2108 W 41ST DR 90062

Certificate Information: 2108 W 41ST DR 90062

Application / Permit
20014-10000-03872
Plan Check / Job No.
B20LA16196
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERTING EXISTING 2 CAR GARAGE TO AN A.D.U. 471 SQ. FT. ADDING 95 SQ. FT. FOR A 1 BEDROOM 1 BATH AND KITCHEN FOR A TOTAL OF 566 SQ. FT. Addition (95sqft) and convert (E) two garage (471 sqft) to ADU (566 sqft, one bedroom and one bath with kitchen.
Permit Issued
Issued on 6/3/2021
Issuing Office
Current Status
CofO Issued on 1/19/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 9/9/2020 APPLICANT
Assigned to Plan Check Engineer 9/13/2020 SINA KHOSRAVI
Corrections Issued 9/13/2020 SINA KHOSRAVI
Applicant returned to address corrections 4/1/2021 TSE MING HUANG
Plan Check Approved 4/5/2021 TSE MING HUANG
Issued 6/3/2021 APPLICANT
Building Plans Picked Up 6/4/2021 APPLICANT
CofO in Progress 12/13/2022 ANTHONY EGSON
Permit Finaled 1/19/2023 DEROLD HAUFF
CofO Issued 1/19/2023 DEROLD HAUFF
Permit Finaled 1/19/2023 DEROLD HAUFF

Permit Application Clearance Information

Construction near power lines Cleared 12/15/2020 RIDWAN HARDY
Eng Process Fee Ord 176,300 Cleared 3/4/2021 CECILIO NAVARRO
Roof/Waste drainage to street Cleared 3/4/2021 CECILIO NAVARRO
Sewer availability Cleared 3/4/2021 CECILIO NAVARRO
Address approval Cleared 3/5/2021 CECILIO NAVARRO

Contact Information

Contractor Baron Construction & Design; Lic. No.: 917339-B 1171 N KENMORE AVE APT #8      LOS ANGELES, CA 90029

Inspector Information

LUIS CASTRO, (213) 202-3436 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 6/15/2021 Corrections Issued DAVID FEILER
Footing/Foundation/Slab 6/15/2021 Not Ready for Inspection DAVID FEILER
Deputy Drilled-In Anchors 6/16/2021 No Access for Inspection DAVID FEILER
Excavation/Setback/Form/Re-Bar 6/21/2021 Approved DAVID FEILER
Footing/Foundation/Slab 6/21/2021 Approved DAVID FEILER
BUILDING-Rough-Frame 7/14/2021 Not Ready for Inspection SABAS ALONSO
ELECTRICAL-Rough 7/14/2021 Approved SABAS ALONSO
Gas Test 7/14/2021 Not Ready for Inspection SABAS ALONSO
Green Building Rough 7/14/2021 Not Ready for Inspection SABAS ALONSO
PLUMBING-Rough 7/14/2021 Not Ready for Inspection SABAS ALONSO
Sewer 7/14/2021 Not Ready for Inspection SABAS ALONSO
ELECTRICAL-Rough 7/21/2021 Corrections Issued DAVID FEILER
HVAC-Rough 7/21/2021 Not Ready for Inspection DAVID FEILER
PLUMBING-Rough 7/21/2021 Not Ready for Inspection DAVID FEILER
Sewer 7/21/2021 Not Ready for Inspection DAVID FEILER
BUILDING-Rough-Frame 11/1/2021 Corrections Issued ANTHONY EGSON
ELECTRICAL-Rough 11/1/2021 Not Ready for Inspection ANTHONY EGSON
Green Building Rough 11/1/2021 Not Ready for Inspection ANTHONY EGSON
PLUMBING-Rough 11/1/2021 Corrections Issued ANTHONY EGSON
BUILDING-Rough-Frame 12/27/2021 Corrections Issued ANTHONY EGSON
ELECTRICAL-Rough 12/27/2021 Corrections Issued ANTHONY EGSON
Green Building Rough 12/27/2021 Corrections Issued ANTHONY EGSON
PLUMBING-Rough 12/27/2021 Corrections Issued ANTHONY EGSON
Floor/Roof Diaphrgm/Shear Wall 12/29/2021 Approved JOSE AVILA
ELECTRICAL-Rough 1/5/2022 Approved ANTHONY EGSON
Floor/Roof Diaphrgm/Shear Wall 1/5/2022 Approved ANTHONY EGSON
PLUMBING-Rough 1/5/2022 Approved ANTHONY EGSON
ELECTRICAL-Rough 1/19/2022 Corrections Issued ANTHONY EGSON
HVAC-Rough 1/19/2022 Corrections Issued ANTHONY EGSON
Interior/Exterior Lathing 1/19/2022 Corrections Issued ANTHONY EGSON
PLUMBING-Rough 1/19/2022 Corrections Issued ANTHONY EGSON
ELECTRICAL-Rough 1/24/2022 Conditional Approval FREDDIE RIVERA
PLUMBING-Rough 1/24/2022 Conditional Approval FREDDIE RIVERA
Pre-Inspection 1/24/2022 Corrections Issued FREDDIE RIVERA
Sewer 1/24/2022 Conditional Approval FREDDIE RIVERA
ELECTRICAL-Rough 3/15/2022 Approved ANTHONY EGSON
Interior/Exterior Lathing 3/15/2022 Approved ANTHONY EGSON
PLUMBING-Rough 3/15/2022 Approved ANTHONY EGSON
Sewer 3/15/2022 Approved ANTHONY EGSON
Rough-Elec/Plmb/HVAC 4/1/2022 Approved ANTHONY EGSON
Wood Frame 4/1/2022 Corrections Issued ANTHONY EGSON
BUILDING-Rough-Frame 4/8/2022 Approved ANTHONY EGSON
Green Building Rough 4/8/2022 Approved ANTHONY EGSON
Drywall Nailing 4/14/2022 Corrections Issued ANTHONY EGSON
Drywall Nailing 4/19/2022 Approved ANTHONY EGSON
Interior/Exterior Lathing 4/19/2022 Approved ANTHONY EGSON
Final 7/8/2022 Not Ready for Inspection ANTHONY EGSON
Green Building Final 7/8/2022 Corrections Issued ANTHONY EGSON
SGSOV-Seismic Gas S/O Valve 7/8/2022 SGSOV Not Ready ANTHONY EGSON
Smoke Detectors 7/8/2022 Corrections Issued ANTHONY EGSON
ELECTRICAL-Final 7/22/2022 Corrections Issued ANTHONY EGSON
Final 7/22/2022 Not Ready for Inspection ANTHONY EGSON
Green Building Final 7/22/2022 Approved ANTHONY EGSON
HVAC-Final 7/22/2022 Corrections Issued ANTHONY EGSON
PLUMBING-Final 7/22/2022 Corrections Issued ANTHONY EGSON
SGSOV-Seismic Gas S/O Valve 7/22/2022 SGSOV Not Ready ANTHONY EGSON
Smoke Detectors 7/22/2022 Approved ANTHONY EGSON
Final 9/1/2022 Not Ready for Inspection ANTHONY EGSON
SGSOV-Seismic Gas S/O Valve 9/1/2022 SGSOV Approved ANTHONY EGSON
Final 9/8/2022 Corrections Issued ANTHONY EGSON
Final 9/30/2022 OK to Issue CofO ANTHONY EGSON
Service/Power Release 12/20/2022 Approved ANTHONY EGSON