9208-9210 N GOTHIC AVE 91343

Certificate Information: 9208-9210 N GOTHIC AVE 91343

Application / Permit
20014-10000-03665
Plan Check / Job No.
B20LA15490
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT PORTION OF SFD(193SF) AND EXPAND(59SF) (E) GARAGE(494SF) ATTACHED TO (E) SFD INTO A.D.U. PER LAMC 12.22 A.33(c)-(d).
Permit Issued
Issued on 5/24/2024
Issuing Office
Metro
Current Status
CofO Issued on 8/14/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 8/27/2020 APPLICANT
Assigned to Plan Check Engineer 8/29/2020 LAWRENCE QUIRANTE
Corrections Issued 8/29/2020 LAWRENCE QUIRANTE
Building Plans Picked Up 9/2/2020 APPLICANT
Plan Check Approved 4/12/2024 SAMUEL GONZALEZ
Issued 5/24/2024 APPLICANT
CofO in Progress 8/4/2025 JENNIFER RABUCHIN
Permit Finaled 8/14/2025 RUBEN SALAS
CofO Issued 8/14/2025 RUBEN SALAS
Permit Finaled 8/14/2025 RUBEN SALAS

Permit Application Clearance Information

Roof/Waste drainage to street Cleared 9/9/2020 JOHN TRIANTAFYLLOS
Address approval Cleared 9/10/2020 JOHN TRIANTAFYLLOS
Eng Process Fee Ord 176,300 Cleared 9/10/2020 JOHN TRIANTAFYLLOS
Sewer availability Cleared 9/14/2020 JOHN TRIANTAFYLLOS
Grading Pre-Inspection Cleared 10/15/2020 PATRICK MISCHLICH

Contact Information

Contractor Affordable Building Solutions Inc; Lic. No.: 1068574-B 8885 SANDALWOOD CT      RANCHO CUCAMONGA, CA 91730
Engineer Castillo,, Margarito; Lic. No.: S4808 1205 PINE AVENUE      LONG BEACH, CA 90813

Inspector Information

MICHAEL CORTEZ, (818) 374-1176 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 5/30/2024 Approved RAUL OLAGI
Deputy Drilled-In Anchors 5/31/2024 Conditional Approval JUAN VALENZUELA
BUILDING-Rough-Frame 6/11/2024 Corrections Issued RAUL OLAGI
ELECTRICAL-Rough 6/11/2024 Approved RAUL OLAGI
HVAC-Rough 6/11/2024 Corrections Issued RAUL OLAGI
PLUMBING-Rough 6/11/2024 Corrections Issued RAUL OLAGI
BUILDING-Rough-Frame 6/28/2024 Approved RAUL OLAGI
Green Building Rough 6/28/2024 Not Ready for Inspection RAUL OLAGI
HVAC-Rough 6/28/2024 Approved RAUL OLAGI
Interior/Exterior Lathing 6/28/2024 Partial Approval RAUL OLAGI
PLUMBING-Rough 6/28/2024 Approved RAUL OLAGI
Insulation 7/5/2024 Approved RAUL OLAGI
Interior/Exterior Lathing 7/5/2024 Partial Approval RAUL OLAGI
Drywall Nailing 7/10/2024 Corrections Issued RAUL OLAGI
Drywall Nailing 7/12/2024 Approved RUBEN SALAS
Interior/Exterior Lathing 8/26/2024 Partial Approval STUART CHAPMAN
ELECTRICAL-Final 2/4/2025 Approved GAREN HAYRAPETYAN
PLUMBING-Final 2/4/2025 Corrections Issued GAREN HAYRAPETYAN
SGSOV-Seismic Gas S/O Valve 3/4/2025 SGSOV Not Ready ROBERTO PALACIOS-LOPEZ
BUILDING-Rough-Frame 3/24/2025 Approved SALVADOR MARTINEZ
Final 3/24/2025 Corrections Issued SALVADOR MARTINEZ
Green Building Final 3/24/2025 Not Ready for Inspection SALVADOR MARTINEZ
Green Building Rough 3/24/2025 Approved SALVADOR MARTINEZ
HVAC-Final 3/24/2025 Corrections Issued SALVADOR MARTINEZ
PLUMBING-Final 3/24/2025 Corrections Issued SALVADOR MARTINEZ
SGSOV-Seismic Gas S/O Valve 3/24/2025 SGSOV Not Ready SALVADOR MARTINEZ
Smoke Detectors 3/24/2025 Corrections Issued SALVADOR MARTINEZ
Final 4/9/2025 Corrections Issued SALVADOR MARTINEZ
Green Building Final 4/9/2025 Approved SALVADOR MARTINEZ
HVAC-Final 4/9/2025 Corrections Issued SALVADOR MARTINEZ
PLUMBING-Final 4/9/2025 Corrections Issued SALVADOR MARTINEZ
SGSOV-Seismic Gas S/O Valve 4/9/2025 SGSOV Not Ready SALVADOR MARTINEZ
Smoke Detectors 4/9/2025 Approved SALVADOR MARTINEZ
SGSOV-Seismic Gas S/O Valve 7/9/2025 SGSOV Not Ready SALVADOR MARTINEZ
Final 7/28/2025 Corrections Issued SALVADOR MARTINEZ
SGSOV-Seismic Gas S/O Valve 7/28/2025 SGSOV Not Ready SALVADOR MARTINEZ
SGSOV-Seismic Gas S/O Valve 7/30/2025 SGSOV Not Ready JENNIFER RABUCHIN
ELECTRICAL-Final 8/1/2025 Approved JENNIFER RABUCHIN
Final 8/1/2025 OK to Issue CofO JENNIFER RABUCHIN
Gas Test 8/1/2025 Approved JENNIFER RABUCHIN
HVAC-Final 8/1/2025 Approved JENNIFER RABUCHIN
PLUMBING-Final 8/1/2025 Approved JENNIFER RABUCHIN
SGSOV-Seismic Gas S/O Valve 8/1/2025 SGSOV Approved JENNIFER RABUCHIN