1525 W 222ND ST 90501
Certificate Information: 1525 W 222ND ST 90501
- Application / Permit
- 20014-10000-03743
- Plan Check / Job No.
- B20LA15719
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- ADDITION AT REAR OF HOME TO INCLUDE A NEW MASTER BEDROOM. ALL WORK PER WFPP.
- Permit Issued
- Issued on 10/12/2020
- Issuing Office
- Current Status
- CofO Issued on 3/5/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 9/8/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 9/11/2020 | FARSHAD ALIMOHAMADI |
| Corrections Issued | 9/15/2020 | FARSHAD ALIMOHAMADI |
| Applicant returned to address corrections | 9/30/2020 | RICARDO RAMIREZ |
| Issued | 10/12/2020 | APPLICANT |
| Building Plans Picked Up | 11/4/2020 | APPLICANT |
| CofO in Progress | 6/24/2021 | JOHN KLARIN |
| Permit Finaled | 3/5/2022 | DEROLD HAUFF |
| CofO Issued | 3/5/2022 | DEROLD HAUFF |
| Permit Finaled | 3/5/2022 | DEROLD HAUFF |
Permit Application Clearance Information
| Roof/Waste drainage to street | Cleared | 9/18/2020 | ERIK BEASLEY |
| Eng Process Fee Ord 176,300 | Cleared | 10/6/2020 | ERIK BEASLEY |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| EUGENE CASSIDY, (310) 548-2508 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 12/2/2020 | Approved | JOHN KLARIN |
| METHANE-Barrier | 12/2/2020 | Approved | JOHN KLARIN |
| METHANE-Subgrade | 12/2/2020 | Approved | JOHN KLARIN |
| Floor/Roof Diaphrgm/Shear Wall | 1/21/2021 | Corrections Issued | JOHN KLARIN |
| BUILDING-Rough-Frame | 3/16/2021 | Approved | JOHN KLARIN |
| ELECTRICAL-Rough | 3/16/2021 | Approved | JOHN KLARIN |
| Floor/Roof Diaphrgm/Shear Wall | 3/16/2021 | Approved | JOHN KLARIN |
| Green Building Rough | 3/16/2021 | Approved | JOHN KLARIN |
| METHANE-Rough | 3/16/2021 | Approved | JOHN KLARIN |
| PLUMBING-Rough | 3/16/2021 | Approved | JOHN KLARIN |
| Insulation | 3/26/2021 | Approved | JOHN KLARIN |
| Shower Pan | 3/26/2021 | Approved | JOHN KLARIN |
| Drywall Nailing | 4/7/2021 | Approved | SABAS ALONSO |
| Interior/Exterior Lathing | 4/7/2021 | Approved | SABAS ALONSO |
| Final | 5/28/2021 | Corrections Issued | JOHN KLARIN |
| Green Building Final | 5/28/2021 | Corrections Issued | JOHN KLARIN |
| SGSOV-Seismic Gas S/O Valve | 5/28/2021 | SGSOV Approved | JOHN KLARIN |
| Smoke Detectors | 5/28/2021 | Corrections Issued | JOHN KLARIN |
| Final | 6/8/2021 | Corrections Issued | JOHN KLARIN |
| Green Building Final | 6/8/2021 | Not Ready for Inspection | JOHN KLARIN |
| Smoke Detectors | 6/8/2021 | Conditional Approval | JOHN KLARIN |
| ELECTRICAL-Final | 6/23/2021 | Approved | JOHN KLARIN |
| Final | 6/23/2021 | OK to Issue CofO | JOHN KLARIN |
| Green Building Final | 6/23/2021 | Approved | JOHN KLARIN |
| HVAC-Final | 6/23/2021 | Approved | JOHN KLARIN |
| PLUMBING-Final | 6/23/2021 | Approved | JOHN KLARIN |
| Smoke Detectors | 6/23/2021 | Approved | JOHN KLARIN |