3506 E 3RD ST 90063
Certificate Information: 3506 E 3RD ST 90063
- Application / Permit
- 20014-10000-03390
- Plan Check / Job No.
- B20LA14306
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- 1 STORY ADDITION TO HOME 498.5 SQFT AND INTERIOR REMODEL, AND REMOVE UNPERMITTED CARPORT, STRUCTURE AND OPEN ALUMINUM PATIO "COMPLY WITH DEPARTMENT ORDER effective date 07/03/2020. PERMIT WILL EXPIRE 30 DAYS FROM ISSUANCE DATE".
- Permit Issued
- Issued on 12/19/2020
- Issuing Office
- Current Status
- Issued on 12/19/2020
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 8/14/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 8/15/2020 | RAHEL BEYENE |
| Corrections Issued | 8/21/2020 | RAHEL BEYENE |
| Applicant returned to address corrections | 9/22/2020 | ADAM HEGAZI |
| Applicant returned to address corrections | 10/13/2020 | ZAW HAN |
| Plan Check Approved | 11/18/2020 | ZAW HAN |
| Issued | 12/19/2020 | APPLICANT |
| Building Plans Picked Up | 12/30/2020 | APPLICANT |
Permit Application Clearance Information
| Hold | Cleared | 8/21/2020 | JASON SHEETS |
| Clean Up Green Up | Cleared | 8/27/2020 | RUBEN VASQUEZ |
| ZA Case | Cleared | 8/27/2020 | RUBEN VASQUEZ |
| Roof/Waste drainage to street | Cleared | 9/1/2020 | JEANIE LAM |
| Eng Process Fee Ord 176,300 | Cleared | 9/2/2020 | JEANIE LAM |
| Sewer availability | Cleared | 9/2/2020 | JEANIE LAM |
| Grading Pre-Inspection | Cleared | 9/11/2020 | KIRK LINKLATER |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Inman,, Donald J; Lic. No.: C11888 | 5131 FOX HILLS AVENUE BUENA PARK, CA 90621 |
Inspector Information
| DANIEL DELACRUZ, (323) 526-9348 | Office Hours: 7:00-8:00 AM MON-FRI |
| PEDRO SIERRA, (323) 526-9348 | Office Hours: 7:00-8:00 AM MON-FRI |
| ROBERT MINASSIANS, (323) 526-9348 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 1/28/2021 | Approved | JUAN ESCOTO DELGADO |
| BUILDING-Rough-Frame | 2/2/2021 | Corrections Issued | JUAN ESCOTO DELGADO |
| Green Building Rough | 2/2/2021 | Not Ready for Inspection | JUAN ESCOTO DELGADO |
| MERV13>=Rough | 2/2/2021 | Not Ready for Inspection | JUAN ESCOTO DELGADO |
| BUILDING-Rough-Frame | 2/5/2021 | Partial Approval | JUAN ESCOTO DELGADO |
| Green Building Rough | 2/5/2021 | Not Ready for Inspection | JUAN ESCOTO DELGADO |
| MERV13>=Rough | 2/5/2021 | Not Ready for Inspection | JUAN ESCOTO DELGADO |
| Insulation | 2/11/2021 | Partial Approval | JUAN ESCOTO DELGADO |
| Green Building Rough | 4/19/2021 | Approved | MARK VAN SLOOTEN |
| ELECTRICAL-Rough | 6/17/2021 | Corrections Issued | MARK VAN SLOOTEN |
| Insulation | 7/16/2021 | Approved | MARK VAN SLOOTEN |
| Drywall Nailing | 7/28/2021 | Approved | MARK VAN SLOOTEN |
| BUILDING-Rough-Frame | 5/11/2022 | Not Ready for Inspection | JUAN ESCOTO DELGADO |
| Final | 5/11/2022 | Not Ready for Inspection | JUAN ESCOTO DELGADO |
| Green Building Final | 5/11/2022 | Not Ready for Inspection | JUAN ESCOTO DELGADO |
| MERV13>=Final | 5/11/2022 | Not Ready for Inspection | JUAN ESCOTO DELGADO |
| MERV13>=Rough | 5/11/2022 | Not Ready for Inspection | JUAN ESCOTO DELGADO |
| SGSOV-Seismic Gas S/O Valve | 5/11/2022 | SGSOV Not Ready | JUAN ESCOTO DELGADO |
| Smoke Detectors | 5/11/2022 | Not Ready for Inspection | JUAN ESCOTO DELGADO |
| ELECTRICAL-Final | 4/8/2024 | Not Ready for Inspection | DANIEL DELACRUZ |
| ELECTRICAL-Rough | 4/8/2024 | Approved | DANIEL DELACRUZ |
| Final | 4/8/2024 | Not Ready for Inspection | DANIEL DELACRUZ |
| Green Building Final | 4/8/2024 | Corrections Issued | DANIEL DELACRUZ |
| HVAC-Final | 4/8/2024 | Not Ready for Inspection | DANIEL DELACRUZ |
| Interior/Exterior Lathing | 4/8/2024 | Not Ready for Inspection | DANIEL DELACRUZ |
| MERV13>=Rough | 4/8/2024 | Approved | DANIEL DELACRUZ |
| PLUMBING-Rough | 4/8/2024 | Approved | DANIEL DELACRUZ |
| SGSOV-Seismic Gas S/O Valve | 4/8/2024 | SGSOV Not Ready | DANIEL DELACRUZ |
| Smoke Detectors | 4/8/2024 | Approved | DANIEL DELACRUZ |
| BUILDING-Rough-Frame | 4/16/2024 | Approved | DANIEL DELACRUZ |