16702 W MORRISON ST 91436

Certificate Information: 16702 W MORRISON ST 91436

Application / Permit
20014-10000-03420
Plan Check / Job No.
B20LA14464
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
ADD 15' x 15'-10" TO REAR OF (E) SFD TO EXPAND AND REMODEL (E) BEDROOM AND BTHRM.
Permit Issued
Issued on 1/20/2021
Issuing Office
Valley
Current Status
CofO Issued on 12/27/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 9/18/2020 APPLICANT
Assigned to Plan Check Engineer 9/25/2020 LAWRENCE QUIRANTE
Corrections Issued 9/26/2020 LAWRENCE QUIRANTE
Building Plans Picked Up 9/29/2020 APPLICANT
Applicant returned to address corrections 11/20/2020 RARES BODEA
Applicant returned to address corrections 12/11/2020 ANGELICA DAVE
Plan Check Approved 1/11/2021 ANGELICA MARTINEZ
Issued 1/20/2021 APPLICANT
CofO in Progress 12/27/2021 MICHAEL SMITH
Permit Finaled 12/27/2021 MICHAEL SMITH
CofO Issued 12/27/2021 MICHAEL SMITH
Permit Finaled 12/27/2021 MICHAEL SMITH

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 12/30/2020 ABDULLAH SADOZAI
Roof/Waste drainage to street Cleared 1/4/2021 ABDULLAH SADOZAI

Contact Information

Contractor Strong Ties Construction Inc; Lic. No.: 868377-B 767 N ALEXANDRIA AVENUE #3      LOS ANGELES, CA 90029

Inspector Information

THOMAS FINNILA, (818) 774-4324 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 2/4/2021 Approved RONALD COWAN
Footing/Foundation/Slab 2/5/2021 Approved RONALD COWAN
Floor/Roof Diaphrgm/Shear Wall 2/10/2021 Partial Approval RONALD COWAN
PLUMBING-Rough 2/10/2021 No Access for Inspection RONALD COWAN
Insulation 2/11/2021 Approved RONALD COWAN
Floor/Roof Diaphrgm/Shear Wall 2/12/2021 Approved RONALD COWAN
Floor/Roof Diaphrgm/Shear Wall 2/22/2021 Approved RONALD COWAN
BUILDING-Rough-Frame 3/1/2021 Corrections Issued RONALD COWAN
ELECTRICAL-Rough 3/1/2021 Approved RONALD COWAN
Green Building Rough 3/1/2021 Corrections Issued RONALD COWAN
HVAC-Rough 3/1/2021 Not Ready for Inspection RONALD COWAN
PLUMBING-Rough 3/1/2021 Approved RONALD COWAN
HVAC-Rough 3/16/2021 Approved RONALD COWAN
Insulation 3/16/2021 Corrections Issued RONALD COWAN
Interior/Exterior Lathing 3/16/2021 Not Ready for Inspection RONALD COWAN
Shower Pan 3/16/2021 Approved RONALD COWAN
BUILDING-Rough-Frame 4/7/2021 Approved RONALD COWAN
Green Building Rough 4/7/2021 Approved RONALD COWAN
PLUMBING-Rough 4/7/2021 Approved RONALD COWAN
Drywall Nailing 4/12/2021 Approved DAVID SCANTLIN
Interior/Exterior Lathing 4/12/2021 Partial Approval DAVID SCANTLIN
Drywall Nailing 4/14/2021 Approved DAVID SCANTLIN
Green Building Rough 4/14/2021 Approved DAVID SCANTLIN
ELECTRICAL-Final 5/25/2021 Approved RONALD COWAN
Final 5/25/2021 Not Ready for Inspection RONALD COWAN
Green Building Final 5/25/2021 Approved RONALD COWAN
HVAC-Final 5/25/2021 Approved RONALD COWAN
PLUMBING-Final 5/25/2021 Approved RONALD COWAN
SGSOV-Seismic Gas S/O Valve 5/25/2021 SGSOV Approved RONALD COWAN
Smoke Detectors 5/25/2021 Approved RONALD COWAN
Final 10/25/2021 Not Ready for Inspection PETER FOLLING
Final 11/18/2021 Conditional Approval ROBERT GOLD