2500 N PESQUERA DR 90049
Certificate Information: 2500 N PESQUERA DR 90049
- Application / Permit
- 20014-10000-03715
- Plan Check / Job No.
- B20LA15685
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- REMODEL AND SECOND STORY ADDITION TO EXISTING TWO STORY SINGLE FAMILY RESIDENCE 1 OF 4
- Permit Issued
- Issued on 5/4/2021
- Issuing Office
- Metro
- Current Status
- CofO Issued on 8/30/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 9/3/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 10/1/2020 | STARR CHEN |
| Corrections Issued | 10/6/2020 | STARR CHEN |
| Quality Review Completed | 10/21/2020 | HERNAN ARREOLA |
| Applicant returned to address corrections | 11/19/2020 | STARR CHEN |
| Applicant returned to address corrections | 1/12/2021 | STARR CHEN |
| Applicant returned to address corrections | 1/13/2021 | STARR CHEN |
| Plan Check Approved | 4/23/2021 | STARR CHEN |
| Issued | 5/4/2021 | APPLICANT |
| Building Plans Picked Up | 5/5/2021 | APPLICANT |
| CofO in Progress | 8/26/2022 | JUAN VALENZUELA |
| Permit Finaled | 8/30/2022 | DANIEL ORRANTE |
| CofO Issued | 8/30/2022 | DANIEL ORRANTE |
| Permit Finaled | 8/30/2022 | DANIEL ORRANTE |
Permit Application Clearance Information
| BHO/Hillside ordinance | Cleared | 11/12/2020 | DINAH GARIN |
| BHO/Hillside ordinance | Cleared | 11/12/2020 | DINAH GARIN |
| BHO/Hillside ordinance | Cleared | 11/12/2020 | DINAH GARIN |
| BHO/Hillside ordinance | Cleared | 11/12/2020 | DINAH GARIN |
| BHO/Hillside ordinance | Cleared | 11/12/2020 | DINAH GARIN |
| Eng Process Fee Ord 176,300 | Cleared | 11/19/2020 | DINAH GARIN |
| Sewer availability | Cleared | 11/19/2020 | DINAH GARIN |
| GPI Written Notices | Cleared | 1/12/2021 | STARR CHEN |
| Grading Pre-Inspection | Cleared | 1/12/2021 | STARR CHEN |
| Low Impact Development | Cleared | 3/16/2021 | SARAH YOUSSEF |
| Roof/Waste drainage to street | Cleared | 3/16/2021 | DINAH GARIN |
Contact Information
| Contractor | Caa General Contractor Inc; Lic. No.: 696570-B | 5901 COLFAX AVE NORTH HOLLYWOOD, CA 91601 |
| Engineer | Baad,, Katherine Firestone; Lic. No.: C64669 | 5232 ZAKON RD TORRANCE, CA 90505 |
| Engineer | Barajas,, George Luis; Lic. No.: L8399 | 3635 SHADOW GROVE RD PASADENA, CA 91107 |
| Engineer | Howe,, Carl William; Lic. No.: C44773 | 4358 SEPULVEDA BLVD CULVER CITY, CA 90230 |
| Engineer | Tsai,, Steve Shi-Shen; Lic. No.: GE2268 | 1545 VICTORY BLVD GLENDALE, CA 91201 |
| Geologist | Carnegie,, Vincent John; Lic. No.: EG1608 | P.O. BOX 5444 GLENDALE, CA 912012036 |
Inspector Information
| KEVIN SARGSYAN, (310) 914-3889 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 6/8/2021 | Conditional Approval | ROBERT SHELLY |
| Footing/Foundation/Slab | 6/24/2021 | Partial Approval | JUAN VALENZUELA |
| Footing/Foundation/Slab | 7/6/2021 | Partial Approval | JUAN VALENZUELA |
| Footing/Foundation/Slab | 7/13/2021 | Partial Approval | JUAN VALENZUELA |
| Footing/Foundation/Slab | 7/26/2021 | Not Ready for Inspection | JUAN VALENZUELA |
| Footing/Foundation/Slab | 7/29/2021 | Partial Approval | JUAN VALENZUELA |
| Floor/Roof Diaphrgm/Shear Wall | 8/2/2021 | Partial Approval | JUAN VALENZUELA |
| Green Building Rough | 8/2/2021 | Not Ready for Inspection | JUAN VALENZUELA |
| Verify Sprinkler Sign Off | 8/2/2021 | Not Ready for Inspection | JUAN VALENZUELA |
| Deputy Wood Construction | 8/16/2021 | Conditional Approval | JUAN VALENZUELA |
| Floor/Roof Diaphrgm/Shear Wall | 8/17/2021 | Partial Approval | JUAN VALENZUELA |
| Green Building Rough | 8/17/2021 | Not Ready for Inspection | JUAN VALENZUELA |
| Verify Sprinkler Sign Off | 8/17/2021 | Not Ready for Inspection | JUAN VALENZUELA |
| Special/Order Compliance | 8/27/2021 | Partial Approval | JESUS RODRIGUEZ |
| Underground Mechanical | 8/27/2021 | Partial Approval | JUAN VALENZUELA |
| Footing/Foundation/Slab | 9/3/2021 | Partial Approval | BRENDAN LOONEY |
| ELECTRICAL-Rough | 10/13/2021 | Approved | JUAN VALENZUELA |
| HVAC-Rough | 10/13/2021 | Partial Approval | JUAN VALENZUELA |
| PLUMBING-Rough | 10/19/2021 | Approved | JUAN VALENZUELA |
| Deputy Wood Construction | 10/22/2021 | Conditional Approval | JUAN VALENZUELA |
| BUILDING-Rough-Frame | 10/26/2021 | Partial Approval | JUAN VALENZUELA |
| Green Building Rough | 10/26/2021 | Not Ready for Inspection | JUAN VALENZUELA |
| Verify Sprinkler Sign Off | 10/26/2021 | Approved | JUAN VALENZUELA |
| BUILDING-Rough-Frame | 11/12/2021 | Approved | ANDREW NAVE |
| Green Building Rough | 11/12/2021 | Approved | ANDREW NAVE |
| Insulation | 11/19/2021 | Approved | STEPHANIE SWANSON |
| Interior/Exterior Lathing | 11/19/2021 | Partial Approval | STEPHANIE SWANSON |
| PLUMBING-Rough | 11/19/2021 | Approved | STEPHANIE SWANSON |
| Shower Pan | 11/24/2021 | Approved | DEANDRE HOFFMAN |
| Drywall Nailing | 12/2/2021 | Approved | JUAN VALENZUELA |
| Interior/Exterior Lathing | 12/7/2021 | Approved | JUAN VALENZUELA |
| Underground Mechanical | 1/31/2022 | Partial Approval | JUAN VALENZUELA |
| Underground Mechanical | 2/14/2022 | Partial Approval | JUAN VALENZUELA |
| Gas Test | 4/6/2022 | Approved | JUAN VALENZUELA |
| Service/Power Release | 4/7/2022 | Not Ready for Inspection | JUAN VALENZUELA |
| ELECTRICAL-Final | 5/9/2022 | Approved | JUAN VALENZUELA |
| Service/Power Release | 5/9/2022 | Approved | JUAN VALENZUELA |
| HVAC-Final | 6/1/2022 | Corrections Issued | JUAN VALENZUELA |
| HVAC-Final | 7/19/2022 | Not Ready for Inspection | KEVIN SARGSYAN |
| PLUMBING-Final | 7/19/2022 | Corrections Issued | KEVIN SARGSYAN |
| HVAC-Final | 8/10/2022 | Approved | JUAN VALENZUELA |
| PLUMBING-Final | 8/10/2022 | Approved | JUAN VALENZUELA |
| Final | 8/24/2022 | Conditional Approval | JUAN VALENZUELA |
| Footing/Foundation/Slab | 8/24/2022 | Approved | JUAN VALENZUELA |
| Green Building Final | 8/24/2022 | Approved | JUAN VALENZUELA |
| SGSOV-Seismic Gas S/O Valve | 8/24/2022 | SGSOV Approved | JUAN VALENZUELA |
| Smoke Detectors | 8/24/2022 | Approved | JUAN VALENZUELA |