4927 N COLLIS AVE 90032

Certificate Information: 4927 N COLLIS AVE 90032

Application / Permit
20014-10000-03757
Plan Check / Job No.
B20LA15794
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
CONVERT (E) CRAWLSPACE INTO 2 BEDROOMS, 1-BATHROOM FOR (E) 1 STORY SFD W/ ATTACHED GARAGE
Permit Issued
Issued on 9/15/2022
Issuing Office
Current Status
CofO Issued on 12/5/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 2/10/2021 APPLICANT
Assigned to Plan Check Engineer 2/25/2021 HERNAN ARREOLA
Corrections Issued 3/16/2021 HERNAN ARREOLA
Quality Review Completed 3/19/2021 JASON HEALEY
Building Plans Picked Up 3/25/2021 APPLICANT
Applicant returned to address corrections 9/17/2021 HERNAN ARREOLA
Plan Check Approved 9/14/2022 HERNAN ARREOLA
Issued 9/15/2022 APPLICANT
CofO in Progress 11/21/2023 ROY SPAULDING
CofO Issued 12/5/2023 DEROLD HAUFF
Permit Finaled 12/5/2023 DEROLD HAUFF

Permit Application Clearance Information

BHO/Hillside ordinance Cleared 10/14/2021 RENZ SORIANO
BHO/Hillside ordinance Cleared 10/14/2021 RENZ SORIANO
BHO/Hillside ordinance Cleared 10/14/2021 RENZ SORIANO
BHO/Hillside ordinance Cleared 10/14/2021 RENZ SORIANO
BHO/Hillside ordinance Cleared 10/14/2021 RENZ SORIANO
Eng Process Fee Ord 176,300 Cleared 10/25/2021 PAMELA TENEZA
Sewer availability Cleared 10/25/2021 PAMELA TENEZA
GPI Written Notices Cleared 8/18/2022 HERNAN ARREOLA
Grading Pre-Inspection Cleared 8/18/2022 HERNAN ARREOLA
"D" conditions Cleared 8/29/2022 SHASHA YU
"Q" conditions Cleared 8/29/2022 SHASHA YU

Contact Information

Contractor Owner-Builder       ,
Engineer Cooke,, Conway Cecil; Lic. No.: S5524 34658 LINDA ROSEA RD      TEMECULA, CA 92592

Inspector Information

No Data Available.

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 11/17/2022 Partial Approval AMY COLIN
Excavation/Setback/Form/Re-Bar 11/22/2022 Corrections Issued AMY COLIN
Excavation/Setback/Form/Re-Bar 12/1/2022 Approved AMY COLIN
Excavation/Setback/Form/Re-Bar 12/28/2022 Approved AMY COLIN
Footing/Foundation/Slab 12/28/2022 Approved AMY COLIN
PLUMBING-Rough 12/28/2022 Partial Approval AMY COLIN
Deputy Drilled-In Anchors 1/26/2023 Conditional Approval AMY COLIN
BUILDING-Rough-Frame 1/30/2023 Not Ready for Inspection AMY COLIN
Green Building Rough 1/30/2023 Not Ready for Inspection AMY COLIN
BUILDING-Rough-Frame 3/20/2023 Corrections Issued AMY COLIN
ELECTRICAL-Rough 3/20/2023 Approved AMY COLIN
Green Building Rough 3/20/2023 Approved AMY COLIN
PLUMBING-Rough 3/20/2023 Corrections Issued AMY COLIN
Rough-Elec/Plmb/HVAC 3/20/2023 Not Ready for Inspection AMY COLIN
Insulation 5/4/2023 Partial Inspection AMY COLIN
PLUMBING-Rough 5/4/2023 Approved AMY COLIN
Special/Order Compliance 5/4/2023 Corrections Issued AMY COLIN
Deputy Drilled-In Anchors 5/23/2023 Conditional Approval AMY COLIN
Excavation/Setback/Form/Re-Bar 5/24/2023 Partial Approval AMY COLIN
Excavation/Setback/Form/Re-Bar 6/1/2023 Approved AMY COLIN
Drywall Nailing 6/13/2023 Approved AMY COLIN
Interior/Exterior Lathing 9/22/2023 Approved BRENDAN MORELLI
BUILDING-Rough-Frame 10/27/2023 Approved AMY COLIN
Final 10/27/2023 Corrections Issued AMY COLIN
Green Building Final 10/27/2023 Approved AMY COLIN
SGSOV-Seismic Gas S/O Valve 10/27/2023 SGSOV Not Ready AMY COLIN
Smoke Detectors 10/27/2023 Partial Inspection AMY COLIN
Final 11/20/2023 OK to Issue CofO ROY SPAULDING
SGSOV-Seismic Gas S/O Valve 11/20/2023 SGSOV Approved ROY SPAULDING
Smoke Detectors 11/20/2023 Approved ROY SPAULDING