1525 W 222ND ST 90501

Certificate Information: 1525 W 222ND ST 90501

Application / Permit
20014-10000-03743
Plan Check / Job No.
B20LA15719
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
ADDITION AT REAR OF HOME TO INCLUDE A NEW MASTER BEDROOM. ALL WORK PER WFPP.
Permit Issued
Issued on 10/12/2020
Issuing Office
Current Status
CofO Issued on 3/5/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 9/8/2020 APPLICANT
Assigned to Plan Check Engineer 9/11/2020 FARSHAD ALIMOHAMADI
Corrections Issued 9/15/2020 FARSHAD ALIMOHAMADI
Applicant returned to address corrections 9/30/2020 RICARDO RAMIREZ
Issued 10/12/2020 APPLICANT
Building Plans Picked Up 11/4/2020 APPLICANT
CofO in Progress 6/24/2021 JOHN KLARIN
Permit Finaled 3/5/2022 DEROLD HAUFF
CofO Issued 3/5/2022 DEROLD HAUFF
Permit Finaled 3/5/2022 DEROLD HAUFF

Permit Application Clearance Information

Roof/Waste drainage to street Cleared 9/18/2020 ERIK BEASLEY
Eng Process Fee Ord 176,300 Cleared 10/6/2020 ERIK BEASLEY

Contact Information

Contractor Owner-Builder       ,

Inspector Information

EUGENE CASSIDY, (310) 548-2508 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 12/2/2020 Approved JOHN KLARIN
METHANE-Barrier 12/2/2020 Approved JOHN KLARIN
METHANE-Subgrade 12/2/2020 Approved JOHN KLARIN
Floor/Roof Diaphrgm/Shear Wall 1/21/2021 Corrections Issued JOHN KLARIN
BUILDING-Rough-Frame 3/16/2021 Approved JOHN KLARIN
ELECTRICAL-Rough 3/16/2021 Approved JOHN KLARIN
Floor/Roof Diaphrgm/Shear Wall 3/16/2021 Approved JOHN KLARIN
Green Building Rough 3/16/2021 Approved JOHN KLARIN
METHANE-Rough 3/16/2021 Approved JOHN KLARIN
PLUMBING-Rough 3/16/2021 Approved JOHN KLARIN
Insulation 3/26/2021 Approved JOHN KLARIN
Shower Pan 3/26/2021 Approved JOHN KLARIN
Drywall Nailing 4/7/2021 Approved SABAS ALONSO
Interior/Exterior Lathing 4/7/2021 Approved SABAS ALONSO
Final 5/28/2021 Corrections Issued JOHN KLARIN
Green Building Final 5/28/2021 Corrections Issued JOHN KLARIN
SGSOV-Seismic Gas S/O Valve 5/28/2021 SGSOV Approved JOHN KLARIN
Smoke Detectors 5/28/2021 Corrections Issued JOHN KLARIN
Final 6/8/2021 Corrections Issued JOHN KLARIN
Green Building Final 6/8/2021 Not Ready for Inspection JOHN KLARIN
Smoke Detectors 6/8/2021 Conditional Approval JOHN KLARIN
ELECTRICAL-Final 6/23/2021 Approved JOHN KLARIN
Final 6/23/2021 OK to Issue CofO JOHN KLARIN
Green Building Final 6/23/2021 Approved JOHN KLARIN
HVAC-Final 6/23/2021 Approved JOHN KLARIN
PLUMBING-Final 6/23/2021 Approved JOHN KLARIN
Smoke Detectors 6/23/2021 Approved JOHN KLARIN