1864 W JEFFERSON BLVD 90018
Certificate Information: 1864 W JEFFERSON BLVD 90018
- Application / Permit
- 20014-10000-03645
- Plan Check / Job No.
- B20LA15391
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- Commercial
- Primary Use
- (13) Veterinary Clinic
- Work Description
- ADDITION TO (E) COMMERICAL BLDG & CHANGE OF USE TO VET CLINIC WITH NEW ON SITE PARKING (NO OVERNIGHT STAY OF ANIMALS).
- Permit Issued
- Issued on 9/6/2022
- Issuing Office
- Metro
- Current Status
- Issued on 9/6/2022
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 8/28/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 9/25/2020 | ARMEN JIVALAGIAN |
| Corrections Issued | 9/29/2020 | ARMEN JIVALAGIAN |
| Quality Review Completed | 10/1/2020 | CHAD DOI |
| Building Plans Picked Up | 10/5/2020 | APPLICANT |
| Disabled Access Plans Picked Up | 10/19/2020 | APPLICANT |
| Green Plans Picked Up | 5/18/2021 | APPLICANT |
| Applicant returned to address corrections | 8/25/2021 | ARMEN JIVALAGIAN |
| Applicant returned to address corrections | 1/11/2022 | ARMEN JIVALAGIAN |
| Applicant returned to address corrections | 1/19/2022 | ARMEN JIVALAGIAN |
| Applicant returned to address corrections | 1/21/2022 | ARMEN JIVALAGIAN |
| Applicant returned to address corrections | 2/18/2022 | ARMEN JIVALAGIAN |
| Applicant returned to address corrections | 5/19/2022 | ARMEN JIVALAGIAN |
| Applicant returned to address corrections | 6/22/2022 | ARMEN JIVALAGIAN |
| Plan Check Approved | 9/2/2022 | QUAN NGHIEM |
| Issued | 9/6/2022 | APPLICANT |
Permit Application Clearance Information
| Low Impact Development | Cleared | 2/11/2021 | SARAH YOUSSEF |
| Green Code | Cleared | 5/17/2021 | AARON COSTA |
| Eng Process Fee Ord 176,300 | Cleared | 6/7/2021 | RENZ SORIANO |
| DAS Clearance | Cleared | 6/29/2021 | ARMEN JIVALAGIAN |
| Sewer availability | Cleared | 7/27/2021 | RENZ SORIANO |
| Highway dedication | Cleared | 8/2/2021 | RENZ SORIANO |
| City Hist. Cultural Monument | Cleared | 8/3/2021 | MAX LODER |
| HPOZ | Cleared | 8/3/2021 | MAX LODER |
| Historic monument | Cleared | 8/3/2021 | MAX LODER |
| Miscellaneous | Cleared | 8/3/2021 | MAX LODER |
| Miscellaneous | Cleared | 8/3/2021 | MAX LODER |
| Roof/Waste drainage to street | Cleared | 8/11/2021 | RENZ SORIANO |
| "D" conditions | Cleared | 8/16/2021 | RAFAEL FONTES |
| Community Plan Implem. Overlay | Cleared | 8/16/2021 | RAFAEL FONTES |
| Trees in Parkway | Cleared | 8/19/2021 | JOHN KIM |
| Miscellaneous | Cleared | 8/31/2021 | RICHARD REASER |
| Miscellaneous | Cleared | 9/1/2021 | MAX LODER |
| Prkng lot landscape/Water mgmt | Cleared | 9/1/2021 | RICHARD REASER |
| Permit | Cleared | 9/17/2021 | CECILIO NAVARRO |
| Driveway location | Cleared | 12/21/2021 | PETE EYRE |
Contact Information
| Contractor | Y V General Construction Company Inc; Lic. No.: 1013222-B | 1522 S ANDREWS PL APT #102 LOS ANGELES, CA 90019 |
| Engineer | Chakar,, Jean-Pierre M; Lic. No.: S6213 | 2011 OCEAN PARK BLVD APT B SANTA MONICA, CA 90405 |
Inspector Information
| PAUL BAZERKANIAN, (213) 482-0353 | Office Hours: 7:00-8:00 AM MON-FRI |
| LUIS CCAMACHO, (213) 482-0353 | Office Hours: 7:00-8:00 AM MON-FRI |
| ALAN MORELOS, (213) 482-0353 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 11/2/2022 | Partial Approval | RUSSELL BONVOULOIR |
| METHANE-Barrier | 11/2/2022 | Partial Inspection | RUSSELL BONVOULOIR |
| METHANE-Subgrade | 11/2/2022 | Partial Inspection | RUSSELL BONVOULOIR |
| Footing/Foundation/Slab | 11/30/2022 | Partial Approval | RUSSELL BONVOULOIR |
| METHANE-Barrier | 11/30/2022 | Partial Inspection | RUSSELL BONVOULOIR |
| METHANE-Subgrade | 11/30/2022 | Partial Inspection | RUSSELL BONVOULOIR |
| Special/Order Compliance | 1/10/2023 | Partial Inspection | GREGORY POMISH |
| Pre-Inspection | 1/11/2023 | Approved | ALAN MORELOS |
| Special/Order Compliance | 1/11/2023 | Corrections Issued | GREGORY POMISH |
| Deputy Methane Barrier | 2/8/2023 | Conditional Approval | MICHAEL ROSENBERG |
| Footing/Foundation/Slab | 2/13/2023 | Partial Approval | GREGORY POMISH |
| METHANE-Barrier | 2/13/2023 | Approved | GREGORY POMISH |
| METHANE-Subgrade | 2/13/2023 | Approved | GREGORY POMISH |
| Floor/Roof Diaphrgm/Shear Wall | 6/12/2023 | Partial Approval | MARTIN TAVITIAN |
| Green Building Rough | 6/12/2023 | Not Ready for Inspection | MARTIN TAVITIAN |
| Light Gage Steel Frame | 6/12/2023 | Partial Approval | MARTIN TAVITIAN |
| METHANE-Rough | 6/12/2023 | Partial Approval | MARTIN TAVITIAN |
| Wood Frame | 6/12/2023 | Partial Approval | MARTIN TAVITIAN |
| Interior/Exterior Lathing | 7/11/2023 | Approved | MARTIN TAVITIAN |
| Special/Order Compliance | 7/11/2023 | No Access for Inspection | TED RIES |
| Insulation | 8/18/2023 | Approved | JULIAN CAPUCETTI |
| Drywall Nailing | 8/29/2023 | Partial Approval | MARTIN TAVITIAN |
| T-Bar Ceiling | 8/29/2023 | Partial Approval | MARTIN TAVITIAN |
| Grading Pre-Inspection | 2/6/2024 | Not Ready for Inspection | MARTIN TAVITIAN |
| Grading Pre-Inspection | 1/21/2025 | Not Ready for Inspection | ALFREDO LOPEZ |