1760 S CARMELINA AVE 90025
Certificate Information: 1760 S CARMELINA AVE 90025
- Application / Permit
- 20014-10000-03456
- Plan Check / Job No.
- B20LA14640
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- 2 STORY GROUND FLOOR ADDITION TO EXISTING SFD
- Permit Issued
- Issued on 12/11/2020
- Issuing Office
- Current Status
- CofO Issued on 2/9/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 8/14/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 8/21/2020 | SERGIO GUTIERREZ |
| Corrections Issued | 8/25/2020 | SERGIO GUTIERREZ |
| Quality Review Completed | 9/2/2020 | KESETE HAREGOT |
| Building Plans Picked Up | 9/3/2020 | APPLICANT |
| Applicant returned to address corrections | 11/5/2020 | SERGIO GUTIERREZ |
| Plan Check Approved | 12/11/2020 | SERGIO GUTIERREZ |
| Issued | 12/11/2020 | APPLICANT |
| CofO in Progress | 2/9/2023 | DAVID FEILER |
| Permit Finaled | 2/9/2023 | DANIEL ORRANTE |
| CofO Issued | 2/9/2023 | DANIEL ORRANTE |
| Permit Finaled | 2/9/2023 | DANIEL ORRANTE |
Permit Application Clearance Information
| Sewer availability | Cleared | 9/4/2020 | DINAH GARIN |
| Eng Process Fee Ord 176,300 | Cleared | 9/10/2020 | DINAH GARIN |
| Specific Plan | Cleared | 9/16/2020 | RICHARD REASER |
| Hydrant and Access approval | Cleared | 9/30/2020 | KURT CORRAL |
| Specific Plan | Cleared | 10/19/2020 | PEDRO AYALA |
| Specific Plan | Cleared | 10/26/2020 | RICHARD REASER |
| Low Impact Development | Cleared | 12/3/2020 | ANDRES COVARRUBIAS |
| Roof/Waste drainage to street | Cleared | 12/9/2020 | DINAH GARIN |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Mohammadi,, Saeid; Lic. No.: C82330 | 17412 VENTUTRA BLVD 21 ENCINO, CA 91316 |
Inspector Information
| ANTHONY EGSON, (310) 914-3893 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 12/23/2020 | Partial Approval | OGANES TARAKHCHYAN |
| Footing/Foundation/Slab | 12/23/2020 | Partial Approval | OGANES TARAKHCHYAN |
| Floor/Roof Diaphrgm/Shear Wall | 2/16/2021 | Partial Approval | OGANES TARAKHCHYAN |
| Green Building Rough | 2/16/2021 | Not Ready for Inspection | OGANES TARAKHCHYAN |
| Floor/Roof Diaphrgm/Shear Wall | 2/22/2021 | Partial Approval | OGANES TARAKHCHYAN |
| Service/Power Release | 9/29/2021 | Approved | OGANES TARAKHCHYAN |
| Underground Mechanical | 9/29/2021 | Partial Approval | OGANES TARAKHCHYAN |
| Deputy Drilled-In Anchors | 9/30/2021 | Partial Approval | OGANES TARAKHCHYAN |
| Footing/Foundation/Slab | 10/6/2021 | Approved | OGANES TARAKHCHYAN |
| Deputy Drilled-In Anchors | 10/12/2021 | Partial Approval | OGANES TARAKHCHYAN |
| Deputy Reinf. Concrete | 10/12/2021 | Partial Approval | OGANES TARAKHCHYAN |
| Floor/Roof Diaphrgm/Shear Wall | 12/7/2021 | Partial Approval | OGANES TARAKHCHYAN |
| Deputy Drilled-In Anchors | 3/3/2022 | Partial Approval | OGANES TARAKHCHYAN |
| Deputy Wood Construction | 3/3/2022 | Partial Approval | OGANES TARAKHCHYAN |
| Floor/Roof Diaphrgm/Shear Wall | 3/3/2022 | Approved | OGANES TARAKHCHYAN |
| Special/Order Compliance | 3/3/2022 | Corrections Issued | OGANES TARAKHCHYAN |
| Deputy Drilled-In Anchors | 3/25/2022 | Approved | MICHAEL PELHAM |
| Footing/Foundation/Slab | 3/30/2022 | Approved | OGANES TARAKHCHYAN |
| Wood Frame | 4/8/2022 | Partial Approval | OGANES TARAKHCHYAN |
| Deputy Wood Construction | 5/24/2022 | Partial Approval | OGANES TARAKHCHYAN |
| Shower Pan | 6/7/2022 | Partial Approval | KENNETH NAGLE |
| ELECTRICAL-Rough | 6/30/2022 | Corrections Issued | OGANES TARAKHCHYAN |
| ELECTRICAL-Rough | 7/6/2022 | Corrections Issued | KENNETH NAGLE |
| PLUMBING-Final | 7/6/2022 | Corrections Issued | KENNETH NAGLE |
| PLUMBING-Rough | 7/6/2022 | Partial Approval | KENNETH NAGLE |
| Shower Pan | 7/6/2022 | Approved | KENNETH NAGLE |
| Enclosure/Fence | 7/8/2022 | Not Ready for Inspection | OGANES TARAKHCHYAN |
| Floor/Roof Diaphrgm/Shear Wall | 7/8/2022 | Not Ready for Inspection | OGANES TARAKHCHYAN |
| HVAC-Rough | 7/8/2022 | Not Ready for Inspection | OGANES TARAKHCHYAN |
| Special/Order Compliance | 7/12/2022 | Partial Inspection | MICHAEL PELHAM |
| BUILDING-Rough-Frame | 7/13/2022 | Conditional Approval | KENNETH NAGLE |
| ELECTRICAL-Rough | 7/13/2022 | Approved | KENNETH NAGLE |
| Green Building Rough | 7/13/2022 | Approved | KENNETH NAGLE |
| HVAC-Rough | 7/13/2022 | Approved | KENNETH NAGLE |
| PLUMBING-Rough | 7/13/2022 | Approved | KENNETH NAGLE |
| BUILDING-Rough-Frame | 7/20/2022 | Approved | MICHAEL PELHAM |
| Drywall Nailing | 7/20/2022 | Corrections Issued | MICHAEL PELHAM |
| Interior/Exterior Lathing | 7/22/2022 | Partial Approval | KENNETH NAGLE |
| Insulation | 7/28/2022 | Approved | KENNETH NAGLE |
| Drywall Nailing | 8/4/2022 | Approved | JOHN KIDWELL |
| HVAC-Final | 12/13/2022 | Corrections Issued | ASHLEY THOMPSON |
| PLUMBING-Final | 12/13/2022 | Approved | ASHLEY THOMPSON |
| ELECTRICAL-Final | 12/14/2022 | Corrections Issued | ASHLEY THOMPSON |
| HVAC-Final | 12/14/2022 | Approved | ASHLEY THOMPSON |
| ELECTRICAL-Final | 12/20/2022 | Approved | ASHLEY THOMPSON |
| Gas Test | 12/20/2022 | Approved | ASHLEY THOMPSON |
| Green Building Final | 12/20/2022 | Corrections Issued | ASHLEY THOMPSON |
| Smoke Detectors | 12/20/2022 | Approved | ASHLEY THOMPSON |
| Final | 1/17/2023 | Corrections Issued | CLAYTON GRAHAM |
| Green Building Final | 1/17/2023 | Approved | CLAYTON GRAHAM |
| SGSOV-Seismic Gas S/O Valve | 1/17/2023 | SGSOV Approved | CLAYTON GRAHAM |
| Final | 1/24/2023 | Corrections Issued | JULIAN AMAYA |
| Final | 2/1/2023 | OK to Issue CofO | DAVID FEILER |