3011 1/2 S 10TH AVE 90018
Certificate Information: 3011 1/2 S 10TH AVE 90018
- Application / Permit
- 20014-10000-03450
- Plan Check / Job No.
- B20LA14613
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- ADDITION TO GARAGE TO CREATE ADU. per LAMC 12.22 A.33(c) AND (d)
- Permit Issued
- Issued on 12/23/2020
- Issuing Office
- Current Status
- CofO Issued on 10/16/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 8/14/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 8/17/2020 | RICARDO RAMIREZ |
| Corrections Issued | 8/18/2020 | RICARDO RAMIREZ |
| Applicant returned to address corrections | 12/3/2020 | LUKE GONZALES |
| Plan Check Approved | 12/16/2020 | SAMUEL GONZALEZ |
| Building Plans Picked Up | 12/18/2020 | APPLICANT |
| Issued | 12/23/2020 | APPLICANT |
| CofO in Progress | 8/27/2021 | STUART CHAPMAN |
| Permit Finaled | 10/16/2021 | DEROLD HAUFF |
| CofO Issued | 10/16/2021 | DEROLD HAUFF |
| Permit Finaled | 10/16/2021 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 9/16/2020 | RENZ SORIANO |
| Eng Process Fee Ord 176,300 | Cleared | 9/16/2020 | RENZ SORIANO |
| Roof/Waste drainage to street | Cleared | 9/16/2020 | RENZ SORIANO |
| Sewer availability | Cleared | 9/17/2020 | RENZ SORIANO |
| Hydrant and Access approval | Cleared | 9/29/2020 | MATTHEW CRAIG |
| Construction near power lines | Cleared | 11/20/2020 | RIDWAN HARDY |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| JUSTIN HAWLEY, (213) 202-3432 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Floor/Roof Diaphrgm/Shear Wall | 2/23/2021 | Corrections Issued | STUART CHAPMAN |
| Deputy Drilled-In Anchors | 3/18/2021 | Conditional Approval | SABAS ALONSO |
| Wood Frame | 4/7/2021 | Partial Approval | KATHRYN BUTTERWORTH |
| ELECTRICAL-Rough | 4/12/2021 | Not Ready for Inspection | SABAS ALONSO |
| PLUMBING-Rough | 4/12/2021 | Not Ready for Inspection | SABAS ALONSO |
| ELECTRICAL-Rough | 4/14/2021 | Not Ready for Inspection | KATHRYN BUTTERWORTH |
| PLUMBING-Rough | 4/14/2021 | Not Ready for Inspection | KATHRYN BUTTERWORTH |
| ELECTRICAL-Rough | 5/13/2021 | Approved | STUART CHAPMAN |
| PLUMBING-Rough | 5/13/2021 | Partial Approval | STUART CHAPMAN |
| HVAC-Rough | 6/2/2021 | Approved | STUART CHAPMAN |
| Insulation | 6/2/2021 | Corrections Issued | STUART CHAPMAN |
| PLUMBING-Rough | 6/2/2021 | Approved | STUART CHAPMAN |
| Insulation | 6/8/2021 | Approved | STUART CHAPMAN |
| Floor/Roof Diaphrgm/Shear Wall | 6/17/2021 | Approved | KATHRYN BUTTERWORTH |
| Interior/Exterior Lathing | 6/30/2021 | Approved | STUART CHAPMAN |
| BUILDING-Rough-Frame | 8/13/2021 | Approved | STUART CHAPMAN |
| Final | 8/13/2021 | Corrections Issued | STUART CHAPMAN |
| Footing/Foundation/Slab | 8/13/2021 | Approved | STUART CHAPMAN |
| Green Building Final | 8/13/2021 | Approved | STUART CHAPMAN |
| Green Building Rough | 8/13/2021 | Approved | STUART CHAPMAN |
| SGSOV-Seismic Gas S/O Valve | 8/13/2021 | SGSOV Approved | STUART CHAPMAN |
| Smoke Detectors | 8/13/2021 | Approved | STUART CHAPMAN |
| ELECTRICAL-Final | 8/26/2021 | Approved | STUART CHAPMAN |
| Final | 8/26/2021 | OK to Issue CofO | STUART CHAPMAN |
| HVAC-Final | 8/26/2021 | Approved | STUART CHAPMAN |
| PLUMBING-Final | 8/26/2021 | Approved | STUART CHAPMAN |