3190 W LARGA AVE 90039

Certificate Information: 3190 W LARGA AVE 90039

Application / Permit
20014-10000-03663
Plan Check / Job No.
B20LA15450
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
PROPOSED 1ST AND 2ND STORY ADDTION TO EXISTING SINGLE FAMILY DWELLING AT REAR (NFPA 13D THRU OUT)
Permit Issued
Issued on 9/20/2021
Issuing Office
Current Status
CofO Issued on 8/22/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 9/23/2020 APPLICANT
Assigned to Plan Check Engineer 10/22/2020 AUNG SOE
Corrections Issued 10/27/2020 AUNG SOE
Quality Review Completed 10/29/2020 HERNAN ARREOLA
Applicant returned to address corrections 8/31/2021 AUNG SOE
Plan Check Approved 8/31/2021 AUNG SOE
No Progress 8/31/2021 AUNG SOE
Plan Check Approved 9/9/2021 AUNG SOE
Issued 9/20/2021 APPLICANT
Building Plans Picked Up 9/24/2021 APPLICANT
CofO in Progress 8/14/2023 HAMIK HARTOUNIAN
CofO in Progress 8/14/2023 DONALD CRICHLOW
CofO in Progress 8/22/2023 HAMIK HARTOUNIAN
CofO Issued 8/22/2023 RONALD MYRICK
Permit Finaled 8/22/2023 RONALD MYRICK

Permit Application Clearance Information

Sewer availability Cleared 11/12/2020 RENZ SORIANO
Eng Process Fee Ord 176,300 Cleared 12/3/2020 RENZ SORIANO
Community Plan Implem. Overlay Cleared 1/19/2021 MARITZA PRZEKOP
Low Impact Development Cleared 4/27/2021 SUNG JOON WON
Roof/Waste drainage to street Cleared 6/9/2021 RENZ SORIANO
Hydrant and Access approval Cleared 8/12/2021 MATTHEW CRAIG

Contact Information

Contractor Reyes Erasmo; Lic. No.: 926630-B 6912 ALDEA AVE      LAKE BALBOA, CA 91406
Engineer Chavez,, Eduardo; Lic. No.: C76372 437 ARCADIA WAY      WALNUT, CA 91789

Inspector Information

NICHOLAS LOPEZ, (213) 202-3224 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 9/29/2021 Not Ready for Inspection HAMIK HARTOUNIAN
Footing/Foundation/Slab 10/21/2021 Corrections Issued HAMIK HARTOUNIAN
Footing/Foundation/Slab 11/2/2021 Conditional Approval HAMIK HARTOUNIAN
PLUMBING-Rough 11/30/2021 Approved HAMIK HARTOUNIAN
Footing/Foundation/Slab 12/3/2021 Approved HAMIK HARTOUNIAN
Insulation 12/3/2021 Partial Approval HAMIK HARTOUNIAN
Floor/Roof Diaphrgm/Shear Wall 12/14/2021 No Access for Inspection HAMIK HARTOUNIAN
Floor/Roof Diaphrgm/Shear Wall 12/17/2021 Partial Approval HAMIK HARTOUNIAN
Floor/Roof Diaphrgm/Shear Wall 1/26/2022 Partial Approval HAMIK HARTOUNIAN
Green Building Rough 1/26/2022 Approved HAMIK HARTOUNIAN
BUILDING-Rough-Frame 2/8/2022 Corrections Issued HAMIK HARTOUNIAN
Floor/Roof Diaphrgm/Shear Wall 2/10/2022 Partial Approval HAMIK HARTOUNIAN
BUILDING-Rough-Frame 3/8/2022 Corrections Issued HAMIK HARTOUNIAN
Floor/Roof Diaphrgm/Shear Wall 4/26/2022 Corrections Issued HAMIK HARTOUNIAN
BUILDING-Rough-Frame 6/13/2022 No Access for Inspection HAMIK HARTOUNIAN
Shower Pan 8/4/2022 Conditional Approval HAMIK HARTOUNIAN
ELECTRICAL-Rough 8/17/2022 Approved HAMIK HARTOUNIAN
Interior/Exterior Lathing 8/17/2022 Conditional Approval HAMIK HARTOUNIAN
Interior/Exterior Lathing 10/14/2022 Partial Approval HAMIK HARTOUNIAN
HVAC-Rough 10/21/2022 Not Ready for Inspection HAMIK HARTOUNIAN
BUILDING-Rough-Frame 11/8/2022 Approved HAMIK HARTOUNIAN
Insulation 11/30/2022 Conditional Approval CHARLES BOGHOSKHAN
Drywall Nailing 12/20/2022 Conditional Approval HAMIK HARTOUNIAN
HVAC-Rough 12/20/2022 Conditional Approval HAMIK HARTOUNIAN
Drywall Nailing 12/27/2022 Conditional Approval JOSEPH MCGARRY
HVAC-Rough 12/27/2022 Approved JOSEPH MCGARRY
Final 6/23/2023 Corrections Issued HAMIK HARTOUNIAN
Green Building Final 6/23/2023 Corrections Issued HAMIK HARTOUNIAN
SGSOV-Seismic Gas S/O Valve 6/23/2023 SGSOV Not Ready HAMIK HARTOUNIAN
Smoke Detectors 6/23/2023 Approved HAMIK HARTOUNIAN
Final 7/26/2023 Corrections Issued HAMIK HARTOUNIAN
Green Building Final 7/26/2023 Corrections Issued HAMIK HARTOUNIAN
SGSOV-Seismic Gas S/O Valve 7/26/2023 SGSOV Approved HAMIK HARTOUNIAN
Final 8/11/2023 No Access for Inspection HAMIK HARTOUNIAN
Green Building Final 8/11/2023 Approved HAMIK HARTOUNIAN
Final 8/22/2023 OK to Issue CofO HAMIK HARTOUNIAN