1313 1/2-1/4 W 40TH PL 90037
Certificate Information: 1313 1/2-1/4 W 40TH PL 90037
- Application / Permit
- 20014-10000-03407
- Plan Check / Job No.
- B20LA14365
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CREATE 2 ADUs DETACHED ADUs PER MULTIPLE ADU STATE LAW GCS 65852.2(e)(1)(D)
- Permit Issued
- Issued on 5/13/2022
- Issuing Office
- Metro
- Current Status
- CofO Issued on 10/9/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 8/11/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 9/3/2020 | CARLOS MONTES |
| Corrections Issued | 10/9/2020 | CARLOS MONTES |
| Quality Review Completed | 10/21/2020 | WING SUEN |
| Building Plans Picked Up | 10/23/2020 | APPLICANT |
| Plan Check Approved | 3/25/2022 | CARLOS MONTES |
| Issued | 5/13/2022 | APPLICANT |
| CofO in Progress | 9/29/2023 | SABAS ALONSO |
| CofO Issued | 10/9/2023 | DEROLD HAUFF |
| Permit Finaled | 10/9/2023 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 9/30/2021 | CELINA MORENO |
| Eng Process Fee Ord 176,300 | Cleared | 10/5/2021 | CELINA MORENO |
| Sewer availability | Cleared | 10/5/2021 | CELINA MORENO |
| Low Impact Development | Cleared | 11/2/2021 | MITESH PATEL |
| Roof/Waste drainage to street | Cleared | 1/20/2022 | AMAAN MALIK |
| Hydrant and Access approval | Cleared | 3/4/2022 | DWAYNE LAURENT |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Espino,, Manuel A; Lic. No.: C55526 | 12109 WOODRUFF AVE DOWNEY, CA 90241 |
Inspector Information
| SABAS ALONSO, (213) 202-3468 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 9/28/2022 | Not Ready for Inspection | HORACE FULTZ |
| PLUMBING-Rough | 9/28/2022 | Partial Approval | HORACE FULTZ |
| PLUMBING-Rough | 9/30/2022 | Approved | SABAS ALONSO |
| Footing/Foundation/Slab | 10/4/2022 | Approved | SABAS ALONSO |
| Floor/Roof Diaphrgm/Shear Wall | 11/4/2022 | Partial Approval | SABAS ALONSO |
| ELECTRICAL-Rough | 2/15/2023 | Approved | SABAS ALONSO |
| Green Building Rough | 2/15/2023 | Approved | SABAS ALONSO |
| HVAC-Rough | 2/15/2023 | Approved | SABAS ALONSO |
| PLUMBING-Rough | 2/15/2023 | Approved | SABAS ALONSO |
| BUILDING-Rough-Frame | 2/24/2023 | Not Ready for Inspection | SABAS ALONSO |
| Interior/Exterior Lathing | 2/24/2023 | Not Ready for Inspection | SABAS ALONSO |
| Pre-Inspection | 2/24/2023 | Partial Inspection | SABAS ALONSO |
| Verify Sprinkler Sign Off | 2/24/2023 | Approved | SABAS ALONSO |
| Insulation | 3/7/2023 | Approved | STUART CHAPMAN |
| Interior/Exterior Lathing | 3/7/2023 | Approved | STUART CHAPMAN |
| Drywall Nailing | 3/14/2023 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Drywall Nailing | 5/12/2023 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Drywall Nailing | 6/5/2023 | Approved | SABAS ALONSO |
| Gas Test | 6/5/2023 | Approved | SABAS ALONSO |
| PLUMBING-Final | 6/5/2023 | Approved | SABAS ALONSO |
| BUILDING-Rough-Frame | 7/19/2023 | Approved | STUART CHAPMAN |
| Final | 7/19/2023 | Corrections Issued | STUART CHAPMAN |
| Green Building Final | 7/19/2023 | Approved | STUART CHAPMAN |
| SGSOV-Seismic Gas S/O Valve | 7/19/2023 | SGSOV Not Ready | STUART CHAPMAN |
| Service/Power Release | 7/19/2023 | Not Ready for Inspection | STUART CHAPMAN |
| Smoke Detectors | 7/19/2023 | Approved | STUART CHAPMAN |
| ELECTRICAL-Final | 9/15/2023 | Approved | SABAS ALONSO |
| Final | 9/15/2023 | Corrections Issued | SABAS ALONSO |
| SGSOV-Seismic Gas S/O Valve | 9/15/2023 | SGSOV Approved | SABAS ALONSO |
| Service/Power Release | 9/15/2023 | Not Ready for Inspection | SABAS ALONSO |
| Final | 9/19/2023 | Corrections Issued | SABAS ALONSO |
| Final | 9/28/2023 | OK to Issue CofO | SABAS ALONSO |
| Service/Power Release | 9/28/2023 | Approved | SABAS ALONSO |