1357 N AVENUE 57 90042
Certificate Information: 1357 N AVENUE 57 90042
- Application / Permit
- 20014-10000-03742
- Plan Check / Job No.
- B20LA15703
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- ADDITION TO (E) SINGLE FAMILY DWELLING W/ATT GARAGE. ADDITION ON 1ST FLOOR UNDERNEATH EXISTING GARAGE, NEW DECK ON 2ND FLOOR
- Permit Issued
- Issued on 4/8/2021
- Issuing Office
- Current Status
- CofO Issued on 5/21/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 9/1/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 9/10/2020 | LAMAR DAVIS |
| Corrections Issued | 9/15/2020 | LAMAR DAVIS |
| Quality Review Completed | 9/25/2020 | TU HUA |
| Building Plans Picked Up | 9/28/2020 | APPLICANT |
| Plan Check Approved | 4/5/2021 | LAMAR DAVIS |
| Issued | 4/8/2021 | APPLICANT |
| CofO in Progress | 11/9/2021 | CRAIG VAUGHAN |
| CofO in Progress | 5/19/2022 | CRAIG VAUGHAN |
| Permit Finaled | 5/21/2022 | DEROLD HAUFF |
| CofO Issued | 5/21/2022 | DEROLD HAUFF |
| Permit Finaled | 5/21/2022 | DEROLD HAUFF |
Permit Application Clearance Information
| Grading Pre-Inspection | Cleared | 9/11/2020 | LAMAR DAVIS |
| BHO/Hillside ordinance | Cleared | 12/23/2020 | WALLIE JONG |
| BHO/Hillside ordinance | Cleared | 12/23/2020 | WALLIE JONG |
| BHO/Hillside ordinance | Cleared | 12/23/2020 | WALLIE JONG |
| BHO/Hillside ordinance | Cleared | 12/23/2020 | WALLIE JONG |
| BHO/Hillside ordinance | Cleared | 12/23/2020 | WALLIE JONG |
| Roof/Waste drainage to street | Cleared | 12/29/2020 | WALLIE JONG |
| Sewer availability | Cleared | 12/29/2020 | WALLIE JONG |
| Eng Process Fee Ord 176,300 | Cleared | 12/31/2020 | WALLIE JONG |
| Hydrant and Access approval | Cleared | 1/29/2021 | KURT CORRAL |
| ZA Case | Cleared | 3/16/2021 | TERRI OSBORNE |
| GPI Written Notices | Cleared | 3/20/2021 | ROBERT HUGHES |
| Miscellaneous | Cleared | 4/1/2021 | LAMAR DAVIS |
Contact Information
| Contractor | Opus Builders Inc; Lic. No.: 1059646-B | 213 N ORANGE STREET SUITE D GLENDALE, CA 91203 |
| Engineer | Acciani,, Mark; Lic. No.: C83929 | PO BOX 1390 RUNNING SPRINGS, CA 92382 |
| Engineer | Haro,, Ruben; Lic. No.: C72213 | 355 N LANTANA ST STE 492 CAMARILLO, CA 93010 |
| Geologist | George,, Richard Kevin; Lic. No.: EG2516 | 6588 ASA WAY RIVERSIDE, CA 925097233 |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 4/23/2021 | Partial Inspection | CRAIG VAUGHAN |
| Excavation/Setback/Form/Re-Bar | 5/26/2021 | Approved | CRAIG VAUGHAN |
| Footing/Foundation/Slab | 5/26/2021 | Partial Approval | CRAIG VAUGHAN |
| Underground Mechanical | 6/10/2021 | Partial Approval | CRAIG VAUGHAN |
| Wood Frame | 8/19/2021 | Partial Approval | CRAIG VAUGHAN |
| BUILDING-Rough-Frame | 8/23/2021 | Approved | CRAIG VAUGHAN |
| ELECTRICAL-Rough | 8/23/2021 | Approved | CRAIG VAUGHAN |
| Green Building Rough | 8/23/2021 | Approved | CRAIG VAUGHAN |
| HVAC-Rough | 8/23/2021 | Approved | CRAIG VAUGHAN |
| PLUMBING-Rough | 8/23/2021 | Approved | CRAIG VAUGHAN |
| Insulation | 8/26/2021 | Approved | CHARLES BOGHOSKHAN |
| Drywall Nailing | 9/7/2021 | Approved | HAMIK HARTOUNIAN |
| Interior/Exterior Lathing | 9/7/2021 | Conditional Approval | HAMIK HARTOUNIAN |
| Deck | 9/10/2021 | Not Ready for Inspection | CRAIG VAUGHAN |
| Interior/Exterior Lathing | 9/10/2021 | Corrections Issued | CRAIG VAUGHAN |
| Shower Pan | 9/10/2021 | Not Ready for Inspection | CRAIG VAUGHAN |
| Deck | 9/13/2021 | Not Ready for Inspection | CRAIG VAUGHAN |
| Interior/Exterior Lathing | 9/13/2021 | Partial Approval | CRAIG VAUGHAN |
| Shower Pan | 9/13/2021 | Not Ready for Inspection | CRAIG VAUGHAN |
| Shower Pan | 9/16/2021 | Approved | KATHRYN BUTTERWORTH |
| Deck | 9/24/2021 | Not Ready for Inspection | CRAIG VAUGHAN |
| Interior/Exterior Lathing | 9/28/2021 | Approved | CRAIG VAUGHAN |
| Final | 11/1/2021 | Not Ready for Inspection | OSVALDO PARAMO |
| Footing/Foundation/Slab | 11/1/2021 | Approved | OSVALDO PARAMO |
| Green Building Final | 11/1/2021 | Not Ready for Inspection | OSVALDO PARAMO |
| SGSOV-Seismic Gas S/O Valve | 11/1/2021 | SGSOV Not Ready | OSVALDO PARAMO |
| Smoke Detectors | 11/1/2021 | Not Ready for Inspection | OSVALDO PARAMO |
| Final | 11/4/2021 | Corrections Issued | CRAIG VAUGHAN |
| Green Building Final | 11/4/2021 | Approved | CRAIG VAUGHAN |
| SGSOV-Seismic Gas S/O Valve | 11/4/2021 | SGSOV Approved | CRAIG VAUGHAN |
| Smoke Detectors | 11/4/2021 | Approved | CRAIG VAUGHAN |
| ELECTRICAL-Final | 11/8/2021 | Approved | CRAIG VAUGHAN |
| Final | 11/8/2021 | OK to Issue CofO | CRAIG VAUGHAN |
| HVAC-Final | 11/8/2021 | Approved | CRAIG VAUGHAN |
| PLUMBING-Final | 11/8/2021 | Approved | CRAIG VAUGHAN |