3566 S TILDEN AVE 90034

Certificate Information: 3566 S TILDEN AVE 90034

Application / Permit
20014-10000-03686
Plan Check / Job No.
B20LA15567
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
REMODEL OF EXISTING ONE-STORY SINGLE FAMILY RESIDENCE WITH ATTACHED GARAGE AND ADDITION OF SECOND STORY. 1 OF 2
Permit Issued
Issued on 8/13/2021
Issuing Office
Current Status
CofO Issued on 8/10/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 9/9/2020 APPLICANT
Assigned to Plan Check Engineer 10/1/2020 CRYSTEL MAALOUF
Corrections Issued 10/14/2020 CRYSTEL MAALOUF
Quality Review Completed 11/9/2020 WING SUEN
Building Plans Picked Up 11/16/2020 APPLICANT
Applicant returned to address corrections 4/6/2021 CRYSTEL MAALOUF
Plan Check Approved 8/5/2021 CRYSTEL MAALOUF
Issued 8/13/2021 APPLICANT
CofO in Progress 8/3/2023 JESUS PINEDA
Permit Finaled 8/10/2023 DANIEL ORRANTE
CofO Issued 8/10/2023 DANIEL ORRANTE
Permit Finaled 8/10/2023 DANIEL ORRANTE

Permit Application Clearance Information

Construction within easement Cleared 3/5/2021 WALTER RAMIREZ
Eng Process Fee Ord 176,300 Cleared 3/17/2021 ANTHONY MAINEZ
Sewer availability Cleared 3/17/2021 ANTHONY MAINEZ
Specific Plan Cleared 3/25/2021 PEDRO AYALA
Low Impact Development Cleared 7/2/2021 TA ANH
Roof/Waste drainage to street Cleared 7/13/2021 DINAH GARIN
Work Adjacent to Public Way Cleared 7/14/2021 SAUL GARCIA
Miscellaneous Cleared 7/20/2021 RAYMOND MUGAMBWA
Miscellaneous Cleared 7/26/2021 JENSON LEE
GPI Written Notices Cleared 8/5/2021 CRYSTEL MAALOUF
Grading Pre-Inspection Cleared 8/5/2021 CRYSTEL MAALOUF

Contact Information

Contractor Roth Development Group Inc; Lic. No.: 1006385-B 602 ROSARIO DR      THOUSAND OAKS, CA 91362
Engineer Toedter,, Randy W; Lic. No.: S2991 7474 EISENHOWER ST      VENTURA, CA 93003

Inspector Information

KIRK SANDERS, (310) 914-3896 Office Hours: 7:00-8:00 AM MON-FRI
ARAM AVEDISIAN, (310) 914-3896 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 10/22/2021 Approved JOHNNY MIRANDA
Underground Mechanical 11/1/2021 Corrections Issued JOHNNY MIRANDA
Underground Mechanical 11/3/2021 Partial Approval JOHNNY MIRANDA
Footing/Foundation/Slab 12/3/2021 Partial Approval OGANES TARAKHCHYAN
Floor/Roof Diaphrgm/Shear Wall 2/15/2022 Partial Approval JOHNNY MIRANDA
Floor/Roof Diaphrgm/Shear Wall 3/14/2022 Conditional Approval JOHNNY MIRANDA
Deputy Wood Construction 3/16/2022 Conditional Approval JOHNNY MIRANDA
Floor/Roof Diaphrgm/Shear Wall 3/17/2022 Partial Approval OGANES TARAKHCHYAN
ELECTRICAL-Rough 5/18/2022 Approved JOHNNY MIRANDA
PLUMBING-Rough 5/18/2022 Not Ready for Inspection JOHNNY MIRANDA
HVAC-Rough 6/13/2022 Corrections Issued JOHNNY MIRANDA
PLUMBING-Rough 6/13/2022 Not Ready for Inspection JOHNNY MIRANDA
Shower Pan 6/13/2022 Not Ready for Inspection JOHNNY MIRANDA
HVAC-Rough 6/30/2022 Approved JOHNNY MIRANDA
Insulation 6/30/2022 Not Ready for Inspection JOHNNY MIRANDA
PLUMBING-Rough 6/30/2022 Approved JOHNNY MIRANDA
Shower Pan 6/30/2022 Approved JOHNNY MIRANDA
Deputy Wood Construction 7/6/2022 Conditional Approval MICHAEL PELHAM
BUILDING-Rough-Frame 7/11/2022 Corrections Issued STEPHANIE SWANSON
Green Building Rough 7/11/2022 Not Ready for Inspection STEPHANIE SWANSON
Interior/Exterior Lathing 7/11/2022 Partial Approval STEPHANIE SWANSON
BUILDING-Rough-Frame 7/14/2022 Approved JOHNNY MIRANDA
Green Building Rough 7/14/2022 Approved JOHNNY MIRANDA
Interior/Exterior Lathing 7/14/2022 Approved JOHNNY MIRANDA
Insulation 7/21/2022 Approved JOHNNY MIRANDA
Drywall Nailing 8/5/2022 Approved JOHNNY MIRANDA
Underground Mechanical 8/26/2022 Partial Approval JOHNNY MIRANDA
Gas Test 3/10/2023 Corrections Issued JESUS PINEDA
Gas Test 4/14/2023 Approved JOHNNY MIRANDA
Service/Power Release 4/14/2023 Not Ready for Inspection JOHNNY MIRANDA
PLUMBING-Final 6/7/2023 Corrections Issued HERBERT GIRON
ELECTRICAL-Final 6/8/2023 Corrections Issued HERBERT GIRON
HVAC-Final 6/8/2023 Corrections Issued HERBERT GIRON
HVAC-Final 6/14/2023 Corrections Issued JOHNNY MIRANDA
PLUMBING-Final 6/14/2023 Approved JOHNNY MIRANDA
ELECTRICAL-Final 6/16/2023 Approved JOHNNY MIRANDA
Service/Power Release 6/16/2023 Not Ready for Inspection JOHNNY MIRANDA
HVAC-Final 6/28/2023 No Access for Inspection DAVID FEILER
Final 7/24/2023 Corrections Issued JESUS PINEDA
Footing/Foundation/Slab 7/24/2023 Approved JESUS PINEDA
Green Building Final 7/24/2023 Approved JESUS PINEDA
HVAC-Final 7/24/2023 Approved JESUS PINEDA
SGSOV-Seismic Gas S/O Valve 7/24/2023 SGSOV Approved JESUS PINEDA
Service/Power Release 7/24/2023 Not Ready for Inspection JESUS PINEDA
Smoke Detectors 7/24/2023 Approved JESUS PINEDA
Final 8/2/2023 OK to Issue CofO JESUS PINEDA
Service/Power Release 8/2/2023 Approved JESUS PINEDA