4230 N VAN NUYS BLVD 91423
Certificate Information: 4230 N VAN NUYS BLVD 91423
- Application / Permit
- 20014-10000-03781
- Plan Check / Job No.
- B20LA15853
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT (E) DETACHED GARAGE TO ACCESSORY DWELLING UNIT WITH ADDITION (13'-0" X 24'-1")
- Permit Issued
- Issued on 8/10/2021
- Issuing Office
- Current Status
- CofO Issued on 5/1/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 9/3/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 9/9/2020 | STANLEY RAAP |
| Corrections Issued | 9/9/2020 | STANLEY RAAP |
| Applicant returned to address corrections | 12/9/2020 | LUKE GONZALES |
| Plan Check Approved | 7/3/2021 | FARSHAD ALIMOHAMADI |
| Building Plans Picked Up | 7/13/2021 | APPLICANT |
| Issued | 8/10/2021 | APPLICANT |
| CofO in Progress | 3/27/2024 | ARAM AVAKIAN |
| Permit Finaled | 5/1/2024 | DANIEL SANCHEZ |
| CofO Issued | 5/1/2024 | DANIEL SANCHEZ |
| Permit Finaled | 5/1/2024 | DANIEL SANCHEZ |
Permit Application Clearance Information
| Grading Pre-Inspection | Cleared | 12/3/2020 | BARTON HOLMES |
| Construction near power lines | Cleared | 12/24/2020 | RIDWAN HARDY |
| Low Impact Development | Cleared | 6/2/2021 | JORGE MEJIA LEMUS |
| Address approval | Cleared | 6/8/2021 | CARLOS AGUILERA |
| Eng Process Fee Ord 176,300 | Cleared | 6/9/2021 | CARLOS AGUILERA |
| Sewer availability | Cleared | 6/9/2021 | CARLOS AGUILERA |
| Roof/Waste drainage to street | Cleared | 6/14/2021 | CARLOS AGUILERA |
| GPI Written Notices | Cleared | 7/3/2021 | STANLEY RAAP |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Almalla,, Dean; Lic. No.: C58024 | 15053 VENTURA BLVD STE 205 SHERMAN OAKS, CA 91403 |
Inspector Information
| JOEL ORDAZ, (213) 252-3049 | Office Hours: 7:00-8:00 AM MON-FRI |
| PTOLEMY HILL, (213) 252-3049 | Office Hours: 7:00-8:00 AM MON-FRI |
| ARAM AVAKIAN, (213) 252-3049 | Office Hours: 7:00-8:00 AM MON-FRI |
| EDMOND DECKERT, (213) 252-3049 | Office Hours: 7:00-8:00 AM MON-FRI |
| TIMOTHY KEY, (213) 252-3049 | Office Hours: 7:00-8:00 AM MON-FRI |
| ROBERT CHAVEZ, (213) 252-3049 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Sewer | 4/18/2023 | Corrections Issued | MISAEL ESPARZA |
| Deputy Drilled-In Anchors | 4/26/2023 | Conditional Approval | MICHAEL SMITH |
| Sewer | 4/26/2023 | Approved | MATTHEW NELSON |
| Footing/Foundation/Slab | 5/1/2023 | Corrections Issued | MATTHEW NELSON |
| Footing/Foundation/Slab | 5/3/2023 | Approved | PATRICK LIEBREGT |
| Floor/Roof Diaphrgm/Shear Wall | 6/30/2023 | Partial Approval | PATRICK LIEBREGT |
| BUILDING-Rough-Frame | 7/11/2023 | Not Ready for Inspection | JOEL ORDAZ |
| Floor/Roof Diaphrgm/Shear Wall | 7/11/2023 | Approved | JOEL ORDAZ |
| Green Building Rough | 7/11/2023 | Not Ready for Inspection | JOEL ORDAZ |
| BUILDING-Rough-Frame | 7/28/2023 | Partial Approval | JOEL ORDAZ |
| ELECTRICAL-Rough | 7/28/2023 | Approved | JOEL ORDAZ |
| Green Building Rough | 7/28/2023 | Not Ready for Inspection | JOEL ORDAZ |
| PLUMBING-Rough | 7/28/2023 | Approved | JOEL ORDAZ |
| Shower Pan | 7/28/2023 | Approved | JOEL ORDAZ |
| HVAC-Rough | 8/8/2023 | Corrections Issued | PATRICK LIEBREGT |
| Insulation | 8/8/2023 | Approved | PATRICK LIEBREGT |
| HVAC-Rough | 8/18/2023 | Approved | JOEL ORDAZ |
| Drywall Nailing | 8/28/2023 | Approved | PATRICK LIEBREGT |
| Green Building Rough | 8/28/2023 | Approved | PATRICK LIEBREGT |
| Pre-Inspection | 8/28/2023 | Corrections Issued | PATRICK LIEBREGT |
| Interior/Exterior Lathing | 9/5/2023 | Corrections Issued | PATRICK LIEBREGT |
| Floor/Roof Diaphrgm/Shear Wall | 10/5/2023 | Approved | PATRICK LIEBREGT |
| BUILDING-Rough-Frame | 3/15/2024 | Approved | ARAM AVAKIAN |
| Final | 3/15/2024 | Corrections Issued | ARAM AVAKIAN |
| Green Building Final | 3/15/2024 | Approved | ARAM AVAKIAN |
| SGSOV-Seismic Gas S/O Valve | 3/15/2024 | SGSOV Not Ready | ARAM AVAKIAN |
| Smoke Detectors | 3/15/2024 | Approved | ARAM AVAKIAN |
| Final | 3/26/2024 | OK to Issue CofO | ARAM AVAKIAN |
| SGSOV-Seismic Gas S/O Valve | 3/26/2024 | SGSOV Approved | ARAM AVAKIAN |