13736 W BRANFORD ST 91331
Certificate Information: 13736 W BRANFORD ST 91331
- Application / Permit
- 20014-10000-03871
- Plan Check / Job No.
- B20LA16195
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- REMODEL AND ADDITIONS TO EXISITNG SFD
- Permit Issued
- Issued on 7/22/2022
- Issuing Office
- Current Status
- CofO Issued on 2/23/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 9/8/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 10/1/2020 | CARLOS MONTES |
| Corrections Issued | 10/5/2020 | CARLOS MONTES |
| Quality Review Completed | 10/28/2020 | WING SUEN |
| Building Plans Picked Up | 11/6/2020 | APPLICANT |
| Applicant returned to address corrections | 4/27/2021 | CARLOS MONTES |
| Applicant returned to address corrections | 3/23/2022 | CARLOS MONTES |
| Applicant returned to address corrections | 3/25/2022 | CRISTINA SALAZAR |
| Plan Check Approved | 6/27/2022 | CARLOS MONTES |
| Issued | 7/22/2022 | APPLICANT |
| CofO in Progress | 1/19/2024 | GREGG CUMMINGS |
| Permit Finaled | 2/23/2024 | RUBEN SALAS |
| CofO Issued | 2/23/2024 | RUBEN SALAS |
| Permit Finaled | 2/23/2024 | RUBEN SALAS |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 4/18/2022 | JOSE DUARTE-DIAZ |
| Sewer availability | Cleared | 4/18/2022 | JOSE DUARTE-DIAZ |
| Low Impact Development | Cleared | 6/3/2022 | ANTHONY VARGAS |
| Roof/Waste drainage to street | Cleared | 6/15/2022 | JOSE DUARTE-DIAZ |
| Public Works-Highway Ded. | Cleared | 6/15/2022 | JOSE DUARTE-DIAZ |
Contact Information
| Architect | Kivotos,, Juan M; Lic. No.: C26491 | 1323 N NIAGARA STREET BURBANK, CA 91505 |
| Contractor | Owner-Builder | , |
| Engineer | Yogurtian,, Arpinee; Lic. No.: C49916 | 2529 FOOTHILL BLVD, STE 208 LA CRESCENTA, CA 91214 |
Inspector Information
| OGANES TARAKHCHYAN, (818) 374-1162 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 8/12/2022 | Not Ready for Inspection | GREGG CUMMINGS |
| Footing/Foundation/Slab | 8/12/2022 | Corrections Issued | GREGG CUMMINGS |
| Footing/Foundation/Slab | 8/18/2022 | Conditional Approval | MICHEL ABAJAN |
| PLUMBING-Rough | 9/2/2022 | Partial Approval | MICHEL ABAJAN |
| Wood Frame | 9/2/2022 | Partial Approval | MICHEL ABAJAN |
| Floor/Roof Diaphrgm/Shear Wall | 9/9/2022 | Approved | WILLIAM WREN |
| Insulation | 9/9/2022 | Partial Approval | WILLIAM WREN |
| ELECTRICAL-Rough | 10/20/2022 | Approved | WILLIAM WREN |
| Floor/Roof Diaphrgm/Shear Wall | 10/20/2022 | Partial Approval | WILLIAM WREN |
| PLUMBING-Rough | 10/20/2022 | Order to Comply Issued | WILLIAM WREN |
| HVAC-Rough | 10/27/2022 | Corrections Issued | GREGG CUMMINGS |
| Wood Frame | 10/27/2022 | Partial Approval | GREGG CUMMINGS |
| HVAC-Rough | 11/29/2022 | Not Ready for Inspection | GREGG CUMMINGS |
| Interior/Exterior Lathing | 11/29/2022 | Not Ready for Inspection | GREGG CUMMINGS |
| Wood Frame | 11/29/2022 | Partial Approval | GREGG CUMMINGS |
| HVAC-Rough | 1/20/2023 | Approved | GREGG CUMMINGS |
| Insulation | 1/20/2023 | Approved | GREGG CUMMINGS |
| BUILDING-Rough-Frame | 1/27/2023 | Approved | GREGG CUMMINGS |
| Drywall Nailing | 1/27/2023 | Approved | GREGG CUMMINGS |
| Green Building Rough | 1/27/2023 | Approved | GREGG CUMMINGS |
| Interior/Exterior Lathing | 1/27/2023 | Approved | GREGG CUMMINGS |
| HVAC-Rough | 3/3/2023 | Not Ready for Inspection | GREGG CUMMINGS |
| Sewer | 4/21/2023 | Partial Approval | GREGG CUMMINGS |
| ELECTRICAL-Final | 9/27/2023 | Not Ready for Inspection | GREGG CUMMINGS |
| Final | 9/27/2023 | Corrections Issued | GREGG CUMMINGS |
| Footing/Foundation/Slab | 9/27/2023 | Approved | GREGG CUMMINGS |
| Green Building Final | 9/27/2023 | Approved | GREGG CUMMINGS |
| SGSOV-Seismic Gas S/O Valve | 9/27/2023 | SGSOV Not Ready | GREGG CUMMINGS |
| Smoke Detectors | 9/27/2023 | Not Ready for Inspection | GREGG CUMMINGS |
| ELECTRICAL-Final | 10/4/2023 | Not Ready for Inspection | GREGG CUMMINGS |
| Final | 10/4/2023 | Corrections Issued | GREGG CUMMINGS |
| HVAC-Final | 10/4/2023 | Not Ready for Inspection | GREGG CUMMINGS |
| PLUMBING-Final | 10/4/2023 | Not Ready for Inspection | GREGG CUMMINGS |
| SGSOV-Seismic Gas S/O Valve | 10/4/2023 | SGSOV Approved | GREGG CUMMINGS |
| Smoke Detectors | 10/4/2023 | Not Ready for Inspection | GREGG CUMMINGS |
| ELECTRICAL-Final | 10/5/2023 | Not Ready for Inspection | GREGG CUMMINGS |
| Final | 10/5/2023 | Corrections Issued | GREGG CUMMINGS |
| HVAC-Final | 10/5/2023 | Not Ready for Inspection | GREGG CUMMINGS |
| Final | 10/26/2023 | Corrections Issued | GREGG CUMMINGS |
| HVAC-Final | 10/26/2023 | Approved | GREGG CUMMINGS |
| Smoke Detectors | 10/26/2023 | Approved | GREGG CUMMINGS |
| ELECTRICAL-Final | 1/18/2024 | Approved | GREGG CUMMINGS |
| Final | 1/18/2024 | OK to Issue CofO | GREGG CUMMINGS |
| PLUMBING-Final | 1/18/2024 | Approved | GREGG CUMMINGS |