1434 S HAUSER BLVD 90019
Certificate Information: 1434 S HAUSER BLVD 90019
- Application / Permit
- 20014-10000-03759
- Plan Check / Job No.
- B20LA15796
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (2) Duplex
- Work Description
- LAUNDRY ROOM ADDITION (7 ft x 9ft) TO REAR OF (E) Duplex.
- Permit Issued
- Issued on 2/12/2021
- Issuing Office
- Current Status
- CofO Issued on 2/25/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 9/1/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 9/4/2020 | TSE MING HUANG |
| Corrections Issued | 9/4/2020 | TSE MING HUANG |
| Applicant returned to address corrections | 9/8/2020 | TSE MING HUANG |
| Applicant returned to address corrections | 9/23/2020 | SAMUEL GONZALEZ |
| Applicant returned to address corrections | 10/12/2020 | SINA KHOSRAVI |
| Applicant returned to address corrections | 11/4/2020 | CRISTINA SALAZAR |
| Applicant returned to address corrections | 11/17/2020 | JESSE JIMENEZ |
| Applicant returned to address corrections | 12/7/2020 | RICARDO RAMIREZ |
| Applicant returned to address corrections | 1/7/2021 | SAMUEL GONZALEZ |
| Plan Check Approved | 1/27/2021 | ADAM HEGAZI |
| Building Plans Picked Up | 2/2/2021 | APPLICANT |
| Issued | 2/12/2021 | APPLICANT |
| CofO in Progress | 2/22/2022 | GLEN RAND |
| Permit Finaled | 2/25/2022 | BRUCE TODD |
| CofO Issued | 2/25/2022 | BRUCE TODD |
| Permit Finaled | 2/25/2022 | BRUCE TODD |
Permit Application Clearance Information
| Roof/Waste drainage to street | Cleared | 10/5/2020 | CELINA MORENO |
| Sewer availability | Cleared | 10/5/2020 | CELINA MORENO |
| Eng Process Fee Ord 176,300 | Cleared | 10/6/2020 | CELINA MORENO |
| Tenant Habitability Plan | Cleared | 10/26/2020 | MICHAEL GREGERSON |
Contact Information
| Contractor | Alpha Build & Design Inc; Lic. No.: 398659-B | 611 WILSHIRE BLVD #1416 LOS ANGELES, CA 90017 |
| Engineer | Cooke,, Conway Cecil; Lic. No.: S5524 | 34658 LINDA ROSEA RD TEMECULA, CA 92592 |
Inspector Information
| LUIS CORRAL, (213) 252-3964 | Office Hours: 7:00-8:00 AM MON-FRI |
| DONALD WONG, (213) 252-3964 | Office Hours: 7:00-8:00 AM MON-FRI |
| KIM DOEPPING, (213) 252-3964 | Office Hours: 7:00-8:00 AM MON-FRI |
| WILLIAM MICHALAK, (213) 252-3964 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 3/17/2021 | Corrections Issued | GLEN RAND |
| Excavation/Setback/Form/Re-Bar | 3/19/2021 | Approved | GLEN RAND |
| BUILDING-Rough-Frame | 5/20/2021 | Partial Approval | GLEN RAND |
| Green Building Rough | 5/20/2021 | Not Ready for Inspection | GLEN RAND |
| METHANE-Rough | 5/20/2021 | Approved | GLEN RAND |
| BUILDING-Rough-Frame | 6/4/2021 | Corrections Issued | GLEN RAND |
| ELECTRICAL-Rough | 7/12/2021 | Partial Approval | WILLIAM MICHALAK |
| PLUMBING-Rough | 7/12/2021 | Partial Approval | WILLIAM MICHALAK |
| BUILDING-Rough-Frame | 7/15/2021 | Corrections Issued | GLEN RAND |
| Green Building Rough | 7/15/2021 | Approved | GLEN RAND |
| Insulation | 7/15/2021 | Approved | GLEN RAND |
| Floor/Roof Diaphrgm/Shear Wall | 7/20/2021 | Approved | GLEN RAND |
| Underground Mechanical | 7/20/2021 | Corrections Issued | GLEN RAND |
| Drywall Nailing | 7/21/2021 | Approved | GLEN RAND |
| Interior/Exterior Lathing | 9/2/2021 | Approved | WILLIAM MICHALAK |
| BUILDING-Rough-Frame | 9/10/2021 | Corrections Issued | WILLIAM MICHALAK |
| Final | 9/10/2021 | Not Ready for Inspection | WILLIAM MICHALAK |
| Footing/Foundation/Slab | 9/10/2021 | Not Ready for Inspection | WILLIAM MICHALAK |
| Green Building Final | 9/10/2021 | Not Ready for Inspection | WILLIAM MICHALAK |
| METHANE-Barrier | 9/10/2021 | Not Ready for Inspection | WILLIAM MICHALAK |
| METHANE-Subgrade | 9/10/2021 | Not Ready for Inspection | WILLIAM MICHALAK |
| Smoke Detectors | 9/10/2021 | Not Ready for Inspection | WILLIAM MICHALAK |
| Pre-Inspection | 9/17/2021 | Corrections Issued | GLEN RAND |
| ELECTRICAL-Final | 9/21/2021 | Approved | GLEN RAND |
| BUILDING-Rough-Frame | 9/24/2021 | Corrections Issued | GLEN RAND |
| Footing/Foundation/Slab | 9/24/2021 | Corrections Issued | GLEN RAND |
| Gas Test | 9/24/2021 | Corrections Issued | GLEN RAND |
| Green Building Final | 9/24/2021 | Not Ready for Inspection | GLEN RAND |
| METHANE-Barrier | 9/24/2021 | Approved | GLEN RAND |
| METHANE-Subgrade | 9/24/2021 | Approved | GLEN RAND |
| Smoke Detectors | 9/24/2021 | Approved | GLEN RAND |
| Pre-Inspection | 9/27/2021 | Conditional Approval | GLEN RAND |
| Wood Frame | 9/30/2021 | Partial Approval | GLEN RAND |
| ELECTRICAL-Rough | 10/6/2021 | Corrections Issued | GLEN RAND |
| Footing/Foundation/Slab | 10/7/2021 | Approved | GLEN RAND |
| Wood Frame | 10/14/2021 | Approved | GLEN RAND |
| BUILDING-Rough-Frame | 10/25/2021 | Approved | GLEN RAND |
| Final | 10/28/2021 | Corrections Issued | GLEN RAND |
| Green Building Final | 10/28/2021 | Corrections Issued | GLEN RAND |
| Final | 11/9/2021 | Corrections Issued | GLEN RAND |
| Final | 11/10/2021 | OK to Issue CofO | GLEN RAND |
| Green Building Final | 11/10/2021 | Approved | GLEN RAND |