127 W 118TH PL 90061

Certificate Information: 127 W 118TH PL 90061

Application / Permit
20014-10000-03470
Plan Check / Job No.
B20LA14677
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
500 SQ.FT. ADDITION TO EXISTING SFR. 1 OF 2
Permit Issued
Issued on 12/13/2021
Issuing Office
Current Status
CofO Issued on 5/10/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 8/17/2020 APPLICANT
Assigned to Plan Check Engineer 9/10/2020 CRYSTEL MAALOUF
Corrections Issued 10/6/2020 CRYSTEL MAALOUF
Quality Review Completed 10/26/2020 WING SUEN
Applicant returned to address corrections 4/8/2021 CRYSTEL MAALOUF
Applicant returned to address corrections 6/11/2021 CRYSTEL MAALOUF
Plan Check Approved 9/21/2021 CRYSTEL MAALOUF
Issued 12/13/2021 APPLICANT
Building Plans Picked Up 1/4/2022 APPLICANT
CofO in Progress 12/27/2022 JOHN KLARIN
Permit Finaled 5/10/2023 DANIEL ORRANTE
CofO Issued 5/10/2023 DANIEL ORRANTE
Permit Finaled 5/10/2023 DANIEL ORRANTE

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 12/15/2020 CECILIO NAVARRO
Low Impact Development Cleared 3/16/2021 JORGE MEJIA LEMUS
Sewer availability Cleared 5/3/2021 CECILIO NAVARRO
Roof/Waste drainage to street Cleared 9/21/2021 CECILIO NAVARRO

Contact Information

Contractor Amce Design Build; Lic. No.: 919611-B 8301 E FLORENCE AVE SUITE 205      DOWNEY, CA 90240
Engineer Espino,, Manuel A; Lic. No.: C55526 12109 WOODRUFF AVE      DOWNEY, CA 90241

Inspector Information

JOHN KLARIN, (310) 732-4558 Office Hours: 7:00-8:00 AM MON-FRI
ARTHUR NEGRETE, (310) 732-4558 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 1/6/2022 Corrections Issued EUGENE CASSIDY
Footing/Foundation/Slab 1/6/2022 Not Ready for Inspection EUGENE CASSIDY
PLUMBING-Rough 1/6/2022 Not Ready for Inspection EUGENE CASSIDY
Pre-Inspection 1/6/2022 Not Ready for Inspection EUGENE CASSIDY
Deputy Drilled-In Anchors 1/7/2022 Partial Approval EUGENE CASSIDY
ELECTRICAL-Rough 2/22/2022 Not Ready for Inspection JOHN KLARIN
Excavation/Setback/Form/Re-Bar 2/22/2022 Approved JOHN KLARIN
Footing/Foundation/Slab 2/22/2022 Approved JOHN KLARIN
Grounding or Bonding 2/22/2022 Not Ready for Inspection JOHN KLARIN
HVAC-Rough 2/22/2022 Not Ready for Inspection JOHN KLARIN
PLUMBING-Rough 2/22/2022 Partial Approval JOHN KLARIN
Floor/Roof Diaphrgm/Shear Wall 3/2/2022 Approved JOHN KLARIN
Floor/Roof Diaphrgm/Shear Wall 3/4/2022 Partial Approval JOHN KLARIN
Deputy Drilled-In Anchors 5/4/2022 Conditional Approval ALIZAH MAYAGOITIA
Floor/Roof Diaphrgm/Shear Wall 5/10/2022 Approved ALIZAH MAYAGOITIA
Rough-Elec/Plmb/HVAC 5/10/2022 Corrections Issued ALIZAH MAYAGOITIA
Wood Frame 5/10/2022 Approved ALIZAH MAYAGOITIA
Interior/Exterior Lathing 6/10/2022 Approved JOHN KLARIN
Insulation 6/17/2022 Approved JOHN KLARIN
Drywall Nailing 7/6/2022 Approved ALIZAH MAYAGOITIA
Service/Power Release 8/16/2022 Not Ready for Inspection JOHN KLARIN
Service/Power Release 8/18/2022 Not Ready for Inspection JOHN KLARIN
Service/Power Release 8/23/2022 Not Ready for Inspection EUGENE CASSIDY
Service/Power Release 8/26/2022 Corrections Issued JOHN KLARIN
Service/Power Release 8/30/2022 Corrections Issued RYAN SALAZAR
Service/Power Release 9/7/2022 Approved ALIZAH MAYAGOITIA
ELECTRICAL-Final 9/13/2022 Partial Approval ALIZAH MAYAGOITIA
Green Building Final 9/13/2022 Approved ALIZAH MAYAGOITIA
HVAC-Final 9/13/2022 Approved ALIZAH MAYAGOITIA
PLUMBING-Final 9/13/2022 Not Ready for Inspection ALIZAH MAYAGOITIA
Smoke Detectors 9/13/2022 Not Ready for Inspection ALIZAH MAYAGOITIA
ELECTRICAL-Final 9/29/2022 Not Ready for Inspection ALIZAH MAYAGOITIA
PLUMBING-Final 9/29/2022 Approved ALIZAH MAYAGOITIA
Smoke Detectors 9/29/2022 Approved ALIZAH MAYAGOITIA
BUILDING-Rough-Frame 9/30/2022 Approved ALIZAH MAYAGOITIA
ELECTRICAL-Final 9/30/2022 Partial Approval ALIZAH MAYAGOITIA
Final 9/30/2022 Not Ready for Inspection ALIZAH MAYAGOITIA
Green Building Rough 9/30/2022 Approved ALIZAH MAYAGOITIA
HVAC-Final 9/30/2022 Approved ALIZAH MAYAGOITIA
MERV13>=Final 9/30/2022 Approved ALIZAH MAYAGOITIA
MERV13>=Rough 9/30/2022 Approved ALIZAH MAYAGOITIA
PLUMBING-Final 9/30/2022 Approved ALIZAH MAYAGOITIA
SGSOV-Seismic Gas S/O Valve 9/30/2022 SGSOV Approved ALIZAH MAYAGOITIA
Smoke Detectors 9/30/2022 Approved ALIZAH MAYAGOITIA
ELECTRICAL-Final 12/23/2022 Approved JOHN KLARIN
Final 12/23/2022 OK to Issue CofO JOHN KLARIN
PLUMBING-Final 12/23/2022 Approved JOHN KLARIN