1814 W MIDDLETON PL 90062
Certificate Information: 1814 W MIDDLETON PL 90062
- Application / Permit
- 20014-10000-03550
- Plan Check / Job No.
- B20LA14999
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- ADDITION AND CONVERT EXISTING GARAGE TO ADU PER 12.22 A33 C & D & PER WFPP
- Permit Issued
- Issued on 5/20/2021
- Issuing Office
- Current Status
- CofO Issued on 9/21/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 8/24/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 9/17/2020 | STARR CHEN |
| Corrections Issued | 9/25/2020 | STARR CHEN |
| Quality Review Completed | 10/7/2020 | HERNAN ARREOLA |
| Building Plans Picked Up | 10/13/2020 | APPLICANT |
| Applicant returned to address corrections | 2/25/2021 | STARR CHEN |
| Applicant returned to address corrections | 4/23/2021 | STARR CHEN |
| Plan Check Approved | 5/20/2021 | STARR CHEN |
| Issued | 5/20/2021 | APPLICANT |
| CofO in Progress | 9/14/2023 | SABAS ALONSO |
| Permit Finaled | 9/21/2023 | DEROLD HAUFF |
| CofO Issued | 9/21/2023 | DEROLD HAUFF |
| Permit Finaled | 9/21/2023 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 10/1/2020 | JUAN ASHTON |
| Eng Process Fee Ord 176,300 | Cleared | 10/5/2020 | JUAN ASHTON |
| Sewer availability | Cleared | 10/9/2020 | JUAN ASHTON |
| Hydrant and Access approval | Cleared | 12/3/2020 | MATTHEW CRAIG |
| Low Impact Development | Cleared | 12/28/2020 | JORGE MEJIA LEMUS |
| Roof/Waste drainage to street | Cleared | 2/25/2021 | JUAN ASHTON |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| SABAS ALONSO, (213) 202-3468 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 6/21/2021 | Not Ready for Inspection | DAVID FEILER |
| Footing/Foundation/Slab | 8/31/2021 | Approved | SABAS ALONSO |
| Floor/Roof Diaphrgm/Shear Wall | 9/29/2022 | Not Ready for Inspection | RYAN SALAZAR |
| ELECTRICAL-Rough | 11/10/2022 | Approved | SABAS ALONSO |
| HVAC-Rough | 11/10/2022 | Not Ready for Inspection | SABAS ALONSO |
| PLUMBING-Rough | 11/10/2022 | Corrections Issued | SABAS ALONSO |
| PLUMBING-Rough | 11/17/2022 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Insulation | 11/28/2022 | Partial Approval | HORACE FULTZ |
| Floor/Roof Diaphrgm/Shear Wall | 12/6/2022 | Approved | ALIZAH MAYAGOITIA |
| HVAC-Rough | 12/6/2022 | Approved | ALIZAH MAYAGOITIA |
| PLUMBING-Rough | 12/6/2022 | Approved | ALIZAH MAYAGOITIA |
| Floor/Roof Diaphrgm/Shear Wall | 12/9/2022 | Approved | SABAS ALONSO |
| BUILDING-Rough-Frame | 12/20/2022 | Approved | SABAS ALONSO |
| Green Building Rough | 12/20/2022 | Approved | SABAS ALONSO |
| Interior/Exterior Lathing | 12/20/2022 | Partial Approval | SABAS ALONSO |
| Insulation | 2/17/2023 | No Access for Inspection | LILIANA PORTILLO |
| Insulation | 2/23/2023 | Corrections Issued | SABAS ALONSO |
| Drywall Nailing | 3/15/2023 | Approved | ALEJANDRO DE ARTOLA |
| Shower Pan | 3/15/2023 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Shower Pan | 3/21/2023 | Corrections Issued | SABAS ALONSO |
| Shower Pan | 3/22/2023 | Approved | SABAS ALONSO |
| ELECTRICAL-Final | 8/2/2023 | Corrections Issued | SABAS ALONSO |
| Gas Test | 8/2/2023 | Approved | SABAS ALONSO |
| Final | 9/1/2023 | Corrections Issued | SABAS ALONSO |
| SGSOV-Seismic Gas S/O Valve | 9/1/2023 | SGSOV Approved | SABAS ALONSO |
| Smoke Detectors | 9/1/2023 | Approved | SABAS ALONSO |
| Final | 9/13/2023 | OK to Issue CofO | SABAS ALONSO |