12152 W HATTERAS ST 91607

Certificate Information: 12152 W HATTERAS ST 91607

Application / Permit
20014-10000-03544
Plan Check / Job No.
B20LA14974
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
(N) 2-STORY ACCESSORY DWELLING UNIT ADDITION TO (E) GARAGE PER LAMC 12.22.A.33(c)-(d)
Permit Issued
Issued on 5/11/2021
Issuing Office
Current Status
CofO Issued on 5/15/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 8/24/2020 APPLICANT
Assigned to Plan Check Engineer 9/17/2020 DANIEL YIP
Corrections Issued 9/21/2020 DANIEL YIP
Quality Review Completed 10/9/2020 ALLEN MANALANSAN
Applicant returned to address corrections 12/16/2020 DANIEL YIP
Building Plans Picked Up 4/6/2021 APPLICANT
Plan Check Approved 4/15/2021 DANIEL YIP
Issued 5/11/2021 APPLICANT
CofO in Progress 5/3/2023 KIRK SANDERS
Permit Finaled 5/15/2023 MICHAEL SMITH
CofO Issued 5/15/2023 MICHAEL SMITH
Permit Finaled 5/15/2023 MICHAEL SMITH

Permit Application Clearance Information

Construction within easement Cleared 2/2/2021 RIDWAN HARDY
Low Impact Development Cleared 2/28/2021 ORVAL HERNANDEZ-MARCI
Address approval Cleared 3/10/2021 JOHN TRIANTAFYLLOS
Sewer availability Cleared 3/15/2021 JOHN TRIANTAFYLLOS
Eng Process Fee Ord 176,300 Cleared 3/18/2021 JOHN TRIANTAFYLLOS
Roof/Waste drainage to street Cleared 3/18/2021 JOHN TRIANTAFYLLOS

Contact Information

Contractor Owner-Builder       ,
Engineer Alson,, Ken; Lic. No.: C41697 9744 MAPLE ST 201      BELLFLOWER, CA 90706

Inspector Information

WAYNE REGESTER, (818) 374-1164 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 5/28/2021 Partial Inspection MICHAEL TEMPLE
Excavation/Setback/Form/Re-Bar 11/15/2021 Corrections Issued CHRISTOPHE COCHRAN
Underground Mechanical 11/15/2021 Not Ready for Inspection CHRISTOPHE COCHRAN
Excavation/Setback/Form/Re-Bar 11/18/2021 Corrections Issued CHRISTOPHE COCHRAN
PLUMBING-Rough 11/18/2021 Partial Approval CHRISTOPHE COCHRAN
Footing/Foundation/Slab 11/24/2021 Approved DAVID MATSON
BUILDING-Rough-Frame 1/31/2022 Partial Approval CHRISTOPHE COCHRAN
Green Building Rough 1/31/2022 Approved CHRISTOPHE COCHRAN
Sewer 2/2/2022 Not Ready for Inspection CHRISTOPHE COCHRAN
BUILDING-Rough-Frame 2/9/2022 Not Ready for Inspection CHRISTOPHE COCHRAN
Floor/Roof Diaphrgm/Shear Wall 2/9/2022 Corrections Issued CHRISTOPHE COCHRAN
Sewer 2/9/2022 Not Ready for Inspection CHRISTOPHE COCHRAN
BUILDING-Rough-Frame 2/24/2022 Not Ready for Inspection CHRISTOPHE COCHRAN
Floor/Roof Diaphrgm/Shear Wall 2/24/2022 Partial Approval CHRISTOPHE COCHRAN
Sewer 2/24/2022 Partial Approval CHRISTOPHE COCHRAN
BUILDING-Rough-Frame 3/4/2022 Partial Approval CHRISTOPHE COCHRAN
Floor/Roof Diaphrgm/Shear Wall 3/4/2022 Approved CHRISTOPHE COCHRAN
BUILDING-Rough-Frame 4/26/2022 Partial Approval CHRISTOPHE COCHRAN
Gas Test 4/26/2022 Not Ready for Inspection CHRISTOPHE COCHRAN
HVAC-Rough 4/26/2022 Not Ready for Inspection CHRISTOPHE COCHRAN
PLUMBING-Rough 4/26/2022 Partial Inspection CHRISTOPHE COCHRAN
Sewer 4/26/2022 Not Ready for Inspection CHRISTOPHE COCHRAN
Underground Mechanical 4/26/2022 Corrections Issued CHRISTOPHE COCHRAN
Sewer 5/4/2022 Approved CHRISTOPHE COCHRAN
Underground Mechanical 5/4/2022 Approved CHRISTOPHE COCHRAN
Interior/Exterior Lathing 6/16/2022 Approved RAFAEL CORTES
Shower Pan 6/29/2022 Approved HERBERT GIRON
ELECTRICAL-Rough 8/5/2022 Approved RAFAEL CORTES
HVAC-Rough 8/5/2022 Approved RAFAEL CORTES
PLUMBING-Rough 8/5/2022 Approved RAFAEL CORTES
Rough-Elec/Plmb/HVAC 8/5/2022 Approved RAFAEL CORTES
Insulation 8/12/2022 Approved RAFAEL CORTES
Drywall Nailing 10/11/2022 Approved ALAN MORELOS
Interior/Exterior Lathing 10/11/2022 Approved ALAN MORELOS
Deputy Drilled-In Anchors 11/3/2022 Conditional Approval MICHAEL SMITH
Deputy Steel/Welding 11/23/2022 Conditional Approval ROBERT GOLD
BUILDING-Rough-Frame 4/3/2023 Approved KIRK SANDERS
ELECTRICAL-Final 4/3/2023 Corrections Issued KIRK SANDERS
Final 4/3/2023 Corrections Issued KIRK SANDERS
Gas Test 4/3/2023 Approved KIRK SANDERS
Green Building Final 4/3/2023 Not Ready for Inspection KIRK SANDERS
HVAC-Final 4/3/2023 Corrections Issued KIRK SANDERS
PLUMBING-Final 4/3/2023 Not Ready for Inspection KIRK SANDERS
SGSOV-Seismic Gas S/O Valve 4/3/2023 SGSOV Not Ready KIRK SANDERS
Smoke Detectors 4/3/2023 Approved KIRK SANDERS
ELECTRICAL-Final 4/10/2023 Partial Approval KIRK SANDERS
Final 4/10/2023 Partial Approval KIRK SANDERS
Green Building Final 4/10/2023 Approved KIRK SANDERS
HVAC-Final 4/10/2023 Approved KIRK SANDERS
PLUMBING-Final 4/10/2023 Approved KIRK SANDERS
SGSOV-Seismic Gas S/O Valve 4/10/2023 SGSOV Approved KIRK SANDERS
Service/Power Release 4/10/2023 Not Ready for Inspection KIRK SANDERS
ELECTRICAL-Final 4/24/2023 Approved KIRK SANDERS
Final 4/24/2023 Corrections Issued KIRK SANDERS
Service/Power Release 4/24/2023 Approved KIRK SANDERS
Final 5/2/2023 OK to Issue CofO KIRK SANDERS