2746 1/2 S THURMAN AVE 90016
Certificate Information: 2746 1/2 S THURMAN AVE 90016
- Application / Permit
- 20014-10000-03580
- Plan Check / Job No.
- B20LA15075
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- GARAGE CONVERSION TO ACCESSORY DWELLING UNIT AND ADDITION WITH ENGINEER DESIGN **update address pending boe clearance **methane
- Permit Issued
- Issued on 3/19/2021
- Issuing Office
- Current Status
- CofO Issued on 4/29/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 8/25/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 8/28/2020 | GEORGE ALVAREZ |
| Corrections Issued | 8/31/2020 | GEORGE ALVAREZ |
| Building Plans Picked Up | 9/2/2020 | APPLICANT |
| Applicant returned to address corrections | 3/12/2021 | SAMUEL GONZALEZ |
| Plan Check Approved | 3/17/2021 | SAMUEL GONZALEZ |
| Issued | 3/19/2021 | APPLICANT |
| CofO in Progress | 3/19/2024 | STUART CHAPMAN |
| Permit Finaled | 4/29/2024 | DEROLD HAUFF |
| CofO Issued | 4/29/2024 | DEROLD HAUFF |
| Permit Finaled | 4/29/2024 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 9/14/2020 | WALLIE JONG |
| Eng Process Fee Ord 176,300 | Cleared | 9/15/2020 | WALLIE JONG |
| Sewer availability | Cleared | 9/15/2020 | WALLIE JONG |
| Low Impact Development | Cleared | 2/26/2021 | JORGE MEJIA LEMUS |
| Roof/Waste drainage to street | Cleared | 3/2/2021 | CELINA MORENO |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Madero,, Fidencio; Lic. No.: C81695 | 10002 PANGBORN AVE DOWNEY, CA 90240 |
| Engineer | Nester,, Melvin Russell; Lic. No.: C26324 | 2902 TYLER CT SIMI VALLEY, CA 93063 |
Inspector Information
| DAVID WILLIAMS, (213) 202-3126 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 5/18/2021 | Conditional Approval | SCOTT FINNILA |
| Excavation/Setback/Form/Re-Bar | 6/30/2021 | Not Ready for Inspection | DAVID FEILER |
| METHANE-Barrier | 6/30/2021 | Corrections Issued | DAVID FEILER |
| Footing/Foundation/Slab | 7/14/2021 | Not Ready for Inspection | CHRISTOPHER DELLEFIELD |
| METHANE-Barrier | 7/14/2021 | Not Ready for Inspection | CHRISTOPHER DELLEFIELD |
| METHANE-Subgrade | 7/14/2021 | Corrections Issued | CHRISTOPHER DELLEFIELD |
| Excavation/Setback/Form/Re-Bar | 8/6/2021 | Approved | ALFREDO BALANDRA |
| Floor/Roof Diaphrgm/Shear Wall | 10/8/2021 | Approved | JUSTIN HAWLEY |
| ELECTRICAL-Rough | 3/21/2022 | Corrections Issued | JOSE AVILA |
| HVAC-Rough | 3/21/2022 | Not Ready for Inspection | JOSE AVILA |
| PLUMBING-Rough | 3/21/2022 | Corrections Issued | JOSE AVILA |
| ELECTRICAL-Rough | 4/5/2022 | Approved | JOSE AVILA |
| HVAC-Rough | 4/5/2022 | Corrections Issued | JOSE AVILA |
| PLUMBING-Rough | 4/5/2022 | Approved | JOSE AVILA |
| BUILDING-Rough-Frame | 5/23/2022 | Conditional Approval | JOSE AVILA |
| Green Building Rough | 5/23/2022 | Approved | JOSE AVILA |
| HVAC-Rough | 5/23/2022 | Order to Comply Issued | JOSE AVILA |
| METHANE-Rough | 5/23/2022 | Corrections Issued | JOSE AVILA |
| Wood Frame | 5/23/2022 | Conditional Approval | JOSE AVILA |
| Interior/Exterior Lathing | 6/28/2022 | Conditional Approval | JOSE AVILA |
| BUILDING-Rough-Frame | 10/25/2022 | Approved | JOSE AVILA |
| HVAC-Rough | 10/25/2022 | Approved | JOSE AVILA |
| METHANE-Rough | 10/25/2022 | Approved | JOSE AVILA |
| Insulation | 11/3/2022 | Approved | JOSE AVILA |
| Drywall Nailing | 11/29/2022 | Approved | JOSE AVILA |
| Sewer | 3/6/2023 | Corrections Issued | MICHAEL LEWIS |
| Sewer | 3/10/2023 | Approved | JOSE AVILA |
| Rough-Elec/Plmb/HVAC | 7/11/2023 | Not Ready for Inspection | STUART CHAPMAN |
| Underground Mechanical | 7/11/2023 | Approved | STUART CHAPMAN |
| Final | 10/17/2023 | Corrections Issued | JOSE AVILA |
| ELECTRICAL-Final | 12/27/2023 | Not Ready for Inspection | SCOTT FINNILA |
| PLUMBING-Final | 12/27/2023 | Not Ready for Inspection | SCOTT FINNILA |
| Final | 2/6/2024 | Corrections Issued | STUART CHAPMAN |
| Footing/Foundation/Slab | 2/6/2024 | Approved | STUART CHAPMAN |
| Green Building Final | 2/6/2024 | Approved | STUART CHAPMAN |
| METHANE-Barrier | 2/6/2024 | Approved | STUART CHAPMAN |
| METHANE-Subgrade | 2/6/2024 | Approved | STUART CHAPMAN |
| SGSOV-Seismic Gas S/O Valve | 2/6/2024 | SGSOV Approved | STUART CHAPMAN |
| Smoke Detectors | 2/6/2024 | Approved | STUART CHAPMAN |
| Final | 2/8/2024 | Corrections Issued | STUART CHAPMAN |
| ELECTRICAL-Final | 3/18/2024 | Approved | STUART CHAPMAN |
| Final | 3/18/2024 | OK to Issue CofO | STUART CHAPMAN |
| HVAC-Final | 3/18/2024 | Approved | STUART CHAPMAN |
| PLUMBING-Final | 3/18/2024 | Approved | STUART CHAPMAN |
| Service/Power Release | 4/11/2024 | Approved | STUART CHAPMAN |