3830 S GRAYBURN AVE 90008

Certificate Information: 3830 S GRAYBURN AVE 90008

Application / Permit
20014-10000-03421
Plan Check / Job No.
B20LA14465
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
Ground floor addition to (E) SFD, including remodel of (E) SFD and new uncovered wood decks at rear and front
Permit Issued
Issued on 11/5/2020
Issuing Office
Current Status
CofO Issued on 7/27/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 8/12/2020 APPLICANT
Assigned to Plan Check Engineer 8/15/2020 HELEN NGUYEN
Corrections Issued 8/17/2020 HELEN NGUYEN
Applicant returned to address corrections 9/10/2020 SINA KHOSRAVI
Plan Check Approved 9/23/2020 SINA KHOSRAVI
Issued 11/5/2020 APPLICANT
Building Plans Picked Up 11/12/2020 APPLICANT
CofO in Progress 7/8/2021 FREDDIE RIVERA
Permit Finaled 7/27/2021 DEROLD HAUFF
CofO Issued 7/27/2021 DEROLD HAUFF
Permit Finaled 7/27/2021 DEROLD HAUFF

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 9/14/2020 JAMES KHO
Roof/Waste drainage to street Cleared 9/14/2020 JAMES KHO

Contact Information

Contractor Dino'S Construction And Home Repair; Lic. No.: 978695-B 2320 W HAVENBROOK STREET      WEST COVINA, CA 91790
Engineer Cheek,, Gary Albert; Lic. No.: C36253 PO BOX 216      MAYWOOD, CA 90270

Inspector Information

LUIS CASTRO, (213) 202-3436 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 11/12/2020 Partial Approval HORACE FULTZ
Footing/Foundation/Slab 11/12/2020 Partial Approval HORACE FULTZ
Floor/Roof Diaphrgm/Shear Wall 12/1/2020 Corrections Issued DAVID FEILER
Floor/Roof Diaphrgm/Shear Wall 12/4/2020 Partial Approval DAVID FEILER
PLUMBING-Rough 12/9/2020 Partial Approval DAVID FEILER
Special/Order Compliance 1/11/2021 Partial Inspection DAVID CHAN
Wood Frame 1/11/2021 Partial Approval DAVID CHAN
Wood Frame 1/25/2021 Corrections Issued DAVID FEILER
BUILDING-Rough-Frame 2/9/2021 Partial Inspection DAVID FEILER
ELECTRICAL-Rough 2/9/2021 Partial Inspection DAVID FEILER
Green Building Rough 2/9/2021 Not Ready for Inspection DAVID FEILER
HVAC-Rough 2/9/2021 Not Ready for Inspection DAVID FEILER
PLUMBING-Rough 2/9/2021 Not Ready for Inspection DAVID FEILER
BUILDING-Rough-Frame 2/12/2021 Partial Approval DAVID FEILER
ELECTRICAL-Rough 2/12/2021 Partial Approval DAVID FEILER
Green Building Rough 2/12/2021 Not Ready for Inspection DAVID FEILER
HVAC-Rough 2/12/2021 Partial Approval DAVID FEILER
PLUMBING-Rough 2/12/2021 Approved DAVID FEILER
BUILDING-Rough-Frame 2/22/2021 Conditional Approval DAVID FEILER
ELECTRICAL-Rough 2/22/2021 Approved DAVID FEILER
Green Building Rough 2/22/2021 Approved DAVID FEILER
HVAC-Rough 2/22/2021 Approved DAVID FEILER
BUILDING-Rough-Frame 3/1/2021 Approved DAVID FEILER
Insulation 3/1/2021 Approved DAVID FEILER
Interior/Exterior Lathing 3/1/2021 Partial Approval DAVID FEILER
Drywall Nailing 3/16/2021 Approved DAVID FEILER
Interior/Exterior Lathing 4/6/2021 Approved DAVID FEILER
Shower Pan 4/6/2021 Corrections Issued DAVID FEILER
Shower Pan 4/19/2021 Approved DAVID FEILER
Final 6/22/2021 Not Ready for Inspection JOAQUIN GREENOUGH
Footing/Foundation/Slab 6/22/2021 Approved JOAQUIN GREENOUGH
Green Building Final 6/22/2021 Approved JOAQUIN GREENOUGH
SGSOV-Seismic Gas S/O Valve 6/22/2021 SGSOV Not Ready JOAQUIN GREENOUGH
Smoke Detectors 6/22/2021 Corrections Issued JOAQUIN GREENOUGH
Final 6/29/2021 Corrections Issued FREDDIE RIVERA
SGSOV-Seismic Gas S/O Valve 6/29/2021 SGSOV Not Ready FREDDIE RIVERA
Smoke Detectors 6/29/2021 Approved FREDDIE RIVERA
Final 7/7/2021 OK to Issue CofO FREDDIE RIVERA
SGSOV-Seismic Gas S/O Valve 7/7/2021 SGSOV Approved FREDDIE RIVERA