2578 N VERBENA DR 90068

Certificate Information: 2578 N VERBENA DR 90068

Application / Permit
20014-10000-03903
Plan Check / Job No.
B20LA16396
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
ADDITION TO COVER (E) UNCOVERED BALCONY AT FRONT OF PROPERTY. REMODEL EXTERIOR FACADE AND INTERIOR REMODEL. EXPAND UNCOVERED PATIO DECK IN BACKYARD
Permit Issued
Issued on 12/3/2021
Issuing Office
Current Status
Issued on 12/3/2021
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 9/9/2020 APPLICANT
Assigned to Plan Check Engineer 9/17/2020 CARLOS MONTES
Corrections Issued 9/25/2020 CARLOS MONTES
Quality Review Completed 10/14/2020 WING SUEN
Applicant returned to address corrections 1/15/2021 CARLOS MONTES
Plan Check Approved 8/31/2021 CARLOS MONTES
Issued 12/3/2021 APPLICANT
Building Plans Picked Up 12/13/2021 APPLICANT

Permit Application Clearance Information

BHO/Hillside ordinance Cleared 11/24/2020 WALLIE JONG
BHO/Hillside ordinance Cleared 11/24/2020 WALLIE JONG
BHO/Hillside ordinance Cleared 11/24/2020 WALLIE JONG
BHO/Hillside ordinance Cleared 11/24/2020 WALLIE JONG
Roof/Waste drainage to street Cleared 11/24/2020 WALLIE JONG
Sewer availability Cleared 11/24/2020 WALLIE JONG
Eng Process Fee Ord 176,300 Cleared 11/30/2020 WALLIE JONG
BHO/Hillside ordinance Cleared 12/1/2020 WALLIE JONG
Grading Pre-Inspection Cleared 7/28/2021 BRIAN MILLER

Contact Information

Architect Greg, Wilhelm, Architect; Lic. No.: BUS14606 84553 COVENANT DRIVE      FALL CREEK, OR 97438
Contractor Golden Point Construction; Lic. No.: 965193-B 731 EAST 75TH STREET      LOS ANGELES, CA 90001
Engineer Phillips,, Craig Richard; Lic. No.: C69673 2123 VESTAL AVE      LOS ANGELES, CA 90026

Inspector Information

CRAIG VAUGHAN, (213) 202-3250 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Special/Order Compliance 1/26/2022 Not Ready for Inspection BRIAN SULLIVAN
Excavation/Setback/Form/Re-Bar 2/11/2022 Corrections Issued BRIAN SULLIVAN
Footing/Foundation/Slab 2/11/2022 Not Ready for Inspection BRIAN SULLIVAN
Excavation/Setback/Form/Re-Bar 2/16/2022 Partial Approval BRIAN SULLIVAN
Footing/Foundation/Slab 3/8/2022 Partial Approval BRIAN SULLIVAN
ELECTRICAL-Rough 3/25/2022 Not Ready for Inspection BRIAN SULLIVAN
Floor/Roof Diaphrgm/Shear Wall 3/25/2022 Partial Approval BRIAN SULLIVAN
PLUMBING-Rough 3/25/2022 Not Ready for Inspection BRIAN SULLIVAN
ELECTRICAL-Rough 4/4/2022 Approved BRIAN SULLIVAN
HVAC-Rough 4/4/2022 Approved BRIAN SULLIVAN
PLUMBING-Rough 4/4/2022 Corrections Issued BRIAN SULLIVAN
BUILDING-Rough-Frame 4/8/2022 Not Ready for Inspection RUBEN SALAS
Green Building Rough 4/8/2022 Approved RUBEN SALAS
PLUMBING-Rough 4/8/2022 Approved RUBEN SALAS
Verify Sprinkler Sign Off 4/8/2022 Corrections Issued RUBEN SALAS
BUILDING-Rough-Frame 4/22/2022 Partial Approval BRIAN SULLIVAN
Verify Sprinkler Sign Off 4/22/2022 Approved BRIAN SULLIVAN
Interior/Exterior Lathing 6/1/2022 Not Ready for Inspection BRIAN SULLIVAN
BUILDING-Rough-Frame 2/3/2023 Corrections Issued JOAQUIN GREENOUGH
BUILDING-Rough-Frame 11/15/2023 Corrections Issued JOAQUIN GREENOUGH
Special/Order Compliance 11/15/2023 Corrections Issued JOAQUIN GREENOUGH
Floor/Roof Diaphrgm/Shear Wall 3/1/2024 Partial Approval BRIAN SULLIVAN
BUILDING-Rough-Frame 8/16/2024 Approved ROY SPAULDING
Interior/Exterior Lathing 8/16/2024 Approved ROY SPAULDING
Drywall Nailing 4/30/2025 Approved CRAIG VAUGHAN