4832 S 11TH AVE 90043
Certificate Information: 4832 S 11TH AVE 90043
- Application / Permit
- 20014-10000-03395
- Plan Check / Job No.
- B20LA14326
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- 650 SF GROUND FLOOR ADDITION TO (E) SFD
- Permit Issued
- Issued on 7/25/2022
- Issuing Office
- Metro
- Current Status
- CofO Issued on 7/9/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 8/12/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 8/12/2020 | AMIR DANAI |
| Corrections Issued | 8/13/2020 | AMIR DANAI |
| Applicant returned to address corrections | 11/27/2021 | SAMUEL GONZALEZ |
| Plan Check Approved | 4/21/2022 | JOSEPH RAFOLS |
| Building Plans Picked Up | 4/22/2022 | APPLICANT |
| Issued | 7/25/2022 | APPLICANT |
| CofO in Progress | 4/22/2024 | ANTHONY EGSON |
| CofO Issued | 7/9/2024 | DEROLD HAUFF |
| Permit Finaled | 7/9/2024 | DEROLD HAUFF |
Permit Application Clearance Information
| Sewer availability | Cleared | 2/4/2021 | RENZ SORIANO |
| Eng Process Fee Ord 176,300 | Cleared | 2/8/2021 | RENZ SORIANO |
| Low Impact Development | Cleared | 2/24/2021 | ORVAL HERNANDEZ-MARCI |
| Roof/Waste drainage to street | Cleared | 4/7/2021 | RENZ SORIANO |
| Green Code | Cleared | 4/21/2022 | AMIR DANAI |
Contact Information
| Contractor | Ballard Nick Construction; Lic. No.: 1010094-B | 8017 CRENSHAW BLVD INGLEWOOD, CA 90305 |
| Engineer | Stewart,, Carl William; Lic. No.: C86681 | 8811 GENTLE WIND DR CORONA, CA 92883 |
Inspector Information
| LUIS CASTRO, (213) 202-3436 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 12/16/2022 | Approved | ANTHONY EGSON |
| Footing/Foundation/Slab | 12/16/2022 | Approved | ANTHONY EGSON |
| Floor/Roof Diaphrgm/Shear Wall | 1/6/2023 | Partial Approval | MICHAEL LEWIS |
| Underground Mechanical | 1/6/2023 | Partial Approval | MICHAEL LEWIS |
| Insulation | 2/15/2023 | Partial Approval | BRENDAN MORELLI |
| ELECTRICAL-Rough | 2/24/2023 | Not Ready for Inspection | ANTHONY EGSON |
| Floor/Roof Diaphrgm/Shear Wall | 2/24/2023 | Partial Approval | ANTHONY EGSON |
| HVAC-Rough | 2/24/2023 | Not Ready for Inspection | ANTHONY EGSON |
| PLUMBING-Rough | 2/24/2023 | Not Ready for Inspection | ANTHONY EGSON |
| BUILDING-Rough-Frame | 4/25/2023 | Corrections Issued | ANTHONY EGSON |
| ELECTRICAL-Rough | 4/25/2023 | Not Ready for Inspection | ANTHONY EGSON |
| Green Building Rough | 4/25/2023 | Not Ready for Inspection | ANTHONY EGSON |
| HVAC-Rough | 4/25/2023 | Corrections Issued | ANTHONY EGSON |
| Interior/Exterior Lathing | 4/25/2023 | Approved | ANTHONY EGSON |
| PLUMBING-Rough | 4/25/2023 | Corrections Issued | ANTHONY EGSON |
| Rough-Elec/Plmb/HVAC | 4/27/2023 | Approved | ANTHONY EGSON |
| Insulation | 5/3/2023 | Approved | ANTHONY EGSON |
| Interior/Exterior Lathing | 5/3/2023 | Not Ready for Inspection | ANTHONY EGSON |
| Shower Pan | 5/3/2023 | Not Ready for Inspection | ANTHONY EGSON |
| Drywall Nailing | 5/17/2023 | Approved | ANTHONY EGSON |
| Interior/Exterior Lathing | 5/17/2023 | Not Ready for Inspection | ANTHONY EGSON |
| Shower Pan | 5/17/2023 | Corrections Issued | ANTHONY EGSON |
| Drywall Nailing | 5/19/2023 | Approved | ANTHONY EGSON |
| Shower Pan | 5/19/2023 | Approved | ANTHONY EGSON |
| Interior/Exterior Lathing | 6/5/2023 | Approved | ANTHONY EGSON |
| Interior/Exterior Lathing | 7/6/2023 | Approved | ANTHONY EGSON |
| Excavation/Setback/Form/Re-Bar | 2/2/2024 | Approved | ANTHONY EGSON |
| ELECTRICAL-Final | 4/1/2024 | Corrections Issued | ANTHONY EGSON |
| HVAC-Final | 4/1/2024 | Approved | ANTHONY EGSON |
| PLUMBING-Final | 4/1/2024 | Approved | ANTHONY EGSON |
| Deck | 4/3/2024 | Corrections Issued | ANTHONY EGSON |
| ELECTRICAL-Final | 4/3/2024 | Approved | ANTHONY EGSON |
| Deck | 4/8/2024 | Approved | ANTHONY EGSON |
| BUILDING-Rough-Frame | 4/18/2024 | Approved | ANTHONY EGSON |
| Final | 4/18/2024 | Not Ready for Inspection | ANTHONY EGSON |
| Green Building Final | 4/18/2024 | Not Ready for Inspection | ANTHONY EGSON |
| Green Building Rough | 4/18/2024 | Approved | ANTHONY EGSON |
| SGSOV-Seismic Gas S/O Valve | 4/18/2024 | SGSOV Approved | ANTHONY EGSON |
| Smoke Detectors | 4/18/2024 | Corrections Issued | ANTHONY EGSON |
| Final | 4/19/2024 | OK to Issue CofO | ANTHONY EGSON |
| Green Building Final | 4/19/2024 | Approved | ANTHONY EGSON |
| Smoke Detectors | 4/19/2024 | Approved | ANTHONY EGSON |