3131 N DORCHESTER AVE 90032

Certificate Information: 3131 N DORCHESTER AVE 90032

Application / Permit
20014-10000-03679
Plan Check / Job No.
B20LA15550
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
NEW 1-STORY BATHROOM ADDITION TO REAR OF EXISTING SFD
Permit Issued
Issued on 2/5/2021
Issuing Office
Current Status
CofO Issued on 3/21/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 8/28/2020 APPLICANT
Assigned to Plan Check Engineer 9/1/2020 JESSE JIMENEZ
Corrections Issued 9/1/2020 JESSE JIMENEZ
Building Plans Picked Up 9/10/2020 APPLICANT
Applicant returned to address corrections 1/6/2021 ADAM HEGAZI
Plan Check Approved 1/26/2021 ADAM HEGAZI
Issued 2/5/2021 APPLICANT
CofO in Progress 3/14/2024 LILIANA PORTILLO
Permit Finaled 3/21/2024 DEROLD HAUFF
CofO Issued 3/21/2024 DEROLD HAUFF
Permit Finaled 3/21/2024 DEROLD HAUFF

Permit Application Clearance Information

Grading Pre-Inspection Cleared 11/17/2020 BARTON HOLMES
Eng Process Fee Ord 176,300 Cleared 11/20/2020 JUAN ASHTON
Roof/Waste drainage to street Cleared 11/20/2020 JUAN ASHTON
Watercourse Cleared 1/26/2021 SAM NAVID

Contact Information

Contractor Viera Design & Construction; Lic. No.: 972064-B 17646 E BENBOW ST      COVINA, CA 91722
Engineer Alson,, Ken; Lic. No.: C41697 9744 MAPLE ST 201      BELLFLOWER, CA 90706

Inspector Information

No Data Available.

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 3/18/2021 OK to Expire Permit COREY HUPP
PLUMBING-Rough 4/15/2021 Partial Approval CRAIG VAUGHAN
Wood Frame 4/15/2021 Partial Approval CRAIG VAUGHAN
BUILDING-Rough-Frame 5/7/2021 Approved OSVALDO PARAMO
ELECTRICAL-Rough 5/7/2021 Approved OSVALDO PARAMO
Green Building Rough 5/7/2021 Approved OSVALDO PARAMO
PLUMBING-Rough 5/7/2021 Approved OSVALDO PARAMO
Interior/Exterior Lathing 5/17/2021 Partial Approval COREY HUPP
Insulation 5/24/2021 Approved COREY HUPP
Shower Pan 5/24/2021 Approved COREY HUPP
Drywall Nailing 6/1/2021 Approved COREY HUPP
Interior/Exterior Lathing 6/1/2021 Approved COREY HUPP
Final 7/1/2021 Corrections Issued COREY HUPP
Footing/Foundation/Slab 7/1/2021 Approved COREY HUPP
Green Building Final 7/1/2021 Approved COREY HUPP
SGSOV-Seismic Gas S/O Valve 7/1/2021 SGSOV Not Ready COREY HUPP
Smoke Detectors 7/1/2021 Approved COREY HUPP
Final 7/9/2021 Conditional Approval COREY HUPP
SGSOV-Seismic Gas S/O Valve 7/9/2021 SGSOV Approved COREY HUPP
ELECTRICAL-Final 3/13/2024 Approved LILIANA PORTILLO
Final 3/13/2024 OK to Issue CofO LILIANA PORTILLO
HVAC-Final 3/13/2024 Approved LILIANA PORTILLO
PLUMBING-Final 3/13/2024 Approved LILIANA PORTILLO