2825 1/2 S 3RD AVE 90018

Certificate Information: 2825 1/2 S 3RD AVE 90018

Application / Permit
20014-10000-03716
Plan Check / Job No.
B20LA15690
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
DETACHED ACCESSORY DWELLING UNIT PER ORDINANCE
Permit Issued
Issued on 3/26/2021
Issuing Office
Current Status
CofO Issued on 7/9/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 8/31/2020 APPLICANT
Assigned to Plan Check Engineer 9/3/2020 AMIR DANAI
Corrections Issued 9/4/2020 AMIR DANAI
Applicant returned to address corrections 2/2/2021 FERNANDO FLORES
Building Plans Picked Up 2/3/2021 APPLICANT
Applicant returned to address corrections 2/16/2021 ADAM HEGAZI
Plan Check Approved 3/24/2021 ADAM HEGAZI
Plan Check Approved 3/26/2021 ADAM HEGAZI
Issued 3/26/2021 APPLICANT
CofO in Progress 5/23/2021 STUART CHAPMAN
Permit Finaled 7/9/2022 DEROLD HAUFF
CofO Issued 7/9/2022 DEROLD HAUFF
Permit Finaled 7/9/2022 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 9/21/2020 JEANIE LAM
Eng Process Fee Ord 176,300 Cleared 9/21/2020 JEANIE LAM
Roof/Waste drainage to street Cleared 9/21/2020 JEANIE LAM
Sewer availability Cleared 9/21/2020 JEANIE LAM
HPOZ Cleared 1/25/2021 MAX LODER
ZI Cleared 1/25/2021 MAX LODER
ZI Cleared 1/25/2021 MAX LODER

Contact Information

Contractor So Cal Construction Enterprises Inc; Lic. No.: 832488-B P O BOX 96      SAN GABRIEL, CA 91778

Inspector Information

JUSTIN HAWLEY, (213) 202-3432 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 3/31/2021 Approved STUART CHAPMAN
Pre-Inspection 3/31/2021 Approved STUART CHAPMAN
Floor/Roof Diaphrgm/Shear Wall 4/3/2021 Off-Hour Fees Due
Floor/Roof Diaphrgm/Shear Wall 4/3/2021 Partial Approval OSVALDO PARAMO
PLUMBING-Rough 4/3/2021 Partial Approval OSVALDO PARAMO
Underground Mechanical 4/3/2021 Off-Hour Fees Due
Floor/Roof Diaphrgm/Shear Wall 4/5/2021 Partial Approval STUART CHAPMAN
Excavation/Setback/Form/Re-Bar 4/6/2021 Not Ready for Inspection DAVID FEILER
Pre-Inspection 4/6/2021 Not Ready for Inspection DAVID FEILER
BUILDING-Rough-Frame 4/9/2021 Partial Approval SCOTT FINNILA
Floor/Roof Diaphrgm/Shear Wall 4/9/2021 Conditional Approval SCOTT FINNILA
Underground Mechanical 4/9/2021 Partial Approval SCOTT FINNILA
BUILDING-Rough-Frame 4/12/2021 Conditional Approval SABAS ALONSO
ELECTRICAL-Rough 4/12/2021 Approved SABAS ALONSO
Green Building Rough 4/12/2021 Approved SABAS ALONSO
Interior/Exterior Lathing 4/12/2021 Partial Approval SABAS ALONSO
PLUMBING-Rough 4/12/2021 Approved SABAS ALONSO
Insulation 4/13/2021 Conditional Approval JOAQUIN GREENOUGH
Interior/Exterior Lathing 4/13/2021 Partial Approval JOAQUIN GREENOUGH
Drywall Nailing 4/15/2021 Approved KATHRYN BUTTERWORTH
BUILDING-Rough-Frame 5/13/2021 Approved STUART CHAPMAN
Final 5/13/2021 Corrections Issued STUART CHAPMAN
Footing/Foundation/Slab 5/13/2021 Approved STUART CHAPMAN
Green Building Final 5/13/2021 Approved STUART CHAPMAN
METHANE-Barrier 5/13/2021 Approved STUART CHAPMAN
METHANE-Final 5/13/2021 Approved STUART CHAPMAN
METHANE-Rough 5/13/2021 Approved STUART CHAPMAN
METHANE-Subgrade 5/13/2021 Approved STUART CHAPMAN
SGSOV-Seismic Gas S/O Valve 5/13/2021 SGSOV Not Required STUART CHAPMAN
Service/Power Release 5/13/2021 Approved STUART CHAPMAN
Smoke Detectors 5/13/2021 Not Ready for Inspection STUART CHAPMAN
Verify Sprinkler Sign Off 5/13/2021 Approved STUART CHAPMAN
ELECTRICAL-Final 5/21/2021 Approved STUART CHAPMAN
Final 5/21/2021 OK to Issue CofO STUART CHAPMAN
HVAC-Final 5/21/2021 Approved STUART CHAPMAN
PLUMBING-Final 5/21/2021 Approved STUART CHAPMAN
Smoke Detectors 5/21/2021 Approved STUART CHAPMAN