1433 N OCCIDENTAL BLVD 90026
Certificate Information: 1433 N OCCIDENTAL BLVD 90026
- Application / Permit
- 20014-10000-03418
- Plan Check / Job No.
- B20LA14443
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- PROPOSED GROUND FLOOR ADDITION AND SECOND STORY ADDITION TO REAR OF EXISTING SINGLE FAMILY DWELLING, FIRST FLOOR WILL CREATE AN ATTACHED 2-CAR GARAGE, COVERED DECK, PORCH, AND COMPLETE INTRIOR REMODEL.SECOND FLOOR WILL CREATE 2 BERDROOMS, 2 BATHROOMS AND UNCOVERED DECK. ***NFPA 13 D SPRINKLERS REQUIRED***
- Permit Issued
- Issued on 3/18/2022
- Issuing Office
- Current Status
- CofO Issued on 12/30/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 8/12/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 9/4/2020 | MICHAEL LOPEZ |
| Corrections Issued | 9/10/2020 | MICHAEL LOPEZ |
| Quality Review Completed | 10/15/2020 | PRANITA SHAH |
| Applicant returned to address corrections | 9/9/2021 | MICHAEL LOPEZ |
| Applicant returned to address corrections | 11/3/2021 | MICHAEL LOPEZ |
| Applicant returned to address corrections | 11/4/2021 | MICHAEL LOPEZ |
| Plan Check Approved | 12/7/2021 | MICHAEL LOPEZ |
| Plan Check Approved | 3/8/2022 | MICHAEL LOPEZ |
| Plan Check Approved | 3/18/2022 | MICHAEL LOPEZ |
| Issued | 3/18/2022 | APPLICANT |
| Building Plans Picked Up | 3/21/2022 | APPLICANT |
| CofO in Progress | 12/27/2023 | THOMAS LOGRASSO |
| Permit Finaled | 12/30/2023 | DEROLD HAUFF |
| CofO Issued | 12/30/2023 | DEROLD HAUFF |
| Permit Finaled | 12/30/2023 | DEROLD HAUFF |
Permit Application Clearance Information
| Grading Pre-Inspection | Cleared | 11/20/2020 | BRIAN MILLER |
| Low Impact Development | Cleared | 4/27/2021 | ANDRES COVARRUBIAS |
| Roof/Waste drainage to street | Cleared | 5/24/2021 | WALLIE JONG |
| Eng Process Fee Ord 176,300 | Cleared | 6/7/2021 | WALLIE JONG |
| Sewer availability | Cleared | 7/14/2021 | WALLIE JONG |
| GPI Written Notices | Cleared | 12/7/2021 | ROBERT HUGHES |
Contact Information
| Contractor | Foothill Construction General Contractors Inc; Lic. No.: 879142-B | PO BOX 8534 LA CRESCENTA, CA 91224 |
| Engineer | Salto,, Alvaro; Lic. No.: C83859 | 7366 W MANCHESTER AVE #B LOS ANGELES, CA 90045 |
Inspector Information
| HAMIK HARTOUNIAN, (213) 202-3275 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 9/12/2022 | Approved | THOMAS LOGRASSO |
| Floor/Roof Diaphrgm/Shear Wall | 10/25/2022 | Partial Approval | THOMAS LOGRASSO |
| Gas Test | 10/25/2022 | Partial Approval | THOMAS LOGRASSO |
| Green Building Rough | 10/25/2022 | Not Ready for Inspection | THOMAS LOGRASSO |
| PLUMBING-Rough | 10/25/2022 | Partial Approval | THOMAS LOGRASSO |
| Floor/Roof Diaphrgm/Shear Wall | 1/24/2023 | Corrections Issued | THOMAS LOGRASSO |
| Floor/Roof Diaphrgm/Shear Wall | 2/24/2023 | Partial Approval | STUART CHAPMAN |
| BUILDING-Rough-Frame | 4/11/2023 | Not Ready for Inspection | THOMAS LOGRASSO |
| ELECTRICAL-Rough | 4/11/2023 | Corrections Issued | THOMAS LOGRASSO |
| Gas Test | 4/11/2023 | Partial Approval | THOMAS LOGRASSO |
| Green Building Rough | 4/11/2023 | Not Ready for Inspection | THOMAS LOGRASSO |
| HVAC-Rough | 4/11/2023 | Corrections Issued | THOMAS LOGRASSO |
| Interior/Exterior Lathing | 4/11/2023 | Not Ready for Inspection | THOMAS LOGRASSO |
| PLUMBING-Rough | 4/11/2023 | Approved | THOMAS LOGRASSO |
| BUILDING-Rough-Frame | 4/18/2023 | Approved | ALIZAH MAYAGOITIA |
| ELECTRICAL-Rough | 4/18/2023 | Approved | ALIZAH MAYAGOITIA |
| Footing/Foundation/Slab | 4/18/2023 | Approved | ALIZAH MAYAGOITIA |
| Green Building Rough | 4/18/2023 | Approved | ALIZAH MAYAGOITIA |
| HVAC-Rough | 4/18/2023 | Approved | ALIZAH MAYAGOITIA |
| Interior/Exterior Lathing | 4/18/2023 | Partial Approval | ALIZAH MAYAGOITIA |
| Insulation | 4/25/2023 | Approved | THOMAS LOGRASSO |
| Drywall Nailing | 5/10/2023 | Approved | THOMAS LOGRASSO |
| Shower Pan | 5/10/2023 | Approved | THOMAS LOGRASSO |
| Interior/Exterior Lathing | 5/31/2023 | Approved | THOMAS LOGRASSO |
| Underground Mechanical | 8/10/2023 | Partial Approval | THOMAS LOGRASSO |
| Underground Mechanical | 10/26/2023 | Corrections Issued | THOMAS LOGRASSO |
| Final | 12/19/2023 | Corrections Issued | THOMAS LOGRASSO |
| Green Building Final | 12/19/2023 | Not Ready for Inspection | THOMAS LOGRASSO |
| SGSOV-Seismic Gas S/O Valve | 12/19/2023 | SGSOV Approved | THOMAS LOGRASSO |
| Smoke Detectors | 12/19/2023 | Approved | THOMAS LOGRASSO |
| Final | 12/26/2023 | OK to Issue CofO | THOMAS LOGRASSO |
| Green Building Final | 12/26/2023 | Approved | THOMAS LOGRASSO |
| Service/Power Release | 12/26/2023 | Approved | THOMAS LOGRASSO |