731 W 112TH ST 90044
Certificate Information: 731 W 112TH ST 90044
- Application / Permit
- 20014-10000-03412
- Plan Check / Job No.
- B20LA14422
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- 1-STORY ADDITION TO (E) 1-STORY SFD
- Permit Issued
- Issued on 6/19/2022
- Issuing Office
- Current Status
- Issued on 6/19/2022
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 9/24/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 10/22/2020 | MAHNAZ NOURHASHEMI |
| Corrections Issued | 10/29/2020 | MAHNAZ NOURHASHEMI |
| Quality Review Completed | 11/10/2020 | TIEN JEN WANG |
| Applicant returned to address corrections | 5/4/2022 | MAHNAZ NOURHASHEMI |
| Plan Check Approved | 5/18/2022 | MAHNAZ NOURHASHEMI |
| Issued | 6/19/2022 | APPLICANT |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 8/12/2021 | WALLIE JONG |
| Low Impact Development | Cleared | 3/25/2022 | ANDRES COVARRUBIAS |
| Roof/Waste drainage to street | Cleared | 4/6/2022 | WALLIE JONG |
| Sewer availability | Cleared | 4/7/2022 | WALLIE JONG |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Chavez,, Eduardo; Lic. No.: C76372 | 437 ARCADIA WAY WALNUT, CA 91789 |
Inspector Information
| BEN MOLSTAD, (310) 732-4557 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 9/1/2022 | Corrections Issued | EUGENE CASSIDY |
| Footing/Foundation/Slab | 9/9/2022 | Approved | ALIZAH MAYAGOITIA |
| Wood Frame | 9/21/2022 | Partial Approval | EUGENE CASSIDY |
| PLUMBING-Rough | 9/27/2022 | Partial Approval | ALIZAH MAYAGOITIA |
| Floor/Roof Diaphrgm/Shear Wall | 9/29/2022 | Partial Approval | ALIZAH MAYAGOITIA |
| Wood Frame | 11/15/2022 | Partial Approval | JOHN KLARIN |
| Floor/Roof Diaphrgm/Shear Wall | 12/9/2022 | Approved | JAMES CHAVEZ |
| BUILDING-Rough-Frame | 2/13/2023 | Partial Inspection | JAMES CHAVEZ |
| Floor/Roof Diaphrgm/Shear Wall | 2/13/2023 | Approved | JAMES CHAVEZ |
| Rough-Elec/Plmb/HVAC | 4/3/2023 | Approved | JAMES CHAVEZ |
| BUILDING-Rough-Frame | 4/11/2023 | Approved | JAMES CHAVEZ |
| Green Building Rough | 4/11/2023 | Approved | JAMES CHAVEZ |
| Insulation | 4/17/2023 | Approved | JAMES CHAVEZ |
| Drywall Nailing | 4/24/2023 | Approved | JAMES CHAVEZ |
| Shower Pan | 2/1/2024 | Approved | JOHN KLARIN |
| Interior/Exterior Lathing | 3/26/2025 | Approved | BEN MOLSTAD |