1814 E 109TH ST 90059
Certificate Information: 1814 E 109TH ST 90059
- Application / Permit
- 20014-10000-03587
- Plan Check / Job No.
- B20LA15121
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- NEW REAR ADDITION TO (E) SINGLE FAMILY DWELLING PER WOOD FRAME PRESCRIPTIVE PROVISIONS
- Permit Issued
- Issued on 1/12/2022
- Issuing Office
- Current Status
- CofO Issued on 7/9/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 8/24/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 8/26/2020 | FERNANDO FLORES |
| Corrections Issued | 8/26/2020 | FERNANDO FLORES |
| Building Plans Picked Up | 8/27/2020 | APPLICANT |
| Applicant returned to address corrections | 5/11/2021 | FERNANDO FLORES |
| Applicant returned to address corrections | 11/3/2021 | GEORGE ALVAREZ |
| Plan Check Approved | 11/8/2021 | GEORGE ALVAREZ |
| Issued | 1/12/2022 | APPLICANT |
| CofO in Progress | 6/27/2022 | ALIZAH MAYAGOITIA |
| Permit Finaled | 7/9/2022 | DEROLD HAUFF |
| CofO Issued | 7/9/2022 | DEROLD HAUFF |
| Permit Finaled | 7/9/2022 | DEROLD HAUFF |
Permit Application Clearance Information
| Roof/Waste drainage to street | Cleared | 2/24/2021 | JEANIE LAM |
| Eng Process Fee Ord 176,300 | Cleared | 3/5/2021 | RENZ SORIANO |
| Sewer availability | Cleared | 3/23/2021 | RENZ SORIANO |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| JOHN KLARIN, (310) 732-4558 | Office Hours: 7:00-8:00 AM MON-FRI |
| ARTHUR NEGRETE, (310) 732-4558 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 1/24/2022 | Conditional Approval | ALIZAH MAYAGOITIA |
| Footing/Foundation/Slab | 1/31/2022 | Approved | EUGENE CASSIDY |
| PLUMBING-Rough | 2/22/2022 | Partial Approval | JOHN KLARIN |
| Floor/Roof Diaphrgm/Shear Wall | 2/25/2022 | Not Ready for Inspection | JOHN KLARIN |
| Insulation | 2/25/2022 | Partial Approval | JOHN KLARIN |
| Floor/Roof Diaphrgm/Shear Wall | 3/1/2022 | Partial Approval | JOHN KLARIN |
| BUILDING-Rough-Frame | 4/1/2022 | Corrections Issued | ALIZAH MAYAGOITIA |
| ELECTRICAL-Rough | 4/1/2022 | Approved | ALIZAH MAYAGOITIA |
| Green Building Rough | 4/1/2022 | Not Ready for Inspection | ALIZAH MAYAGOITIA |
| HVAC-Rough | 4/1/2022 | Approved | ALIZAH MAYAGOITIA |
| PLUMBING-Rough | 4/1/2022 | Approved | ALIZAH MAYAGOITIA |
| Shower Pan | 4/1/2022 | Approved | ALIZAH MAYAGOITIA |
| BUILDING-Rough-Frame | 4/6/2022 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Green Building Rough | 4/6/2022 | Approved | ALEJANDRO DE ARTOLA |
| HVAC-Rough | 4/6/2022 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Interior/Exterior Lathing | 4/6/2022 | Corrections Issued | ALEJANDRO DE ARTOLA |
| BUILDING-Rough-Frame | 4/11/2022 | Approved | ALEJANDRO DE ARTOLA |
| Insulation | 4/11/2022 | Approved | ALEJANDRO DE ARTOLA |
| Drywall Nailing | 4/18/2022 | Approved | JOHN KLARIN |
| ELECTRICAL-Final | 6/14/2022 | Corrections Issued | JOHN KLARIN |
| Final | 6/14/2022 | Corrections Issued | JOHN KLARIN |
| Green Building Final | 6/14/2022 | Corrections Issued | JOHN KLARIN |
| HVAC-Final | 6/14/2022 | Approved | JOHN KLARIN |
| PLUMBING-Final | 6/14/2022 | Approved | JOHN KLARIN |
| SGSOV-Seismic Gas S/O Valve | 6/14/2022 | SGSOV Approved | JOHN KLARIN |
| Smoke Detectors | 6/14/2022 | Approved | JOHN KLARIN |
| ELECTRICAL-Final | 6/27/2022 | Approved | ALIZAH MAYAGOITIA |
| Final | 6/27/2022 | OK to Issue CofO | ALIZAH MAYAGOITIA |
| Green Building Final | 6/27/2022 | Approved | ALIZAH MAYAGOITIA |
| HVAC-Final | 6/27/2022 | Approved | ALIZAH MAYAGOITIA |
| PLUMBING-Final | 6/27/2022 | Approved | ALIZAH MAYAGOITIA |