12152 W HATTERAS ST 91607
Certificate Information: 12152 W HATTERAS ST 91607
- Application / Permit
- 20014-10000-03544
- Plan Check / Job No.
- B20LA14974
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- (N) 2-STORY ACCESSORY DWELLING UNIT ADDITION TO (E) GARAGE PER LAMC 12.22.A.33(c)-(d)
- Permit Issued
- Issued on 5/11/2021
- Issuing Office
- Current Status
- CofO Issued on 5/15/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 8/24/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 9/17/2020 | DANIEL YIP |
| Corrections Issued | 9/21/2020 | DANIEL YIP |
| Quality Review Completed | 10/9/2020 | ALLEN MANALANSAN |
| Applicant returned to address corrections | 12/16/2020 | DANIEL YIP |
| Building Plans Picked Up | 4/6/2021 | APPLICANT |
| Plan Check Approved | 4/15/2021 | DANIEL YIP |
| Issued | 5/11/2021 | APPLICANT |
| CofO in Progress | 5/3/2023 | KIRK SANDERS |
| Permit Finaled | 5/15/2023 | MICHAEL SMITH |
| CofO Issued | 5/15/2023 | MICHAEL SMITH |
| Permit Finaled | 5/15/2023 | MICHAEL SMITH |
Permit Application Clearance Information
| Construction within easement | Cleared | 2/2/2021 | RIDWAN HARDY |
| Low Impact Development | Cleared | 2/28/2021 | ORVAL HERNANDEZ-MARCI |
| Address approval | Cleared | 3/10/2021 | JOHN TRIANTAFYLLOS |
| Sewer availability | Cleared | 3/15/2021 | JOHN TRIANTAFYLLOS |
| Eng Process Fee Ord 176,300 | Cleared | 3/18/2021 | JOHN TRIANTAFYLLOS |
| Roof/Waste drainage to street | Cleared | 3/18/2021 | JOHN TRIANTAFYLLOS |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Alson,, Ken; Lic. No.: C41697 | 9744 MAPLE ST 201 BELLFLOWER, CA 90706 |
Inspector Information
| WAYNE REGESTER, (818) 374-1164 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 5/28/2021 | Partial Inspection | MICHAEL TEMPLE |
| Excavation/Setback/Form/Re-Bar | 11/15/2021 | Corrections Issued | CHRISTOPHE COCHRAN |
| Underground Mechanical | 11/15/2021 | Not Ready for Inspection | CHRISTOPHE COCHRAN |
| Excavation/Setback/Form/Re-Bar | 11/18/2021 | Corrections Issued | CHRISTOPHE COCHRAN |
| PLUMBING-Rough | 11/18/2021 | Partial Approval | CHRISTOPHE COCHRAN |
| Footing/Foundation/Slab | 11/24/2021 | Approved | DAVID MATSON |
| BUILDING-Rough-Frame | 1/31/2022 | Partial Approval | CHRISTOPHE COCHRAN |
| Green Building Rough | 1/31/2022 | Approved | CHRISTOPHE COCHRAN |
| Sewer | 2/2/2022 | Not Ready for Inspection | CHRISTOPHE COCHRAN |
| BUILDING-Rough-Frame | 2/9/2022 | Not Ready for Inspection | CHRISTOPHE COCHRAN |
| Floor/Roof Diaphrgm/Shear Wall | 2/9/2022 | Corrections Issued | CHRISTOPHE COCHRAN |
| Sewer | 2/9/2022 | Not Ready for Inspection | CHRISTOPHE COCHRAN |
| BUILDING-Rough-Frame | 2/24/2022 | Not Ready for Inspection | CHRISTOPHE COCHRAN |
| Floor/Roof Diaphrgm/Shear Wall | 2/24/2022 | Partial Approval | CHRISTOPHE COCHRAN |
| Sewer | 2/24/2022 | Partial Approval | CHRISTOPHE COCHRAN |
| BUILDING-Rough-Frame | 3/4/2022 | Partial Approval | CHRISTOPHE COCHRAN |
| Floor/Roof Diaphrgm/Shear Wall | 3/4/2022 | Approved | CHRISTOPHE COCHRAN |
| BUILDING-Rough-Frame | 4/26/2022 | Partial Approval | CHRISTOPHE COCHRAN |
| Gas Test | 4/26/2022 | Not Ready for Inspection | CHRISTOPHE COCHRAN |
| HVAC-Rough | 4/26/2022 | Not Ready for Inspection | CHRISTOPHE COCHRAN |
| PLUMBING-Rough | 4/26/2022 | Partial Inspection | CHRISTOPHE COCHRAN |
| Sewer | 4/26/2022 | Not Ready for Inspection | CHRISTOPHE COCHRAN |
| Underground Mechanical | 4/26/2022 | Corrections Issued | CHRISTOPHE COCHRAN |
| Sewer | 5/4/2022 | Approved | CHRISTOPHE COCHRAN |
| Underground Mechanical | 5/4/2022 | Approved | CHRISTOPHE COCHRAN |
| Interior/Exterior Lathing | 6/16/2022 | Approved | RAFAEL CORTES |
| Shower Pan | 6/29/2022 | Approved | HERBERT GIRON |
| ELECTRICAL-Rough | 8/5/2022 | Approved | RAFAEL CORTES |
| HVAC-Rough | 8/5/2022 | Approved | RAFAEL CORTES |
| PLUMBING-Rough | 8/5/2022 | Approved | RAFAEL CORTES |
| Rough-Elec/Plmb/HVAC | 8/5/2022 | Approved | RAFAEL CORTES |
| Insulation | 8/12/2022 | Approved | RAFAEL CORTES |
| Drywall Nailing | 10/11/2022 | Approved | ALAN MORELOS |
| Interior/Exterior Lathing | 10/11/2022 | Approved | ALAN MORELOS |
| Deputy Drilled-In Anchors | 11/3/2022 | Conditional Approval | MICHAEL SMITH |
| Deputy Steel/Welding | 11/23/2022 | Conditional Approval | ROBERT GOLD |
| BUILDING-Rough-Frame | 4/3/2023 | Approved | KIRK SANDERS |
| ELECTRICAL-Final | 4/3/2023 | Corrections Issued | KIRK SANDERS |
| Final | 4/3/2023 | Corrections Issued | KIRK SANDERS |
| Gas Test | 4/3/2023 | Approved | KIRK SANDERS |
| Green Building Final | 4/3/2023 | Not Ready for Inspection | KIRK SANDERS |
| HVAC-Final | 4/3/2023 | Corrections Issued | KIRK SANDERS |
| PLUMBING-Final | 4/3/2023 | Not Ready for Inspection | KIRK SANDERS |
| SGSOV-Seismic Gas S/O Valve | 4/3/2023 | SGSOV Not Ready | KIRK SANDERS |
| Smoke Detectors | 4/3/2023 | Approved | KIRK SANDERS |
| ELECTRICAL-Final | 4/10/2023 | Partial Approval | KIRK SANDERS |
| Final | 4/10/2023 | Partial Approval | KIRK SANDERS |
| Green Building Final | 4/10/2023 | Approved | KIRK SANDERS |
| HVAC-Final | 4/10/2023 | Approved | KIRK SANDERS |
| PLUMBING-Final | 4/10/2023 | Approved | KIRK SANDERS |
| SGSOV-Seismic Gas S/O Valve | 4/10/2023 | SGSOV Approved | KIRK SANDERS |
| Service/Power Release | 4/10/2023 | Not Ready for Inspection | KIRK SANDERS |
| ELECTRICAL-Final | 4/24/2023 | Approved | KIRK SANDERS |
| Final | 4/24/2023 | Corrections Issued | KIRK SANDERS |
| Service/Power Release | 4/24/2023 | Approved | KIRK SANDERS |
| Final | 5/2/2023 | OK to Issue CofO | KIRK SANDERS |