3729 S BUCKINGHAM ROAD 90016
Certificate Information: 3729 S BUCKINGHAM ROAD 90016
- Application / Permit
- 20014-10000-03622
- Plan Check / Job No.
- B20LA15228
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- ONE-STORY ADDITION (14'X10'6") TO THE REAR OF THE (E) SFD
- Permit Issued
- Issued on 3/25/2021
- Issuing Office
- Current Status
- CofO Issued on 3/1/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 8/26/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 8/26/2020 | AMIR DANAI |
| Corrections Issued | 8/27/2020 | AMIR DANAI |
| Applicant returned to address corrections | 9/25/2020 | AMIR DANAI |
| Applicant returned to address corrections | 12/4/2020 | LUKE GONZALES |
| Applicant returned to address corrections | 1/27/2021 | CRISTINA SALAZAR |
| Plan Check Approved | 2/25/2021 | FARSHAD ALIMOHAMADI |
| Issued | 3/25/2021 | APPLICANT |
| Building Plans Picked Up | 4/1/2021 | APPLICANT |
| CofO in Progress | 2/28/2023 | ANTHONY EGSON |
| Permit Finaled | 3/1/2023 | DEROLD HAUFF |
| CofO Issued | 3/1/2023 | DEROLD HAUFF |
| Permit Finaled | 3/1/2023 | DEROLD HAUFF |
Permit Application Clearance Information
| Roof/Waste drainage to street | Cleared | 9/30/2020 | WALLIE JONG |
| Sewer availability | Cleared | 9/30/2020 | WALLIE JONG |
| Eng Process Fee Ord 176,300 | Cleared | 10/6/2020 | WALLIE JONG |
| Green Code | Cleared | 12/4/2020 | LUKE GONZALES |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| LUIS CASTRO, (213) 202-3436 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 11/10/2021 | Corrections Issued | ANTHONY EGSON |
| Pre-Inspection | 11/10/2021 | Corrections Issued | ANTHONY EGSON |
| Excavation/Setback/Form/Re-Bar | 1/13/2022 | Not Ready for Inspection | SHAVONNE ESPINOZA |
| Excavation/Setback/Form/Re-Bar | 1/18/2022 | Corrections Issued | ANTHONY EGSON |
| Excavation/Setback/Form/Re-Bar | 1/21/2022 | Approved | ANTHONY EGSON |
| Footing/Foundation/Slab | 1/24/2022 | Approved | ANTHONY EGSON |
| BUILDING-Rough-Frame | 3/24/2022 | Approved | HORACE FULTZ |
| ELECTRICAL-Rough | 3/24/2022 | Approved | HORACE FULTZ |
| Green Building Rough | 3/24/2022 | Approved | HORACE FULTZ |
| Insulation | 4/1/2022 | Approved | ANTHONY EGSON |
| Interior/Exterior Lathing | 4/1/2022 | Corrections Issued | ANTHONY EGSON |
| Interior/Exterior Lathing | 4/29/2022 | Approved | ANTHONY EGSON |
| Final | 7/28/2022 | Corrections Issued | ANTHONY EGSON |
| Green Building Final | 7/28/2022 | Corrections Issued | ANTHONY EGSON |
| SGSOV-Seismic Gas S/O Valve | 7/28/2022 | SGSOV Approved | ANTHONY EGSON |
| Smoke Detectors | 7/28/2022 | Approved | ANTHONY EGSON |
| ELECTRICAL-Final | 8/2/2022 | Corrections Issued | ANTHONY EGSON |
| HVAC-Final | 8/2/2022 | Corrections Issued | ANTHONY EGSON |
| PLUMBING-Final | 8/2/2022 | Corrections Issued | ANTHONY EGSON |
| ELECTRICAL-Final | 8/8/2022 | Approved | ANTHONY EGSON |
| Final | 8/8/2022 | Partial Approval | ANTHONY EGSON |
| Green Building Final | 8/8/2022 | Approved | ANTHONY EGSON |
| HVAC-Final | 8/8/2022 | Approved | ANTHONY EGSON |
| PLUMBING-Final | 8/8/2022 | Approved | ANTHONY EGSON |