10600-10602 N SABLE AVE 91040

Certificate Information: 10600-10602 N SABLE AVE 91040

Application / Permit
20014-10000-03627
Plan Check / Job No.
B20LA15323
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
CONVERT EX. GARAGE TO ADU AND ADDING ADDITIONAL SQ FT AT 2ND FLOOR PER LAMC 12.22A.33(c)(e)
Permit Issued
Issued on 7/29/2021
Issuing Office
Current Status
CofO Issued on 3/3/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 9/16/2020 APPLICANT
Assigned to Plan Check Engineer 10/8/2020 ZAW HAN
Corrections Issued 10/13/2020 ZAW HAN
Quality Review Completed 10/15/2020 TU HUA
Applicant returned to address corrections 4/12/2021 ZAW HAN
Plan Check Approved 4/13/2021 ZAW HAN
Building Plans Picked Up 4/15/2021 APPLICANT
Plan Check Approved 7/28/2021 JEFFREY TANGONAN
Issued 7/29/2021 APPLICANT
CofO in Progress 5/25/2022 MATTHEW NELSON
Permit Finaled 3/3/2023 MICHAEL SMITH
CofO Issued 3/3/2023 MICHAEL SMITH
Permit Finaled 3/3/2023 MICHAEL SMITH

Permit Application Clearance Information

Miscellaneous Cleared 11/12/2020 MAXFIELD VERMY
Specific Plan Cleared 11/12/2020 MAXFIELD VERMY
Address approval Cleared 12/22/2020 JOHN TRIANTAFYLLOS
Eng Process Fee Ord 176,300 Cleared 2/4/2021 JOHN TRIANTAFYLLOS
Sewer availability Cleared 2/4/2021 JOHN TRIANTAFYLLOS
Grading Pre-Inspection Cleared 2/12/2021 KIRK LINKLATER
Low Impact Development Cleared 3/4/2021 MITESH PATEL
Roof/Waste drainage to street Cleared 3/22/2021 ADRIAN CASTRO
GPI Written Notices Cleared 4/12/2021 KIRK LINKLATER

Contact Information

Contractor Owner-Builder       ,
Engineer Kim,, Hong Kook; Lic. No.: C64529 3600 WILSHIRE BLVD STE 1903      LOS ANGELES, CA 90010

Inspector Information

NICHOLAS TROWBRIDGE, (818) 374-1174 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 9/29/2021 Partial Approval WILLIAM KUEHN
Footing/Foundation/Slab 10/13/2021 Approved MATTHEW NELSON
Deputy Reinf. Concrete 10/15/2021 Partial Approval MATTHEW NELSON
Floor/Roof Diaphrgm/Shear Wall 11/4/2021 Partial Approval MATTHEW NELSON
Floor/Roof Diaphrgm/Shear Wall 11/24/2021 Approved MATTHEW NELSON
ELECTRICAL-Rough 12/13/2021 Corrections Issued MATTHEW NELSON
HVAC-Rough 12/13/2021 Approved MATTHEW NELSON
PLUMBING-Rough 12/13/2021 Approved MATTHEW NELSON
Sewer 12/13/2021 Not Ready for Inspection MATTHEW NELSON
Deputy Wood Construction 12/15/2021 Partial Approval MATTHEW NELSON
BUILDING-Rough-Frame 12/17/2021 Approved MATTHEW NELSON
ELECTRICAL-Rough 12/17/2021 Approved MATTHEW NELSON
Insulation 12/29/2021 Approved MATTHEW NELSON
Interior/Exterior Lathing 12/29/2021 Approved MATTHEW NELSON
Shower Pan 12/29/2021 Approved MATTHEW NELSON
Drywall Nailing 1/5/2022 Approved MATTHEW NELSON
Interior/Exterior Lathing 1/5/2022 Approved MATTHEW NELSON
Final 5/11/2022 Corrections Issued MATTHEW NELSON
SGSOV-Seismic Gas S/O Valve 5/11/2022 SGSOV Approved MATTHEW NELSON
Smoke Detectors 5/11/2022 Approved MATTHEW NELSON
ELECTRICAL-Final 5/25/2022 Approved MATTHEW NELSON
Final 5/25/2022 OK to Issue CofO MATTHEW NELSON
HVAC-Final 5/25/2022 Approved MATTHEW NELSON