2034 N CASTILIAN DR 90068

Certificate Information: 2034 N CASTILIAN DR 90068

Application / Permit
20014-10000-03442
Plan Check / Job No.
B20LA14579
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
INTERIOR & EXTERIOR REMODEL & ADD M-BATHROOM ON SECOND FLOOR, ENLARGE 1 BATHROOM, AND HALLWAY; REMODEL KITCHEN, DINING ROOM, BEDROOMS AND ALL BATHROOMS; REPLACE WINDOWS & DOORS TO EXISTING SFD
Permit Issued
Issued on 2/1/2021
Issuing Office
Valley
Current Status
CofO Issued on 12/7/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 8/13/2020 APPLICANT
Assigned to Plan Check Engineer 9/4/2020 SAM CHANG
Corrections Issued 9/16/2020 SAM CHANG
Quality Review Completed 9/18/2020 JASON HEALEY
Building Plans Picked Up 9/24/2020 APPLICANT
Applicant returned to address corrections 11/6/2020 SAM CHANG
Plan Check Approved 1/14/2021 SAM CHANG
Issued 2/1/2021 APPLICANT
CofO in Progress 6/22/2023 BRIAN SULLIVAN
Permit Finaled 12/7/2023 DEROLD HAUFF
CofO Issued 12/7/2023 DEROLD HAUFF
Permit Finaled 12/7/2023 DEROLD HAUFF

Permit Application Clearance Information

Grading Pre-Inspection Cleared 11/13/2020 SAM CHANG
CPC Cleared 11/25/2020 RICHARD REASER
Specific Plan Cleared 12/29/2020 DOMINICK ORTIZ
ZI Cleared 12/29/2020 DOMINICK ORTIZ

Contact Information

Contractor Owner-Builder       ,
Engineer Le,, Thang Huu; Lic. No.: S4978 507 MAGELLAN RD      ARCADIA, CA 91007

Inspector Information

ROY SPAULDING, (213) 202-3461 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 2/16/2021 Conditional Approval BRIAN SULLIVAN
Deputy Wood Construction 3/26/2021 Conditional Approval BRIAN SULLIVAN
BUILDING-Rough-Frame 4/8/2021 Partial Approval BRIAN SULLIVAN
Green Building Rough 4/8/2021 Not Ready for Inspection BRIAN SULLIVAN
ELECTRICAL-Rough 9/22/2021 Approved BRIAN SULLIVAN
Floor/Roof Diaphrgm/Shear Wall 9/22/2021 Partial Approval BRIAN SULLIVAN
Deputy Reinf. Concrete 11/22/2021 Conditional Approval BRIAN SULLIVAN
Shower Pan 11/24/2021 Approved BRIAN SULLIVAN
ELECTRICAL-Rough 11/29/2021 Approved BRIAN SULLIVAN
HVAC-Rough 11/29/2021 Corrections Issued BRIAN SULLIVAN
BUILDING-Rough-Frame 12/2/2021 Approved BRIAN SULLIVAN
Green Building Rough 12/2/2021 Approved BRIAN SULLIVAN
HVAC-Rough 12/2/2021 Approved BRIAN SULLIVAN
PLUMBING-Rough 12/2/2021 Approved BRIAN SULLIVAN
Interior/Exterior Lathing 12/17/2021 Partial Approval BRIAN SULLIVAN
Drywall Nailing 1/12/2022 Partial Approval BRIAN SULLIVAN
Final 4/5/2023 Corrections Issued BRIAN SULLIVAN
Final 6/21/2023 OK to Issue CofO BRIAN SULLIVAN
Footing/Foundation/Slab 6/21/2023 Approved BRIAN SULLIVAN
Green Building Final 6/21/2023 Approved BRIAN SULLIVAN
SGSOV-Seismic Gas S/O Valve 6/21/2023 SGSOV Approved BRIAN SULLIVAN
Smoke Detectors 6/21/2023 Approved BRIAN SULLIVAN