15114 W ROXFORD ST 91342

Certificate Information: 15114 W ROXFORD ST 91342

Application / Permit
20014-10000-03452
Plan Check / Job No.
B20LA14615
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
(N) ADDITION TO (E) GARGAE AND CONVERT TO (N) ACCESSORY DWELLING UNTI PER LAMC 12.22 A.33 (c)-(d)
Permit Issued
Issued on 1/21/2021
Issuing Office
Current Status
CofO Issued on 1/25/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 8/14/2020 APPLICANT
Assigned to Plan Check Engineer 8/20/2020 DANIEL YIP
Corrections Issued 8/24/2020 DANIEL YIP
Quality Review Completed 10/1/2020 HERNAN ARREOLA
Building Plans Picked Up 10/9/2020 APPLICANT
Applicant returned to address corrections 10/29/2020 DANIEL YIP
Plan Check Approved 1/21/2021 DANIEL YIP
Issued 1/21/2021 APPLICANT
CofO in Progress 11/6/2023 KEVIN BERBERYAN
Permit Finaled 1/25/2024 RUBEN SALAS
CofO Issued 1/25/2024 RUBEN SALAS
Permit Finaled 1/25/2024 RUBEN SALAS

Permit Application Clearance Information

Hydrant and Access approval Cleared 11/17/2020 MATTHEW CRAIG
Address approval Cleared 11/18/2020 ADRIAN CASTRO
Sewer availability Cleared 11/18/2020 ADRIAN CASTRO
Eng Process Fee Ord 176,300 Cleared 11/19/2020 ADRIAN CASTRO
Low Impact Development Cleared 12/31/2020 JORGE MEJIA LEMUS
Roof/Waste drainage to street Cleared 1/5/2021 ADRIAN CASTRO

Contact Information

Contractor Owner-Builder       ,
Engineer , ; Lic. No.: C91046       ,

Inspector Information

KEVIN BERBERYAN, (818) 374-9931 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 4/28/2021 Not Ready for Inspection MISAEL ESPARZA
Gas Test 5/14/2021 Partial Approval MISAEL ESPARZA
SGSOV-Seismic Gas S/O Valve 5/14/2021 SGSOV Not Ready MISAEL ESPARZA
Sewer 5/14/2021 Corrections Issued MISAEL ESPARZA
Underground Mechanical 5/14/2021 Partial Approval MISAEL ESPARZA
Verify Rec and Parks Fee Memo 5/14/2021 Partial Inspection MISAEL ESPARZA
Gas Test 8/24/2021 Approved MISAEL ESPARZA
Sewer 8/24/2021 Partial Approval MISAEL ESPARZA
Underground Mechanical 8/24/2021 Partial Approval MISAEL ESPARZA
PLUMBING-Rough 9/2/2022 Partial Approval ARAM AVEDISIAN
Excavation/Setback/Form/Re-Bar 9/21/2022 Corrections Issued DEANDRE HOFFMAN
Excavation/Setback/Form/Re-Bar 9/23/2022 Approved ARAM AVEDISIAN
Floor/Roof Diaphrgm/Shear Wall 11/14/2022 Conditional Approval ARAM AVEDISIAN
ELECTRICAL-Rough 12/5/2022 Not Ready for Inspection ARAM AVEDISIAN
HVAC-Rough 12/5/2022 Not Ready for Inspection ARAM AVEDISIAN
PLUMBING-Rough 12/5/2022 Not Ready for Inspection ARAM AVEDISIAN
ELECTRICAL-Rough 12/13/2022 Approved ARAM AVEDISIAN
HVAC-Rough 12/13/2022 Approved ARAM AVEDISIAN
PLUMBING-Rough 12/13/2022 Approved ARAM AVEDISIAN
Deputy Wood Construction 12/15/2022 Conditional Approval ARAM AVEDISIAN
Floor/Roof Diaphrgm/Shear Wall 12/16/2022 Approved ARAM AVEDISIAN
BUILDING-Rough-Frame 12/22/2022 Conditional Approval ARAM AVEDISIAN
Interior/Exterior Lathing 12/22/2022 Partial Approval ARAM AVEDISIAN
BUILDING-Rough-Frame 12/30/2022 Approved ARAM AVEDISIAN
Green Building Rough 12/30/2022 Approved ARAM AVEDISIAN
Insulation 12/30/2022 Conditional Approval ARAM AVEDISIAN
Drywall Nailing 1/4/2023 Approved ARAM AVEDISIAN
Green Building Rough 1/4/2023 Approved ARAM AVEDISIAN
Insulation 1/4/2023 Approved ARAM AVEDISIAN
Interior/Exterior Lathing 1/18/2023 Not Ready for Inspection ARAM AVEDISIAN
Interior/Exterior Lathing 1/27/2023 Partial Approval WILLIAM WREN
Shower Pan 1/27/2023 Not Ready for Inspection WILLIAM WREN
Shower Pan 2/1/2023 Partial Approval JOHN COLEMAN
Interior/Exterior Lathing 2/6/2023 Partial Approval ARAM AVEDISIAN
Shower Pan 2/6/2023 Approved ARAM AVEDISIAN
ELECTRICAL-Final 8/1/2023 Corrections Issued MISAEL ESPARZA
Final 8/1/2023 Not Ready for Inspection MISAEL ESPARZA
Footing/Foundation/Slab 8/1/2023 Approved MISAEL ESPARZA
Green Building Final 8/1/2023 Not Ready for Inspection MISAEL ESPARZA
HVAC-Final 8/1/2023 Corrections Issued MISAEL ESPARZA
PLUMBING-Final 8/1/2023 Corrections Issued MISAEL ESPARZA
SGSOV-Seismic Gas S/O Valve 8/1/2023 SGSOV Not Ready MISAEL ESPARZA
Service/Power Release 8/1/2023 Not Ready for Inspection MISAEL ESPARZA
Smoke Detectors 8/1/2023 Corrections Issued MISAEL ESPARZA
ELECTRICAL-Final 8/9/2023 Partial Approval ROBERT GOLD
Final 8/9/2023 Not Ready for Inspection ROBERT GOLD
Green Building Final 8/9/2023 Approved ROBERT GOLD
HVAC-Final 8/9/2023 Corrections Issued ROBERT GOLD
PLUMBING-Final 8/9/2023 Partial Approval ROBERT GOLD
SGSOV-Seismic Gas S/O Valve 8/9/2023 SGSOV Approved ROBERT GOLD
Service/Power Release 8/9/2023 Not Ready for Inspection ROBERT GOLD
Smoke Detectors 8/9/2023 Approved ROBERT GOLD
ELECTRICAL-Final 8/16/2023 Approved ROBERT GOLD
Final 8/16/2023 Conditional Approval ROBERT GOLD
HVAC-Final 8/16/2023 Approved ROBERT GOLD
PLUMBING-Final 8/16/2023 Approved ROBERT GOLD
Service/Power Release 8/16/2023 Not Required ROBERT GOLD
Final 11/6/2023 OK to Issue CofO KEVIN BERBERYAN