1255 S MEADOWBROOK AVE 90019
Certificate Information: 1255 S MEADOWBROOK AVE 90019
- Application / Permit
- 20014-10000-03592
- Plan Check / Job No.
- B20LA15143
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- NEW ADDITION TO (E) SINGLE FAMILY DWELLING.
- Permit Issued
- Issued on 2/24/2021
- Issuing Office
- Current Status
- CofO Issued on 6/30/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 8/24/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 9/17/2020 | KEVIN MORALES |
| Corrections Issued | 9/29/2020 | KEVIN MORALES |
| Quality Review Completed | 9/29/2020 | EUGENE BARBEAU |
| Applicant returned to address corrections | 12/4/2020 | KEVIN MORALES |
| Plan Check Approved | 1/27/2021 | KEVIN MORALES |
| Issued | 2/24/2021 | APPLICANT |
| Building Plans Picked Up | 6/2/2021 | APPLICANT |
| CofO in Progress | 6/1/2022 | JOSE AVILA |
| Permit Finaled | 6/30/2022 | DEROLD HAUFF |
| CofO Issued | 6/30/2022 | DEROLD HAUFF |
| Permit Finaled | 6/30/2022 | DEROLD HAUFF |
Permit Application Clearance Information
| Roof/Waste drainage to street | Cleared | 12/9/2020 | CECILIO NAVARRO |
| Eng Process Fee Ord 176,300 | Cleared | 12/10/2020 | CECILIO NAVARRO |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Labib,, Youhanna T; Lic. No.: S4549 | 319 MAIN STREET EL SEGUNDO, CA 90245 |
Inspector Information
| DAVID WILLIAMS, (213) 202-3126 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 6/10/2021 | Corrections Issued | STUART CHAPMAN |
| METHANE-Barrier | 6/10/2021 | Approved | STUART CHAPMAN |
| METHANE-Subgrade | 6/10/2021 | Approved | STUART CHAPMAN |
| Footing/Foundation/Slab | 7/8/2021 | Not Ready for Inspection | STUART CHAPMAN |
| Footing/Foundation/Slab | 8/3/2021 | Approved | JOSEPH MCGARRY |
| Special/Order Compliance | 8/3/2021 | Corrections Issued | JOSEPH MCGARRY |
| Wood Frame | 9/7/2021 | Partial Approval | KATHRYN BUTTERWORTH |
| BUILDING-Rough-Frame | 9/22/2021 | Corrections Issued | SCOTT FINNILA |
| ELECTRICAL-Rough | 9/22/2021 | Corrections Issued | SCOTT FINNILA |
| HVAC-Rough | 9/22/2021 | Approved | SCOTT FINNILA |
| ELECTRICAL-Rough | 9/29/2021 | Approved | SCOTT FINNILA |
| Wood Frame | 10/6/2021 | Approved | JUSTIN HAWLEY |
| Insulation | 10/29/2021 | Approved | JOSE AVILA |
| Interior/Exterior Lathing | 10/29/2021 | Approved | JOSE AVILA |
| Interior/Exterior Lathing | 11/2/2021 | No Access for Inspection | JOSE AVILA |
| Drywall Nailing | 11/9/2021 | Approved | JOSE AVILA |
| Green Building Rough | 11/9/2021 | Approved | JOSE AVILA |
| SGSOV-Seismic Gas S/O Valve | 4/15/2022 | SGSOV Not Ready | JOSE AVILA |
| Pre-Inspection | 4/28/2022 | Approved | JOSE AVILA |
| BUILDING-Rough-Frame | 5/23/2022 | Approved | JOSE AVILA |
| Final | 5/23/2022 | OK to Issue CofO | JOSE AVILA |
| Green Building Final | 5/23/2022 | Approved | JOSE AVILA |
| METHANE-Final | 5/23/2022 | Approved | JOSE AVILA |
| METHANE-Rough | 5/23/2022 | Approved | JOSE AVILA |
| SGSOV-Seismic Gas S/O Valve | 5/23/2022 | SGSOV Approved | JOSE AVILA |
| Smoke Detectors | 5/23/2022 | Approved | JOSE AVILA |
| Service/Power Release | 6/20/2022 | Approved | JOSE AVILA |