1243 N DRUMM AVE 90744

Certificate Information: 1243 N DRUMM AVE 90744

Application / Permit
20014-10000-03752
Plan Check / Job No.
B20LA15765
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
2ND FLR ADDITION ABOVE (E) TWO-CAR GARAGE FOR (N) DETACHED ADU PER ORDINANCE
Permit Issued
Issued on 8/19/2021
Issuing Office
Current Status
Issued on 8/19/2021
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 10/21/2020 APPLICANT
Assigned to Plan Check Engineer 11/12/2020 AUNG SOE
Corrections Issued 11/24/2020 CARLOS MONTES
Quality Review Completed 12/7/2020 WING SUEN
Building Plans Picked Up 12/18/2020 APPLICANT
Applicant returned to address corrections 3/11/2021 CARLOS MONTES
Applicant returned to address corrections 5/13/2021 CARLOS MONTES
Applicant returned to address corrections 6/14/2021 CARLOS MONTES
Applicant returned to address corrections 7/22/2021 CARLOS MONTES
Plan Check Approved 7/26/2021 CARLOS MONTES
Issued 8/19/2021 APPLICANT

Permit Application Clearance Information

Address approval Cleared 2/22/2021 CHINH DINH
Clean Up Green Up Cleared 2/23/2021 RUBEN VASQUEZ
ZA Case Cleared 2/23/2021 RUBEN VASQUEZ
ZA Case Cleared 2/23/2021 RUBEN VASQUEZ
ZA Case Cleared 2/23/2021 RUBEN VASQUEZ
Eng Process Fee Ord 176,300 Cleared 3/5/2021 CHINH DINH
Sewer availability Cleared 3/5/2021 CHINH DINH
Low Impact Development Cleared 6/23/2021 SUNG JOON WON
Roof/Waste drainage to street Cleared 7/23/2021 JOSE HERNANDEZ

Contact Information

Contractor Owner-Builder       ,
Engineer Cooke,, Conway Cecil; Lic. No.: S5524 34658 LINDA ROSEA RD      TEMECULA, CA 92592

Inspector Information

EUGENE CASSIDY, (310) 548-2508 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 9/10/2021 Approved JOHN KLARIN
Footing/Foundation/Slab 9/10/2021 Approved JOHN KLARIN
METHANE-Barrier 9/10/2021 Approved JOHN KLARIN
METHANE-Subgrade 9/10/2021 Approved JOHN KLARIN
Floor/Roof Diaphrgm/Shear Wall 9/23/2021 Corrections Issued JOHN KLARIN
Floor/Roof Diaphrgm/Shear Wall 10/4/2021 Corrections Issued JOHN KLARIN
Floor/Roof Diaphrgm/Shear Wall 10/14/2021 Partial Approval JOHN KLARIN
ELECTRICAL-Rough 11/23/2021 Approved JOHN KLARIN
Gas Test 11/23/2021 Approved JOHN KLARIN
HVAC-Rough 11/23/2021 Approved JOHN KLARIN
PLUMBING-Rough 11/23/2021 Approved JOHN KLARIN
Shower Pan 11/23/2021 Approved JOHN KLARIN
BUILDING-Rough-Frame 12/1/2021 Corrections Issued JOHN KLARIN
Insulation 12/1/2021 Conditional Approval JOHN KLARIN
BUILDING-Rough-Frame 1/20/2022 Approved EUGENE CASSIDY
Green Building Rough 1/20/2022 Approved EUGENE CASSIDY
Insulation 1/20/2022 Approved EUGENE CASSIDY
METHANE-Rough 1/20/2022 Approved EUGENE CASSIDY
Drywall Nailing 2/2/2022 Approved EUGENE CASSIDY
PLUMBING-Final 4/21/2023 Corrections Issued EUGENE CASSIDY
PLUMBING-Rough 4/21/2023 Approved EUGENE CASSIDY
Final 5/22/2023 Corrections Issued EUGENE CASSIDY
Green Building Final 5/22/2023 Not Ready for Inspection EUGENE CASSIDY
SGSOV-Seismic Gas S/O Valve 5/22/2023 SGSOV Approved EUGENE CASSIDY
Smoke Detectors 5/22/2023 Approved EUGENE CASSIDY
Final 2/3/2026 Corrections Issued EUGENE CASSIDY
Green Building Final 2/3/2026 Approved EUGENE CASSIDY