | DAVID FEILER |
| PLUMBING-Final | 8/30/2022 | Not Ready for Inspection | DAVID FEILER |
| SGSOV-Seismic Gas S/O Valve | 8/30/2022 | SGSOV Approved | DAVID FEILER |
| Smoke Detectors | 8/30/2022 | Not Ready for Inspection | DAVID FEILER |
| Final | 9/8/2022 | Partial Inspection | DAVID FEILER |
| Footing/Foundation/Slab | 9/8/2022 | Not Ready for Inspection | DAVID FEILER |
| Smoke Detectors | 9/8/2022 | Approved | DAVID FEILER |
| Final | 9/16/2022 | OK to Issue CofO | DAVID FEILER |
| Footing/Foundation/Slab | 9/16/2022 | Approved | DAVID FEILER |