1111 W 65TH ST 90044

Certificate Information: 1111 W 65TH ST 90044

Application / Permit
20014-10000-03502
Plan Check / Job No.
B20LA14836
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
PROPOSED ROOM ADDITION AT REAR OF EXISTING 1 STORY SINGLE FAMILY DEWLLING PER ENGINEER DESIGN
Permit Issued
Issued on 11/22/2021
Issuing Office
Metro
Current Status
Issued on 11/22/2021
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 2/12/2021 APPLICANT
Assigned to Plan Check Engineer 2/18/2021 AUNG SOE
Corrections Issued 2/22/2021 AUNG SOE
Plan Check Approved 5/13/2021 AUNG SOE
Issued 11/22/2021 APPLICANT
Building Plans Picked Up 11/24/2021 APPLICANT

Permit Application Clearance Information

Roof/Waste drainage to street Cleared 3/3/2021 CECILIO NAVARRO
Sewer availability Cleared 3/3/2021 CECILIO NAVARRO
Eng Process Fee Ord 176,300 Cleared 3/8/2021 CECILIO NAVARRO

Contact Information

Contractor James Terry R; Lic. No.: 572426-B 6226 ACACIA ST      LOS ANGELES, CA 90056
Engineer Cooke,, Conway Cecil; Lic. No.: S5524 34658 LINDA ROSEA RD      TEMECULA, CA 92592

Inspector Information

BARRY HACHE, (213) 202-9851 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 12/2/2021 Approved FREDDIE RIVERA
BUILDING-Rough-Frame 12/14/2021 Partial Approval FREDDIE RIVERA
PLUMBING-Rough 12/14/2021 Partial Approval FREDDIE RIVERA
ELECTRICAL-Rough 1/20/2022 Approved ANTHONY EGSON
PLUMBING-Rough 1/20/2022 Approved ANTHONY EGSON
Wood Frame 1/20/2022 Partial Approval ANTHONY EGSON
Green Building Rough 1/26/2022 Approved FREDDIE RIVERA
HVAC-Rough 1/26/2022 Approved FREDDIE RIVERA
Wood Frame 1/26/2022 Approved FREDDIE RIVERA
Insulation 2/1/2022 Approved FREDDIE RIVERA
Drywall Nailing 2/8/2022 Approved SHAVONNE ESPINOZA
Interior/Exterior Lathing 2/8/2022 Partial Approval SHAVONNE ESPINOZA
BUILDING-Rough-Frame 3/11/2022 Approved FREDDIE RIVERA
Final 3/11/2022 Corrections Issued FREDDIE RIVERA
Green Building Final 3/11/2022 Approved FREDDIE RIVERA
SGSOV-Seismic Gas S/O Valve 3/11/2022 SGSOV Not Ready FREDDIE RIVERA
Smoke Detectors 3/11/2022 Approved FREDDIE RIVERA
Final 3/17/2022 Corrections Issued ENRIQUE MIRELES
SGSOV-Seismic Gas S/O Valve 3/17/2022 SGSOV Not Ready ENRIQUE MIRELES
Final 3/24/2022 Corrections Issued HORACE FULTZ
SGSOV-Seismic Gas S/O Valve 3/24/2022 SGSOV Approved HORACE FULTZ
Final 3/31/2022 Corrections Issued ENRIQUE MIRELES