Work Description
REMODEL AND SECOND STORY ADDITION TO EXISTING TWO STORY SINGLE FAMILY RESIDENCE 1 OF 4
Permit Issued
Issued on 5/4/2021
Issuing Office
Metro
Current Status
CofO Issued on 8/30/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 9/3/2020 APPLICANT
Assigned to Plan Check Engineer 10/1/2020 STARR CHEN
Corrections Issued 10/6/2020 STARR CHEN
Quality Review Completed 10/21/2020 HERNAN ARREOLA
Applicant returned to address corrections 11/19/2020 STARR CHEN
Applicant returned to address corrections 1/12/2021 STARR CHEN
Applicant returned to address corrections 1/13/2021 STARR CHEN
Plan Check Approved 4/23/2021 STARR CHEN
Issued 5/4/2021 APPLICANT
Building Plans Picked Up 5/5/2021 APPLICANT
CofO in Progress 8/26/2022 JUAN VALENZUELA
Permit Finaled 8/30/2022 DANIEL ORRANTE
CofO Issued 8/30/2022 DANIEL ORRANTE
Permit Finaled 8/30/2022 DANIEL ORRANTE

Permit Application Clearance Information

BHO/Hillside ordinance Cleared 11/12/2020 DINAH GARIN
BHO/Hillside ordinance Cleared 11/12/2020 DINAH GARIN
BHO/Hillside ordinance Cleared 11/12/2020 DINAH GARIN
BHO/Hillside ordinance Cleared 11/12/2020 DINAH GARIN
BHO/Hillside ordinance Cleared 11/12/2020 DINAH GARIN
Eng Process Fee Ord 176,300 Cleared 11/19/2020 DINAH GARIN
Sewer availability Cleared 11/19/2020 DINAH GARIN
GPI Written Notices Cleared 1/12/2021 STARR CHEN
Grading Pre-Inspection Cleared 1/12/2021 STARR CHEN
Low Impact Development Cleared 3/16/2021 SARAH YOUSSEF
Roof/Waste drainage to street Cleared 3/16/2021 DINAH GARIN

Contact Information

Contractor Caa General Contractor Inc; Lic. No.: 696570-B 5901 COLFAX AVE      NORTH HOLLYWOOD, CA 91601
Engineer Baad,, Katherine Firestone; Lic. No.: C64669 5232 ZAKON RD      TORRANCE, CA 90505
Engineer Barajas,, George Luis; Lic. No.: L8399 3635 SHADOW GROVE RD      PASADENA, CA 91107
Engineer Howe,, Carl William; Lic. No.: C44773 4358 SEPULVEDA BLVD      CULVER CITY, CA 90230
Engineer Tsai,, Steve Shi-Shen; Lic. No.: GE2268 1545 VICTORY BLVD      GLENDALE, CA 91201
Geologist Carnegie,, Vincent John; Lic. No.: EG1608 P.O. BOX 5444      GLENDALE, CA 912012036

Inspector Information

KEVIN SARGSYAN, (310) 914-3889 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 6/8/2021 Conditional Approval ROBERT SHELLY
Footing/Foundation/Slab 6/24/2021 Partial Approval JUAN VALENZUELA
Footing/Foundation/Slab 7/6/2021 Partial Approval JUAN VALENZUELA
Footing/Foundation/Slab 7/13/2021 Partial Approval JUAN VALENZUELA
Footing/Foundation/Slab 7/26/2021 Not Ready for Inspection JUAN VALENZUELA
Footing/Foundation/Slab 7/29/2021 Partial Approval JUAN VALENZUELA
Floor/Roof Diaphrgm/Shear Wall 8/2/2021 Partial Approval JUAN VALENZUELA
Green Building Rough 8/2/2021 Not Ready for Inspection JUAN VALENZUELA
Verify Sprinkler Sign Off 8/2/2021 Not Ready for Inspection JUAN VALENZUELA
Deputy Wood Construction 8/16/2021 Conditional Approval JUAN VALENZUELA
Floor/Roof Diaphrgm/Shear Wall 8/17/2021 Partial Approval JUAN VALENZUELA
Green Building Rough 8/17/2021 Not Ready for Inspection JUAN VALENZUELA
Verify Sprinkler Sign Off 8/17/2021 Not Ready for Inspection JUAN VALENZUELA
Special/Order Compliance 8/27/2021 Partial Approval JESUS RODRIGUEZ
Underground Mechanical 8/27/2021 Partial Approval JUAN VALENZUELA
Footing/Foundation/Slab 9/3/2021 Partial Approval BRENDAN LOONEY
ELECTRICAL-Rough 10/13/2021 Approved JUAN VALENZUELA
HVAC-Rough 10/13/2021 Partial Approval JUAN VALENZUELA
PLUMBING-Rough 10/19/2021 Approved JUAN VALENZUELA
Deputy Wood Construction 10/22/2021 Conditional Approval JUAN VALENZUELA
BUILDING-Rough-Frame 10/26/2021 Partial Approval JUAN VALENZUELA
Green Building Rough 10/26/2021 Not Ready for Inspection JUAN VALENZUELA
Verify Sprinkler Sign Off 10/26/2021 Approved JUAN VALENZUELA
BUILDING-Rough-Frame 11/12/2021 Approved ANDREW NAVE
Green Building Rough 11/12/2021 Approved ANDREW NAVE
Insulation 11/19/2021 Approved STEPHANIE SWANSON
Interior/Exterior Lathing 11/19/2021 Partial Approval STEPHANIE SWANSON
PLUMBING-Rough 11/19/2021 Approved STEPHANIE SWANSON
Shower Pan 11/24/2021 Approved DEANDRE HOFFMAN
Drywall Nailing 12/2/2021 Approved JUAN VALENZUELA
Interior/Exterior Lathing 12/7/2021 Approved JUAN VALENZUELA
Underground Mechanical 1/31/2022 Partial Approval JUAN VALENZUELA
Underground Mechanical 2/14/2022 Partial Approval JUAN VALENZUELA
Gas Test 4/6/2022 Approved JUAN VALENZUELA
Service/Power Release 4/7/2022 Not Ready for Inspection JUAN VALENZUELA
ELECTRICAL-Final 5/9/2022 Approved JUAN VALENZUELA
Service/Power Release 5/9/2022 Approved JUAN VALENZUELA
HVAC-Final 6/1/2022 Corrections Issued JUAN VALENZUELA
HVAC-Final 7/19/2022 Not Ready for Inspection KEVIN SARGSYAN
PLUMBING-Final 7/19/2022 Corrections Issued KEVIN SARGSYAN
HVAC-Final 8/10/2022 Approved JUAN VALENZUELA
PLUMBING-Final 8/10/2022 Approved JUAN VALENZUELA
Final 8/24/2022 Conditional Approval JUAN VALENZUELA
Footing/Foundation/Slab 8/24/2022 Approved JUAN VALENZUELA
Green Building Final 8/24/2022 Approved JUAN VALENZUELA
SGSOV-Seismic Gas S/O Valve 8/24/2022 SGSOV Approved JUAN VALENZUELA
Smoke Detectors 8/24/2022 Approved JUAN VALENZUELA