1704 S SYCAMORE AVE 90019

Certificate Information: 1704 S SYCAMORE AVE 90019

Application / Permit
20014-10000-03590
Plan Check / Job No.
B20LA15127
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
ADDITION TO(E) GARAGE AND CONVERSION TO ADU PER ENGINEER CALCULATION Code 65852.2(e)(1)(A).
Permit Issued
Issued on 9/20/2022
Issuing Office
Valley
Current Status
CofO Issued on 7/9/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 9/2/2020 APPLICANT
Assigned to Plan Check Engineer 9/4/2020 RAHEL BEYENE
Corrections Issued 9/9/2020 RAHEL BEYENE
Applicant returned to address corrections 3/3/2021 ADAM HEGAZI
Applicant returned to address corrections 1/11/2022 TSE MING HUANG
Building Plans Picked Up 2/2/2022 APPLICANT
Plan Check Approved 5/27/2022 RAHEL BEYENE
Issued 9/20/2022 APPLICANT
CofO in Progress 6/3/2024 STUART CHAPMAN
CofO Issued 7/9/2024 DEROLD HAUFF
Permit Finaled 7/9/2024 DEROLD HAUFF

Permit Application Clearance Information

Construction near power lines Cleared 2/8/2021 WALTER RAMIREZ
Address approval Cleared 2/16/2021 WALLIE JONG
Roof/Waste drainage to street Cleared 2/16/2021 WALLIE JONG
Eng Process Fee Ord 176,300 Cleared 2/18/2021 WALLIE JONG
Sewer availability Cleared 2/18/2021 WALLIE JONG
Flood clearance Cleared 5/17/2022 BRYAN GATHUKA

Contact Information

Engineer Zhuang,, Wenbin; Lic. No.: S5236 205 S CHAPEL AVE #D-1      ALHAMBRA, CA 91801

Inspector Information

DAVID WILLIAMS, (213) 202-3126 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 12/30/2022 Corrections Issued JOSE AVILA
Pre-Inspection 2/15/2023 Corrections Issued JOSE AVILA
Pre-Inspection 9/6/2023 Partial Inspection JOSE AVILA
Excavation/Setback/Form/Re-Bar 11/13/2023 Corrections Issued JOSE AVILA
Excavation/Setback/Form/Re-Bar 11/17/2023 Conditional Approval SCOTT FINNILA
BUILDING-Rough-Frame 12/1/2023 Not Ready for Inspection JOSE AVILA
Floor/Roof Diaphrgm/Shear Wall 12/1/2023 Corrections Issued JOSE AVILA
BUILDING-Rough-Frame 12/13/2023 Not Ready for Inspection RONNIE MINDANAO
FLOOD-Proofing Certificate 12/13/2023 Not Ready for Inspection RONNIE MINDANAO
Floor/Roof Diaphrgm/Shear Wall 12/13/2023 Corrections Issued RONNIE MINDANAO
Underground Mechanical 12/21/2023 Not Ready for Inspection ALIZAH MAYAGOITIA
Wood Frame 12/21/2023 Not Ready for Inspection ALIZAH MAYAGOITIA
ELECTRICAL-Rough 12/27/2023 Approved SCOTT FINNILA
HVAC-Rough 12/27/2023 Partial Approval SCOTT FINNILA
PLUMBING-Rough 12/27/2023 Approved SCOTT FINNILA
Underground Mechanical 12/27/2023 Partial Approval SCOTT FINNILA
BUILDING-Rough-Frame 1/2/2024 Partial Approval STUART CHAPMAN
Insulation 1/5/2024 Corrections Issued RONNIE MINDANAO
Excavation/Setback/Form/Re-Bar 1/9/2024 Approved ALIZAH MAYAGOITIA
Insulation 1/9/2024 Approved ALIZAH MAYAGOITIA
Interior/Exterior Lathing 1/9/2024 Partial Approval ALIZAH MAYAGOITIA
Drywall Nailing 1/11/2024 Corrections Issued RONNIE MINDANAO
BUILDING-Rough-Frame 1/17/2024 Partial Approval SCOTT FINNILA
Drywall Nailing 1/17/2024 Approved SCOTT FINNILA
Interior/Exterior Lathing 1/17/2024 Approved SCOTT FINNILA
BUILDING-Rough-Frame 2/16/2024 Approved STUART CHAPMAN
ELECTRICAL-Final 2/16/2024 Not Ready for Inspection STUART CHAPMAN
FLOOD-Proofing Certificate 2/16/2024 Approved STUART CHAPMAN
Final 2/16/2024 Corrections Issued STUART CHAPMAN
Footing/Foundation/Slab 2/16/2024 Approved STUART CHAPMAN
Gas Test 2/16/2024 Approved STUART CHAPMAN
HVAC-Final 2/16/2024 Not Ready for Inspection STUART CHAPMAN
PLUMBING-Final 2/16/2024 Approved STUART CHAPMAN
SGSOV-Seismic Gas S/O Valve 2/16/2024 SGSOV Approved STUART CHAPMAN
Service/Power Release 2/16/2024 Not Ready for Inspection STUART CHAPMAN
Smoke Detectors 2/16/2024 Approved STUART CHAPMAN
Service/Power Release 2/28/2024 Not Ready for Inspection STUART CHAPMAN
Service/Power Release 3/1/2024 Not Ready for Inspection JOSEPH MCGARRY
Final 3/19/2024 Corrections Issued STUART CHAPMAN
ELECTRICAL-Final 6/3/2024 Approved STUART CHAPMAN
Final 6/3/2024 OK to Issue CofO STUART CHAPMAN
HVAC-Final 6/3/2024 Approved STUART CHAPMAN
PLUMBING-Final 6/3/2024 Approved STUART CHAPMAN
Service/Power Release 7/8/2024 Approved STUART CHAPMAN