1111 W 65TH ST 90044
Certificate Information: 1111 W 65TH ST 90044
- Application / Permit
- 20014-10000-03502
- Plan Check / Job No.
- B20LA14836
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- PROPOSED ROOM ADDITION AT REAR OF EXISTING 1 STORY SINGLE FAMILY DEWLLING PER ENGINEER DESIGN
- Permit Issued
- Issued on 11/22/2021
- Issuing Office
- Metro
- Current Status
- Issued on 11/22/2021
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 2/12/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 2/18/2021 | AUNG SOE |
| Corrections Issued | 2/22/2021 | AUNG SOE |
| Plan Check Approved | 5/13/2021 | AUNG SOE |
| Issued | 11/22/2021 | APPLICANT |
| Building Plans Picked Up | 11/24/2021 | APPLICANT |
Permit Application Clearance Information
| Roof/Waste drainage to street | Cleared | 3/3/2021 | CECILIO NAVARRO |
| Sewer availability | Cleared | 3/3/2021 | CECILIO NAVARRO |
| Eng Process Fee Ord 176,300 | Cleared | 3/8/2021 | CECILIO NAVARRO |
Contact Information
| Contractor | James Terry R; Lic. No.: 572426-B | 6226 ACACIA ST LOS ANGELES, CA 90056 |
| Engineer | Cooke,, Conway Cecil; Lic. No.: S5524 | 34658 LINDA ROSEA RD TEMECULA, CA 92592 |
Inspector Information
| BARRY HACHE, (213) 202-9851 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 12/2/2021 | Approved | FREDDIE RIVERA |
| BUILDING-Rough-Frame | 12/14/2021 | Partial Approval | FREDDIE RIVERA |
| PLUMBING-Rough | 12/14/2021 | Partial Approval | FREDDIE RIVERA |
| ELECTRICAL-Rough | 1/20/2022 | Approved | ANTHONY EGSON |
| PLUMBING-Rough | 1/20/2022 | Approved | ANTHONY EGSON |
| Wood Frame | 1/20/2022 | Partial Approval | ANTHONY EGSON |
| Green Building Rough | 1/26/2022 | Approved | FREDDIE RIVERA |
| HVAC-Rough | 1/26/2022 | Approved | FREDDIE RIVERA |
| Wood Frame | 1/26/2022 | Approved | FREDDIE RIVERA |
| Insulation | 2/1/2022 | Approved | FREDDIE RIVERA |
| Drywall Nailing | 2/8/2022 | Approved | SHAVONNE ESPINOZA |
| Interior/Exterior Lathing | 2/8/2022 | Partial Approval | SHAVONNE ESPINOZA |
| BUILDING-Rough-Frame | 3/11/2022 | Approved | FREDDIE RIVERA |
| Final | 3/11/2022 | Corrections Issued | FREDDIE RIVERA |
| Green Building Final | 3/11/2022 | Approved | FREDDIE RIVERA |
| SGSOV-Seismic Gas S/O Valve | 3/11/2022 | SGSOV Not Ready | FREDDIE RIVERA |
| Smoke Detectors | 3/11/2022 | Approved | FREDDIE RIVERA |
| Final | 3/17/2022 | Corrections Issued | ENRIQUE MIRELES |
| SGSOV-Seismic Gas S/O Valve | 3/17/2022 | SGSOV Not Ready | ENRIQUE MIRELES |
| Final | 3/24/2022 | Corrections Issued | HORACE FULTZ |
| SGSOV-Seismic Gas S/O Valve | 3/24/2022 | SGSOV Approved | HORACE FULTZ |
| Final | 3/31/2022 | Corrections Issued | ENRIQUE MIRELES |