3610 S BUDLONG AVE 90007

Certificate Information: 3610 S BUDLONG AVE 90007

Application / Permit
20014-10000-03783
Plan Check / Job No.
B20LA15862
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
Conversion and addition to (E) garage (18'-2" x 16'-3") to create Accessory Dwelling Unit per LAMC 12.22 A.33(c) and (d) (438 SF total). All work per engineered design.
Permit Issued
Issued on 1/27/2021
Issuing Office
Current Status
CofO Issued on 4/11/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 9/30/2020 APPLICANT
Assigned to Plan Check Engineer 10/7/2020 CHRISTOPHER KOMANCHECK
Corrections Issued 10/8/2020 CHRISTOPHER KOMANCHECK
Plan Check Approved 1/20/2021 JESSE JIMENEZ
Issued 1/27/2021 APPLICANT
Building Plans Picked Up 2/2/2021 APPLICANT
CofO in Progress 4/11/2024 SABAS ALONSO
Permit Finaled 4/11/2024 DEROLD HAUFF
CofO Issued 4/11/2024 DEROLD HAUFF
Permit Finaled 4/11/2024 DEROLD HAUFF

Permit Application Clearance Information

Roof/Waste drainage to street Cleared 10/26/2020 RENZ SORIANO
Address approval Cleared 11/16/2020 RENZ SORIANO
Eng Process Fee Ord 176,300 Cleared 11/18/2020 RENZ SORIANO
Sewer availability Cleared 11/18/2020 RENZ SORIANO
Tenant Habitability Plan Cleared 11/30/2020 CHARLES GARCIA

Contact Information

Contractor Owner-Builder       ,
Engineer Sarrami,, Gholamali F; Lic. No.: C43720 4942 HIGHLAND VIEW AVENUE      LOS ANGELES, CA 90041

Inspector Information

SABAS ALONSO, (213) 202-3468 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 3/8/2021 Approved FREDDIE RIVERA
PLUMBING-Rough 3/22/2021 Partial Approval ROBERT MCDOWELL
Footing/Foundation/Slab 3/25/2021 Conditional Approval ROBERT MCDOWELL
METHANE-Barrier 3/25/2021 Approved ROBERT MCDOWELL
METHANE-Subgrade 3/25/2021 Approved ROBERT MCDOWELL
ELECTRICAL-Rough 4/16/2021 Approved ROBERT MCDOWELL
Floor/Roof Diaphrgm/Shear Wall 4/16/2021 Approved ROBERT MCDOWELL
Green Building Rough 4/16/2021 Not Ready for Inspection ROBERT MCDOWELL
METHANE-Rough 4/16/2021 Approved ROBERT MCDOWELL
Underground Mechanical 4/16/2021 Approved ROBERT MCDOWELL
ELECTRICAL-Rough 4/27/2021 Approved ROBERT MCDOWELL
HVAC-Rough 4/27/2021 Approved ROBERT MCDOWELL
PLUMBING-Rough 4/27/2021 Approved ROBERT MCDOWELL
Insulation 5/7/2021 Corrections Issued CHRISTOPHER DELLEFIELD
BUILDING-Rough-Frame 5/24/2021 Approved ROBERT MCDOWELL
Drywall Nailing 5/24/2021 Approved ROBERT MCDOWELL
Green Building Rough 5/24/2021 Approved ROBERT MCDOWELL
Insulation 5/24/2021 Approved ROBERT MCDOWELL
Interior/Exterior Lathing 5/24/2021 Approved ROBERT MCDOWELL
Final 9/27/2021 Not Ready for Inspection SABAS ALONSO
Footing/Foundation/Slab 9/27/2021 Approved SABAS ALONSO
Green Building Final 9/27/2021 Approved SABAS ALONSO
SGSOV-Seismic Gas S/O Valve 9/27/2021 SGSOV Not Ready SABAS ALONSO
Smoke Detectors 9/27/2021 Not Ready for Inspection SABAS ALONSO
Final 10/12/2021 Corrections Issued SABAS ALONSO
SGSOV-Seismic Gas S/O Valve 10/12/2021 SGSOV Not Ready SABAS ALONSO
Smoke Detectors 10/12/2021 Approved SABAS ALONSO
Final 10/19/2021 Corrections Issued SABAS ALONSO
SGSOV-Seismic Gas S/O Valve 10/19/2021 SGSOV Approved SABAS ALONSO
Final 2/20/2024 Corrections Issued SABAS ALONSO
Final 3/13/2024 Corrections Issued SABAS ALONSO
Final 4/10/2024 OK to Issue CofO SABAS ALONSO