3928 S VAN NESS AVE 90062

Certificate Information: 3928 S VAN NESS AVE 90062

Application / Permit
20014-10000-03782
Plan Check / Job No.
B20LA15855
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
ADU ADDITION (2STORY) TO (E) SFD AND ON TOP OF EXISTING GARAGE PER ORDINANCE
Permit Issued
Issued on 6/9/2021
Issuing Office
Current Status
Issued on 6/9/2021
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 9/1/2020 APPLICANT
Assigned to Plan Check Engineer 9/25/2020 CARLOS MONTES
Corrections Issued 10/1/2020 CARLOS MONTES
Quality Review Completed 10/19/2020 WING SUEN
Building Plans Picked Up 10/21/2020 APPLICANT
Applicant returned to address corrections 3/4/2021 CARLOS MONTES
Plan Check Approved 5/11/2021 CARLOS MONTES
Issued 6/9/2021 APPLICANT

Permit Application Clearance Information

Address approval Cleared 11/13/2020 RENZ SORIANO
Sewer availability Cleared 11/16/2020 RENZ SORIANO
Eng Process Fee Ord 176,300 Cleared 11/17/2020 JUAN ASHTON
Low Impact Development Cleared 1/13/2021 JORGE MEJIA LEMUS
Roof/Waste drainage to street Cleared 1/20/2021 THOMAS LANG

Contact Information

Contractor Zetino And Son'S Construction; Lic. No.: 817787-B 841 S CALIFORNIA AVE      WEST COVINA, CA 91790

Inspector Information

SABAS ALONSO, (213) 202-3468 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 7/8/2021 Approved JOHN HAMILTON
Excavation/Setback/Form/Re-Bar 7/8/2021 Conditional Approval JOAQUIN GREENOUGH
Footing/Foundation/Slab 7/8/2021 Conditional Approval JOAQUIN GREENOUGH
Footing/Foundation/Slab 7/19/2021 Corrections Issued HORACE FULTZ
Structural Steel Frame 7/19/2021 Approved HORACE FULTZ
Deputy Steel/Welding 7/21/2021 No Access for Inspection ELMER BLAND
Floor/Roof Diaphrgm/Shear Wall 8/19/2021 Not Ready for Inspection SABAS ALONSO
Floor/Roof Diaphrgm/Shear Wall 11/15/2021 Partial Approval HORACE FULTZ
Floor/Roof Diaphrgm/Shear Wall 12/6/2021 Partial Approval SABAS ALONSO
Green Building Rough 12/6/2021 Not Ready for Inspection SABAS ALONSO
BUILDING-Rough-Frame 1/31/2022 Not Ready for Inspection SABAS ALONSO
ELECTRICAL-Rough 1/31/2022 Approved SABAS ALONSO
Green Building Rough 1/31/2022 Not Ready for Inspection SABAS ALONSO
PLUMBING-Rough 1/31/2022 Corrections Issued SABAS ALONSO
BUILDING-Rough-Frame 2/22/2022 Not Ready for Inspection HORACE FULTZ
Green Building Rough 2/22/2022 Order to Comply Issued HORACE FULTZ
Interior/Exterior Lathing 2/22/2022 Not Ready for Inspection HORACE FULTZ
Insulation 3/1/2022 Partial Inspection FREDDIE RIVERA
Wood Frame 3/1/2022 Partial Approval FREDDIE RIVERA
BUILDING-Rough-Frame 3/3/2022 Not Ready for Inspection SABAS ALONSO
ELECTRICAL-Rough 3/3/2022 Approved SABAS ALONSO
Green Building Rough 3/3/2022 Approved SABAS ALONSO
HVAC-Rough 3/3/2022 Corrections Issued SABAS ALONSO
PLUMBING-Rough 3/3/2022 Approved SABAS ALONSO
BUILDING-Rough-Frame 3/7/2022 Approved SABAS ALONSO
Pre-Inspection 3/7/2022 Partial Approval SABAS ALONSO
Deputy Wood Construction 3/9/2022 Conditional Approval SABAS ALONSO
Floor/Roof Diaphrgm/Shear Wall 3/14/2022 Approved SABAS ALONSO
Insulation 3/18/2022 Not Ready for Inspection SABAS ALONSO
Interior/Exterior Lathing 3/18/2022 Corrections Issued SABAS ALONSO
Insulation 3/22/2022 Corrections Issued SABAS ALONSO
Interior/Exterior Lathing 3/22/2022 Partial Approval SABAS ALONSO
Drywall Nailing 3/29/2022 Conditional Approval SABAS ALONSO
Insulation 3/29/2022 Not Ready for Inspection SABAS ALONSO
Service/Power Release 5/19/2022 Corrections Issued SABAS ALONSO
Underground Mechanical 5/19/2022 Partial Approval SABAS ALONSO
Drywall Nailing 6/13/2022 Approved SABAS ALONSO
ELECTRICAL-Final 6/13/2022 Not Ready for Inspection SABAS ALONSO
Final 6/13/2022 Corrections Issued SABAS ALONSO
Footing/Foundation/Slab 6/13/2022 Approved SABAS ALONSO
Green Building Final 6/13/2022 Not Ready for Inspection SABAS ALONSO
HVAC-Final 6/13/2022 Approved SABAS ALONSO
PLUMBING-Final 6/13/2022 Approved SABAS ALONSO
SGSOV-Seismic Gas S/O Valve 6/13/2022 SGSOV Approved SABAS ALONSO
Service/Power Release 6/13/2022 Not Required SABAS ALONSO
Smoke Detectors 6/13/2022 Not Ready for Inspection SABAS ALONSO
ELECTRICAL-Final 7/11/2022 Approved HORACE FULTZ
Final 7/11/2022 Conditional Approval HORACE FULTZ
Green Building Final 7/11/2022 Approved HORACE FULTZ
Smoke Detectors 7/11/2022 Approved HORACE FULTZ