3190 W LARGA AVE 90039
Certificate Information: 3190 W LARGA AVE 90039
- Application / Permit
- 20014-10000-03663
- Plan Check / Job No.
- B20LA15450
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- PROPOSED 1ST AND 2ND STORY ADDTION TO EXISTING SINGLE FAMILY DWELLING AT REAR (NFPA 13D THRU OUT)
- Permit Issued
- Issued on 9/20/2021
- Issuing Office
- Current Status
- CofO Issued on 8/22/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 9/23/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 10/22/2020 | AUNG SOE |
| Corrections Issued | 10/27/2020 | AUNG SOE |
| Quality Review Completed | 10/29/2020 | HERNAN ARREOLA |
| Applicant returned to address corrections | 8/31/2021 | AUNG SOE |
| Plan Check Approved | 8/31/2021 | AUNG SOE |
| No Progress | 8/31/2021 | AUNG SOE |
| Plan Check Approved | 9/9/2021 | AUNG SOE |
| Issued | 9/20/2021 | APPLICANT |
| Building Plans Picked Up | 9/24/2021 | APPLICANT |
| CofO in Progress | 8/14/2023 | HAMIK HARTOUNIAN |
| CofO in Progress | 8/14/2023 | DONALD CRICHLOW |
| CofO in Progress | 8/22/2023 | HAMIK HARTOUNIAN |
| CofO Issued | 8/22/2023 | RONALD MYRICK |
| Permit Finaled | 8/22/2023 | RONALD MYRICK |
Permit Application Clearance Information
| Sewer availability | Cleared | 11/12/2020 | RENZ SORIANO |
| Eng Process Fee Ord 176,300 | Cleared | 12/3/2020 | RENZ SORIANO |
| Community Plan Implem. Overlay | Cleared | 1/19/2021 | MARITZA PRZEKOP |
| Low Impact Development | Cleared | 4/27/2021 | SUNG JOON WON |
| Roof/Waste drainage to street | Cleared | 6/9/2021 | RENZ SORIANO |
| Hydrant and Access approval | Cleared | 8/12/2021 | MATTHEW CRAIG |
Contact Information
| Contractor | Reyes Erasmo; Lic. No.: 926630-B | 6912 ALDEA AVE LAKE BALBOA, CA 91406 |
| Engineer | Chavez,, Eduardo; Lic. No.: C76372 | 437 ARCADIA WAY WALNUT, CA 91789 |
Inspector Information
| NICHOLAS LOPEZ, (213) 202-3224 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 9/29/2021 | Not Ready for Inspection | HAMIK HARTOUNIAN |
| Footing/Foundation/Slab | 10/21/2021 | Corrections Issued | HAMIK HARTOUNIAN |
| Footing/Foundation/Slab | 11/2/2021 | Conditional Approval | HAMIK HARTOUNIAN |
| PLUMBING-Rough | 11/30/2021 | Approved | HAMIK HARTOUNIAN |
| Footing/Foundation/Slab | 12/3/2021 | Approved | HAMIK HARTOUNIAN |
| Insulation | 12/3/2021 | Partial Approval | HAMIK HARTOUNIAN |
| Floor/Roof Diaphrgm/Shear Wall | 12/14/2021 | No Access for Inspection | HAMIK HARTOUNIAN |
| Floor/Roof Diaphrgm/Shear Wall | 12/17/2021 | Partial Approval | HAMIK HARTOUNIAN |
| Floor/Roof Diaphrgm/Shear Wall | 1/26/2022 | Partial Approval | HAMIK HARTOUNIAN |
| Green Building Rough | 1/26/2022 | Approved | HAMIK HARTOUNIAN |
| BUILDING-Rough-Frame | 2/8/2022 | Corrections Issued | HAMIK HARTOUNIAN |
| Floor/Roof Diaphrgm/Shear Wall | 2/10/2022 | Partial Approval | HAMIK HARTOUNIAN |
| BUILDING-Rough-Frame | 3/8/2022 | Corrections Issued | HAMIK HARTOUNIAN |
| Floor/Roof Diaphrgm/Shear Wall | 4/26/2022 | Corrections Issued | HAMIK HARTOUNIAN |
| BUILDING-Rough-Frame | 6/13/2022 | No Access for Inspection | HAMIK HARTOUNIAN |
| Shower Pan | 8/4/2022 | Conditional Approval | HAMIK HARTOUNIAN |
| ELECTRICAL-Rough | 8/17/2022 | Approved | HAMIK HARTOUNIAN |
| Interior/Exterior Lathing | 8/17/2022 | Conditional Approval | HAMIK HARTOUNIAN |
| Interior/Exterior Lathing | 10/14/2022 | Partial Approval | HAMIK HARTOUNIAN |
| HVAC-Rough | 10/21/2022 | Not Ready for Inspection | HAMIK HARTOUNIAN |
| BUILDING-Rough-Frame | 11/8/2022 | Approved | HAMIK HARTOUNIAN |
| Insulation | 11/30/2022 | Conditional Approval | CHARLES BOGHOSKHAN |
| Drywall Nailing | 12/20/2022 | Conditional Approval | HAMIK HARTOUNIAN |
| HVAC-Rough | 12/20/2022 | Conditional Approval | HAMIK HARTOUNIAN |
| Drywall Nailing | 12/27/2022 | Conditional Approval | JOSEPH MCGARRY |
| HVAC-Rough | 12/27/2022 | Approved | JOSEPH MCGARRY |
| Final | 6/23/2023 | Corrections Issued | HAMIK HARTOUNIAN |
| Green Building Final | 6/23/2023 | Corrections Issued | HAMIK HARTOUNIAN |
| SGSOV-Seismic Gas S/O Valve | 6/23/2023 | SGSOV Not Ready | HAMIK HARTOUNIAN |
| Smoke Detectors | 6/23/2023 | Approved | HAMIK HARTOUNIAN |
| Final | 7/26/2023 | Corrections Issued | HAMIK HARTOUNIAN |
| Green Building Final | 7/26/2023 | Corrections Issued | HAMIK HARTOUNIAN |
| SGSOV-Seismic Gas S/O Valve | 7/26/2023 | SGSOV Approved | HAMIK HARTOUNIAN |
| Final | 8/11/2023 | No Access for Inspection | HAMIK HARTOUNIAN |
| Green Building Final | 8/11/2023 | Approved | HAMIK HARTOUNIAN |
| Final | 8/22/2023 | OK to Issue CofO | HAMIK HARTOUNIAN |